MACC IV IDIQ Industry Day Slides 20191016 Rev4.pptx

PPTX presentation 8 MB Posted

Attached to
Hill AFB Multiple Award Construction Contract (MACC IV)
Solicitation number
FA8201-20-D-MACC
Issued by

About this file

This document provides details for the Hill Air Force Base Multiple Award Construction Contract (MACC IV) opportunity. The Department of the Air Force Materiel Command Air Force Sustainment Center is seeking sources for the MACC IV to provide multiple disciplines in design and construction such as maintenance, repair, and alteration of real property, as well as new construction of facilities supported by Hill Air Force Base, Utah. During the life of the contract, projects will be identified as task orders and will be competed amongst successful contractors who receive a basic contract under the Design Build MACC IV. The NAICS code is 236220 Commercial and Institutional Building Construction with a size standard of $36.5M. The agency is interested in all small businesses including 8(a), Service-Disabled Veteran-Owned, HubZone, and Women-Owned small business concerns. The industry day will be held November 5-7, 2019 at Hill Air Force Base and responses to the sources sought notice are due by October 23, 2019.

View the file

Other files

File Type Posted
Attachment 02 - MACC IV Section L - 22 Sep 2020.docx DOCX document
Attachment 03 - MACC IV Section M - 22 Sep 2020.docx DOCX document
FA8201-20-R-0018 Draft RFP Q and A Matrix - 22 Sep 2020.xlsx XLSX spreadsheet
Attachment 01 - MACC IV - Basic SOW 22 Sep 2020.docx DOCX document
Attachment 03 - DRAFT MACC IV Section M - 18 Sep 2020.docx DOCX document
FA8201-20-R-0018 Draft RFP Q and A Matrix - 18 Sep 2020.xlsx XLSX spreadsheet
Attachment 02 - DRAFT MACC IV Section L - 18 Sep 2020.docx DOCX document
Attachment 04 - DRAFT TEP Matrix - 18 Sep 2020.xlsx XLSX spreadsheet
DRAFT Solicitation - FA820120R0018 - 18 Sep 2020.pdf PDF
Attachment 40 - Draft MACC IV PPI Tool.docx DOCX document
Attachment 02 - DRAFT MACC IV Section L - 9 Sep 2020.docx DOCX document
FA8201-20-R-0018 Draft RFP Q and A Matrix - 10 Sep 2020.xlsx XLSX spreadsheet
Attachment 03 - DRAFT MACC IV Section M - 9 Sep 2020.docx DOCX document
Attachment 01 - DRAFT MACC IV Basic SOW - 9 Sep 2020.docx DOCX document
FA8201-20-R-0018 Draft RFP Q and A Matrix.xlsx XLSX spreadsheet
Attachment 02 - DRAFT MACC IV Section L - 2 Sep 2020.docx DOCX document
Attachment 03 - DRAFT MACC IV Section M - 2 Sep 2020.docx DOCX document
DRAFT Solicitation 1 Sept 20 - FA820120R0018.pdf PDF
MACC IV - Consolidation DF - 20 AUG 2020_Redacted.pdf PDF
Attachment 01 - DRAFT MACC IV Basic SOW - 21 Aug 2020.docx DOCX document
Solicitation - FA820120R0018.pdf PDF
Attachment 39 - Wage Determination - Salt Lake County - 31 Jan 2020.pdf PDF
Attachment 36 - Wage Determination - Morgan-Weber Counties - 3 Jan 2020.pdf PDF
Attachment 37 - Wage Determination - Sublette County WY - 14 Jan 2020.pdf PDF
Attachment 04 - DRAFT TEP Matrix.xlsx XLSX spreadsheet
Attachment 05 - DRAFT MACC IV Sample Project SOW - 21 Aug 2020.docx DOCX document
Attachment 02 - DRAFT MACC IV Section L - 21 Aug 2020.docx DOCX document
Attachment 03 - DRAFT MACC IV Section M - 21 Aug 2020.docx DOCX document
Attachment 34 - Wage Determination - Box Elder County - 3 Jan 2020.pdf PDF
Attachment 35 - Wage Determination - Daggett-Duchesne-Rish-Summit Counties - 3 Jan 2020.pdf PDF
Attachment 38 - Wage Determination - Davis County - 3 Jan 2020.pdf PDF
Attachment_05_-_Basic_SOW_01_Oct_2019.pdf PDF
Question_Matrix.xlsx XLSX spreadsheet
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ogden Air Logistics Complex

Hill Air Force Base MACC IV Program Overview

Built Right, Ready to Fight

O G D E N A I R L O G I S T I C S C O M P L E X 75 CEG (Jim)

CLASSIFIED

MACC IV Overview UFC & Other Requirements Submittals Example Projects Safety Security Q & A – Open Discussions

PZ (TSgt Bedoya)

- The agenda for today’s industry day is as follows:

