This document is a request for information from the Department of the Air Force Materiel Command Air Force Sustainment Center regarding the Hill AFB Multiple Award Construction Contract (MACC IV). The RFI seeks responses from potential sources by 23 October to assist in determining the acquisition strategy for the MACC IV, which will consist of multiple disciplines in design and construction services for facilities at Hill Air Force Base in Utah. During the life of the contract, projects will be identified as task orders and competed amongst contractors who receive a basic contract. Responses to the RFI questions and feedback on the statement of work are requested to facilitate decision making. An industry day will be held the week of 5-7 November at Hill AFB for presentations and one-on-one sessions. Each company may send a maximum of three attendees who must provide contact information to register by 23 October.
Questions
View the file
Other files for this federal contract opportunity
Show all 33
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| *Please limit responses to each question to a maximum of 200 words* |
| Multiple Award Contraction Contract IV (MACC IV) Request for Information (RFI) Question Matrix |
| What is your company’s bonding capacity? |
| What is your company’s experience complying with DOD standards including the Unified Facilities Criteria (see Whole Building Design Guide website at www.wbdg.org) when executing design build projects? |
| What is your experience managing complex, multimillion dollar industrial and/or aviation related projects for the Department of Defense and/or the Air Force that will be required for this contract? Examples could include but are not limited to work on aircraft hangars, manufacturing facilities, blast booths, paint booths, radar facilities, munitions facilities, facilities that include hazardous material industrial processes, complex infrastructure projects, airfield pavements or facilities, etc. |
| What is your experience managing complex commercial, office or base support type facility projects for the Department of Defense and/or the Air Force? |
| What is your experience working as a team with Architect/Engineer (A/E) design firms to successfully complete design build projects for the Department of Defense and/or the Air Force? |
| What is your experience performing projects at Hill AFB in Utah? |
| Is your company located within 100 miles of Hill AFB in Utah? |
| How many employees work for your company? |
| What A/E design firms have you partnered with in the past to complete successful design build projects? |
| Will you be bringing a representative or representatives from one of your A/E design partners with you to the planned Industry Day for this contract? This is highly encouraged. |