This document contains a draft request for proposal (RFP) and related questions and answers for the Hill Air Force Base Multiple Award Construction Contract IV opportunity. The Air Force Materiel Command at Hill Air Force Base is seeking construction services from small businesses including 8(a), service-disabled veteran-owned, HubZone, and women-owned firms. The work will involve multiple disciplines in design and construction maintenance, repair, alteration, and new building projects at Hill Air Force Base. During the contract period, projects will be assigned as task orders competed among successful offerors. Responses to the draft RFP are due September 11, 2020. An industry day will be held November 5-7, 2020 at Hill Air Force Base to provide additional details and allow one-on-one meetings with potential offerors.
View the file
Other files for this federal contract opportunity
Show all 33
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Basic SOW
| MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC IV) FA8201-20-D-MACC Sept. 2020 | ||||
| Question # | Reference | Discussion | Question/Comment | Government Response |
Section L
| MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC IV) FA8201-20-D-MACC Sept. 2020 | ||||
| Question # | Reference | Discussion | Question/Comment | Government Response |
1 Section L, APPENDIX A: DOWNLOADING THE PPI TOOL Provide the link to the PPI tool mentioned in the Past Performance section of Attachment L of the RFP? This resource was not among the documents located in the DoD Safe site. The PPI tool has been uploaded to beta.SAM.gov. along with this Q&A Matrix.
Section M
| MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC IV) FA8201-20-D-MACC Sept. 2020 | ||||
| Question # | Reference | Discussion | Question/Comment | Government Response |
| 1 | Section M, 4.3 Subfactor 3: Contractor Requirements (b). | As this is a DRAFT Solicitation, would it be possible to extend the example project (Section M 4.3 Sub-factor 3: Contractor Requirements b) to less than (7) years old from (5) years old? This would allow us to use our past performance on the HAFB MACC III Contract. Can you provide this answer right away? | Yes, the DRAFT RFP contractor requirements will be updated in Sections L & M to "less than (7) years old" instead of (5) years old, and posted. |
| 2 | Section M, 4.3 Subfactor 3: Contractor Requirements (b). | If the design-build threshold of $5M can be reduced to $3M and two others at $1M or if we can remove the design-build and use bid build for project over $5M? |
These type of thresholds have not been seen before for small businesses. We have completed numerous design-build projects but lack the $5M plus design-build threshold as indicated in the solicitation. If for some reason this threshold cannot be changed and if we decide to propose would we be removed from competition for not meeting this threshold?
“Design-build experience as a Prime Contractor on military installations or design-build experience for both commercial aviation infrastructure within airport secured areas and industrial production facilities (see MACC IV SOW section 1.3.3) by submitting three (3) design-build example projects totaling at least $2M that were successfully completed. One project must be over $5M and the other two must be at least $2M.” It is necessary to keep the threshold of $5M due to the anticipated number of task orders expected to be at $5M or more. The current contract has task orders that have exceeded $5M and the number of these types of projects are expected to increase. The small business contractors on the current contract, have been able to compete for these high dollar task orders. In order to meet the criteria of Section M,4.3 (b), Offerors must be able to provide one (1) project over $5M. If Offerors are unable to provide this, they will not be able to meet the minimum criteria, and not eligible for award.
TEP
| MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC IV) FA8201-20-D-MACC Sept. 2020 | ||||
| Question # | Reference | Discussion | Question/Comment | Government Response |
Sample Task Order SOW
| MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC IV) FA8201-20-D-MACC Sept. 2020 | ||||
| Question # | Reference | Discussion | Question/Comment | Government Response |
Draft Solicitation
| MULTIPLE AWARD CONSTRUCTION CONTRACT (MACC IV) FA8201-20-D-MACC Sept. 2020 | ||||
| Question # | Reference | Discussion | Question/Comment | Government Response |
| 1 | Draft Solicitation | Since my company does teaming and subcontracting, do you have a list of Prime companies bidding? | The current prime contractors are: |
| HHI | |||
| E-Corp | |||
| RHI | |||
| Rio Vista | |||
| Gideon | |||
| Sahara Palms | |||
| 2 | Draft Solicitation | The web page on SAM says that this is a sources sought, but I’m seeing documentation that looks like it’s a solicitation. Is this opportunity actually a solicitation and not a sources sought opportunity? | This posting contains the DRAFT solicitation information. The way beta.SAM.gov is set up, it does not provide for a Request for Information (RFI) posting, so we have utilized the sources sought to post our DRAFT solicitation and receive Industry feedback. This is NOT the official solicitation. When we do move to the official solicitation it will be posted in beta.SAM.gov under the Solicitation posting option. |
| 3 | Draft Solicitation | Can you clarify if the RFP is still in draft form or if the notice contains the final and actual RFP? | This is the DRAFT solicitation/RFP posting. The Government intends to post the official solicitation/RFP later this fall. |
| 4 | Draft Solicitation | Based on the SF 1442 proposals are due on October 14, 2020. On Beta Sam it shows the response date as September 21, 2020. | Questions for the DRAFT RFP are due 11 Sept 2020. The date of 14 Oct has been replaced with "TBD". The due date in beta.sam has been updated to 11 Sept. 2020. |