CLASSIFIED

Task Order (TO) USAF Requirements Air Force Design Guides (AFDG), Unified Facilities Criteria (UFC) and Engineering Technical Letters (ETL), found on: http://www.wbdg.org Regulations 10 CFR 435 Energy Conservation Voluntary Performance Standards for New Buildings (Mandatory for Federal Buildings) Energy Policy Act Air Force Instruction (AFI) AFI 32-10141, “Planning and Programming Fire Safety Deficiency Correction Projects”

CLASSIFIED

Task Order (TO) USAF Requirements Navigating to Design Criteria from www.wbdg.org

CLASSIFIED

TO Code Requirements References:

International Building Code International Mechanical Code International Plumbing Code International Energy Conservation Code International Fuel Gas Code Fire Safety Code, NFPA 1 Life Safety Code, National Fire Protection Association, NFPA 101 National Electric Code, NFPA 70 National Electric Safety Code, ANSI C2 Others as applicable to TO scope

Here are some examples of the code requirements that must be met on the MACC IV

CLASSIFIED

TO Standard Requirements References:

Base Facility Design Standard Base Architectural Compatibility Standard SCXP Telecommunications Installation Criteria for Facility Design and Renovation Air Installation Compatible Use Zone (AICUZ), Hill AFB, Amended April 1982 ASCE/SEI 7-05 Minimum Design Loads for Buildings and Other Structures ASHRAE Standard 62.1-2013, Ventilation for Acceptable Indoor Air Quality

Specific requirements for Hill AFB and geographically separated locations supported

CLASSIFIED

TO Standard Requirements (Con’t) References (Con’t):

ASHRAE Standard 90.1-2013, Energy Standard for Buildings Except Low Rise Residential Buildings Illuminating Engineering Society of North America, Reference and Application Lighting Handbook ICSSC RP6 - Standards of Seismic Safety for Existing Federally Owned and Leased Buildings Architectural Barriers Act (ABA) Accessibility Standard for Department of Defense Facilities Other standards as applicable

Specific requirements for Hill AFB and geographically separated locations supported

CLASSIFIED

Basis of Design (Design Analysis) Design Narrative Engineering Calculations Concept, 30%, 60%, 90%, 100% (Final) Drawings (w/ HAFB Title block) UFGS Specifications (Using SpecsIntact) Material and Equipment Cut Sheets Quality Control Plans Maintenance Plans Sub-Contracting Plans Project Schedules TO Design Submittals

75 CEG (Jim)

CLASSIFIED

TO Construction Submittals References:

Safety Plan Tailored to Task Order Material Submittals Progress Schedules and Reports Red Line/As-Built Drawings & Specifications AutoCAD, pdf, paper Test Reports Includes Test & Balance, Fire Suppression, Concrete Strength, etc.

Commissioning Report Independent Commissioning Contractor Maintenance Manuals Custom and Off the Shelf Transfer & Acceptance of DoD Real Property (DD Form1354) Others

CLASSIFIED

Example MACC Projects Example 1 - 388th & 419th FW B5 Bay J Renovation ~$2.3M Reconfiguration/Remodel of Existing Bldg Example 2 - B225 Repair High Bay for F-35 Program ~$5M Reconfiguration of Hangar for F-35 Maintenance Bays Example 3 - B507 Blast Booth Addition ~$1M Building Addition for New Blast Booth Equipment Example 4 - B341 Fire Alarm Replacement ~$350K Fire Alarm and Mass Notification System Example 5 - Little Mountain Substation Upgrade of Substation and Primary Distribution Example 6 - 388th Hanger B43 Renovation ~$5M Fire Suppression and Structural Upgrades Example 7 - 388th B120 Egress Project ~$2.8M Provide New Exterior Egress and Fire Protection

CLASSIFIED

Ex 1 - 388th & 419th FW B5 Bay J Renovation Design & Build of 19,250 SF for 388th & 419th FW Squadrons

75 CEG (Jim)

CLASSIFIED

Ex 1 - 388th & 419th FW B5 Bay J Renovation (Con’t) Project Facts:

Demolition & reconstruction of structure, HVAC, lighting, roofing, electrical, comm, ACS, IDS STC sound wall systems for briefing and mission planning spaces ALIS server room for F-35 mission support Modification of existing fire protection system Finishes including anti-static coating, carpet, ceramic tile, epoxy flooring, etc.

Major primary electrical distribution upgrade to support renovated spaces & existing adjacent spaces

75 CEG (Jim)

CLASSIFIED

Ex 2 - B225 Repair High Bay for F-35 Program Design & Build of 40,000 SF in Existing Hangar Facility

75 CEG (Jim)

CLASSIFIED

Ex 2 - B225 Repair High Bay for F-35 Program (Con’t) Project Facts:

Design of secure space for F-35 maintenance bays Demolition and reconfiguration of electrical distribution system Remove 3 existing C-130 work stands and install overhead crane to service 10 F-35 docks Installation of operator control consoles for aircraft systems testing New grounding system compliant with Lockheed specifications Plumb 10 docks for avionics air conditioning, hydraulic power, and DC power for aircraft

75 CEG (Jim)

CLASSIFIED

Design & Build 4200SF Addition onto an Existing Larger Process Building.

