This document is a Request for Information (RFI) Responses file for a federal electrical construction solicitation at Tinker Air Force Base.

Solicitation Details and Scope: Solicitation FA813726R0014, titled "WWYK240148-Install Electrical from FAB-T and OPCON, B820 & B829," is a Small Business Administration (SBA)-certified Women-Owned Small Business (WOSB) set-aside. The project involves installing electrical systems, including 200-amp and 100-amp disconnects in trailers, conduit installation (with welds required only under generator and generator pad), concrete pad construction under the new disconnect with specific reinforcement specifications, structural elements, and removal of a 100-gallon diesel fuel tank. The contract requires submission of a bid bond with proposals.

Key Technical Requirements and Clarifications: Hydrovac excavation is mandatory for all underground work due to extensive existing utilities. Contractors must bore under drives rather than saw cut and excavate across them. Conduits must be installed with each joint welded only under the generator and pad. The project is not tax-exempt; construction contracts do not qualify for sales tax exemption. Cell phones are allowed outside B820 but prohibited inside with no photographs permitted. The SOW paragraph 4.1.2 establishes the order of precedence for governing documents, with Tinker Specifications provided on the Contractor CD. All documentation, including specifications and Sections L and M (submission and evaluation criteria), are included as solicitation attachments. The government will empty the diesel fuel tank prior to removal and will not require OCC coordination closure reporting. No design requirements apply to this project, and ACM/LBP are assumed present during construction but have not been positively identified.

View the file

Other files

File Type Posted
Solicitation - FA813726R0014.pdf PDF
Solicitation- FA813726R00140001.pdf PDF
Sign In Sheet 3-31-26.pdf PDF
Sign In Sheet 3-25-26.pdf PDF
ATT8_240148_SOW_updated.pdf PDF
ATT9_240148_Submittal Register_Final.pdf PDF
ATT10_240148-Drawings_Final.pdf PDF
Wage Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation FA813726R0014

WWYK240148-Install Electrical from FAB-T and OPCON, B820 & B829

RFI Responses

1. Is this project tax exempt? If so, will the government provide a tax exempt form to the awarded contractor so that they may provide it to their subcontractors? This should be coordinated with your

Construction contracts are not sales tax exempt.-CS

2. Due to the extensive underground utilities and the need for Contractors to bid the same scope requirements, is the GOV requiring all Contractors to excavate by hydrovac instead of traditional excavator? Hydrovac is required. -DBS

3. Drawing E-102, Keynote 1, states to weld each joint. Are you wanting this conduit installed underground with each joint welded? Only the conduits under generator and generator pad. MBT

4. Drawing E-101, note 1 says to install new 200amp disconnect and Drawing E-501, note 1 says to install 100amp disconnect. What size disconnect needs to be installed in the B821 Trailer area? 200amp disconnect. The dra -MT

5. In order for Contractors to bid the same scope requirement, is the GOV allowing Contractors to saw cut and excavate across the drive for the new conduits then patch back, or are Contractors required to bore under the drive to install the conduits? There is trenching across the drive. Bore under the drive to install the conduits. MBT

6. Correct. -DBS

7. The SOW, paragraph 2.8, states that there is ACM and LBP present. Please provide a hazardous materials survey that shows the location and quantities so Contractors can accurately bid this scope. If a survey is not available, please identify an assumed quantity and location that all Contractors can bid so the abatement requirements is equal among all Contractors. The SOW only indicates the contractor not anticipated. -DBS

8. The GOV has provided drawings and SOW for Contractors to bid. Will the GOV provide scope of work: The Drawings or the SOW? The Tinker Specs are provided on your Contractor CD. SOW paragraph 4.1.2 clearly states the order of precedence. -DBS All documents from the Contractor CD are included as attachments to the solicitation. CS

9. Phones were not allowed to be taken into the jobsite area (behind the secure fence). Once awarded, will Contractor personnel be able to have company cell phones on them while supervising work? Phones were and are allowed outside of B820. No photos are allowed. -DBS

10.

a CD. We have not been given a CD, and none of these documents are posted on Sam.GOV. Will the GOV post these documents on Sam.GOV so Contractors can review? Contracting provides the Contractor CD. -DBS All documents from the Contractor CD are included as attachments to the solicitation. CS

RFI Responses

11. -aside to a SBA- This question should be -DBS This is a SBA- certified WOSB set-aside. CS

12.

criteria for proposals.

DBS. Sections L and M are included in the solicitation document. CS

13. Will a bid bond by required to submit with Contractor’s proposals? This should be coordinated with -DBS Yes, a bid bond will be required. CS

14.

Tinker -DBS Included in solicitation. CS

15.

requirements just from the submittal register. We ask for an provided so Contractors can review the specs completely, and if needed, can submit additional RFIs after the specs were provided.

determinatio -DBS Included in solicitation. CS

16. Drawing S-501, Detail 4, is the slab opening a “framed opening” with steel edges/lintels, or simply match slab. -LL

17. The structural drawings indicate enclosure posts, base plates, and anchors provided by others.

Equipment anchors will be installed with post-installed anchors by generator installers. -LL

18. -gal diesel fuel tank associated with the generator that will be removed, will be emptied of fuel by the GOV prior to Contractor demolishing/removing these items. Yes it will be emptied by the government. MBT

19.

requirement to coordinate closure report with OCC for the 100-gal diesel fuel tank. The OCC coordination will not be required. MBT

20. Drawing E-501, shows a new concrete pad being provided under the new disconnect. There is no detail on how this concrete pad is to be constructed. Please provide a detail, to include size, thickness, reinforcement, etc., and whether or not the new pad is to be dowelled into the adjacent/existing pad. Use thickness and reinforcing on keyed note #1/S-101 & detail 7/S-501. Dowel and epoxy into existing with #3x18” at 12” oc.-LL