Ex 3 - B507 Blast Booth Addition

CLASSIFIED

Project Facts:

Evaluation of existing structure with adaptations for new addition Fire suppression and fire alarm system add-ons to existing larger systems Coordination and integration with blast booth equipment provider under a separate contract New ramps over existing waterways to roll up doors Adaptation of schedule due to differing site conditions

Ex 3 - B507 Blast Booth Addition (Con’t)

CLASSIFIED

Design & Build New Fire Alarm and Mass Notification System for a 3-Story Dormitory Building with 144 Resident Rooms

Ex 4 - B341 Fire Alarm Replacement

CLASSIFIED

Project Facts:

Maintained existing fire alarm system until the new system was fully operational and tested.

Addition of Mass Notification System to comply with current UFC/Air Force requirements Complete demolition and removal of previous system Coordination with Housing for supervised access to rooms for work

Ex 4 - B341 Fire Alarm Replacement (Con’t)

CLASSIFIED

Ex 5 - Little Mountain Substation Demolition and Upgrade of Substation and Primary Electrical Distribution System

CLASSIFIED

Ex 5 - Little Mountain Substation (Con’t) Project Facts:

Demolish old 4,160 volt electrical substation, feeders and distribution transformers Construct new 12KV substation with 5 MVA transformer, metering, voltage regulation, switchgear, capacitor bank, and 1MW emergency generator Construct new 12KV distribution system to include underground and overhead conductors, distribution transformers, distribution switches.

Construct new 480 volt and 120 volt secondary distribution

CLASSIFIED

Ex 6 - Hangar B43 Renovation Renovate ~ 22,000 SF fuel cell maintenance facility Complete architectural renovation of office space including new handicapped accessible restrooms and men’s/women’s locker room New structural steel upgrades to hold new hangar doors Replace existing fire suppression with high expansion foam Construct new lightning protection system

CLASSIFIED

Ex 7 - B120 Egress Project Design & Build to Remedy Egress Deficiencies in Existing Building

Ex 7 - B120 Egress Project (Con’t) Project Facts:

Provided new exterior egress stairway Added new automatic sprinkler system throughout the building Added code required interior fire separation for interior stairs Provided various exterior improvements Upgrades to provide ADA compliant access

Safety All Contractors Must Comply With OSHA Requirement - 29 CFR Part 1926 Safety and Health Regulations for Construction Hill AFB Specifications 01 35 26 Government Safety Requirements and Appendix C US Army Corps of Engineers - EM 385-1-1 Safety and Health Requirements Manual Safety Plan Tailored to Task Order Always provide required Personal Protective Equipment (PPE) Other Requirements

CLASSIFIED

Security Reference: IAW Hill Integrated Defense Plan HAFB Security requirements, including disqualifiers, is subject to change without prior notice Positive Access Control Unescorted Access Requirements Visitor Authorization List (VAL) Common Access Card (CAC) Defense Biometrics ID Sys (DBIDS) Criminal background history Access to Secure Areas Escorts Controlled Area Badges Free zone

CLASSIFIED

Security (Con’t) Disqualifiers Any felony involving any type of assault Any felony involving any type of arson Any felony involving any type of burglary or robbery Any felony involving possession or distribution of stolen property Any felony involving any type of willful destruction of property Any felony involving violence at an airport Any felony involving any type of threat or disruption to the public Any type of extortion or bribery Any type of theft, deception, fraud or falsehood Importation or manufacture of a controlled substance Distribution of or intent to distribute a controlled substance Illegal possession or use of a controlled substance Any conspiracy to commit any of the criminal acts listed above

Security (Con’t) Disqualifiers (Con’t) Espionage, sabotage, treason or terrorism Criminal homicide in all forms to include murder, manslaughter and/or negligent homicide Kidnapping, hostage taking, human trafficking / smuggling Mayhem Maiming Rape, forcible sodomy, sexual abuse or sexual assault Any sexual offense involving a minor or child including child molestation or child pornography Child abuse Any active want or warrant Any conspiracy to commit any of the above acts

Security (Con’t)

CLASSIFIED

Questions

Back to TSgt Bedoya

CLASSIFIED

image3.jpeg image4.jpeg image5.png image6.jpeg image7.jpg image8.png image9.jpeg image10.jpeg image11.jpeg image12.jpeg image13.jpeg image14.jpeg image15.jpeg image16.png image17.png image1.png image2.png

File details come from the government source that posted it. Updated .