This Design Narrative documents a project to replace the unit substation, switchgear, and associated electrical infrastructure at Tinker Air Force Base, Oklahoma. The project, located in Building 3001 at Column V51, involves demolishing the existing 12.47kV primary switchgear, 1000kVA transformer, and secondary side switchgear, and installing new equipment. Key electrical requirements include:
- Installing a new 3-phase/12.47kV/480V switchgear with 1600A main breaker and metering stations
- Replacing the 1000kVA transformer with a new unit equipped with a cooling fan
- Installing new 12.47kV and 600V cable runs
- Adding a remote-control cabinet and circuit breaker lifting hoist
- Performing electrical distribution coordination study and arc flash calculations
The project is scheduled for completion by June 3, 2025, with work to be coordinated to minimize disruption to base operations. Electrical demolition and installation will be phased, with power to be maintained through alternate substations during construction.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Design Narrative_v3_05/09/25
Design Narrative
REPLACE UNIT SUBSTATION & SWITCHGEAR, COL
V51, B3001
Project Number: WWYK140020 Work Order: 52142
Revision: 1
Tinker Air Force Base, Oklahoma
June 3, 2025
Prepared By:
Tepa Companies 7535 5th Street, Building 400
Tinker AFB, OK 73145
WWYK140020 - REPLACE UNIT SUBSTATION & SWITCHGEAR, COL V51, B3001
June 3, 2025 | i
CONTENTS
1. Overview
2. Applicable Codes and Standards
2.1 General
2.2 Civil
2.3 Architectural
2.4 Structural
2.5 Mechanical / Plumbing
2.6 Electrical
2.7 Fire Protection
3. Civil Design Narrative – N/A
4. Architectural Design Narrative
4.1 General Design Parameters and Assumptions
4.2 Architectural Demolition
4.3 Architectural Construction
5. Structural Design Narrative – N/A
6. Mechanical Design Narrative
6.1 Mechanical Demolition
6.2 Mechanical Construction
None, not applicable
7. Electrical Design Narrative
7.1 General Design Parameters and Assumptions
7.2 Electrical Demolition
7.3 Electrical Construction
8. Intrusion Detection System (IDS) Design Narrative – N/A
9. Access Control System (ACS) Design Narrative – N/A
10. Communications Design Narrative – N/A
11. Phasing Plan
APPENDICES
Appendix A: Acronyms and Abbreviations
Appendix B: Civil Calculations and Cutsheets
Appendix C: Architectural Calculations and Cutsheets
Appendix D: Structural Calculations and Cutsheets
Appendix E: Mechanical / Plumbing Calculations and Cutsheets
Appendix F: Electrical Calculations and Cutsheets
Appendix G: Fire Protection Calculations and Cutsheets ii | June 3, 2025
June 3, 2025 | 1
1. Overview The existing transformer located on a platform at post V51 in Building 3001 needs to be replaced.
The Mezzanine-level gear accompanying the transformer (primary switch and secondary side switchgear) has outlived its expected life expectancy and will be replaced along with the 600V feeder cables to the 480V busses. The primary cables feeding the transformer from the switch located at Post P53. shall be demolished and a new run of 12.47kV cable shall feed the new primary side switchgear via the V51 switch. Failure of this substation has removed redundant capacity for this part of Building 3001. A second means of egress will also have to be installed, likely on the South-West side of the platform, but final location shall be coordinated with User.
2. Applicable Codes and Standards
2.1 General
ICD/ICS 705 Technical Specifications for Construction and Management of Sensitive Compartmented Information Facilities
IBC International Building Code (as amended by UFC 1-200-01) IEBC International Existing Building Code NFPA 101 Life Safety Code TAFB Facility Standard UFC 1-200-01 DoD Building Code UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings UFC 4-010-05 Sensitive Compartmented Information Facilities Planning, Design, and Construction
2.2 Civil
FAA Advisory Circular 150/5340-1L BASH Manual UFC 3-201-01 Civil Engineering UFC 3-230-01 Water Storage, Distribution, and Transmission UFC 3-250-01 Pavement Design for Roads and Parking Areas UFC 3-260-01 Airfield and Heliport Planning and Design UFC 3-260-02 Pavement Design for Airfields UFC 3-260-04 Airfield and Heliport Marking UFC 4-022-02 Security Fences and Gates
2.3 Architectural
ABA Architectural Barriers Act Standards UFAS Uniform Federal Accessibility Standards UFC 3-101-01 Architecture UFC 3-110-03 Roofing
2 | June 3, 2025
UFC 3-120-10 Interior Design UFC 3-190-06 Protective Coatings and Paints OSHA 1910.29(b) Guard Rail Systems OSHA 1910.29(b)(13) Swing gates OSHA 1917.112 Toe Boards OSHA 1917.118(d) Fixed Ladder Specifications UFC 3-201-02 Landscape Architecture
2.4 Structural
ACI 318-14 Building Code Requirements for Structural Concrete and Commentary
AISC 360-10 Steel Construction Manual, 14th Ed.
ASCE 7-10 Minimum Design Loads for Building and other Structures AISI S100-12 North American Specification for the Design of Cold-formed
Steel Structural Members UFC 3-301-01 Structural Engineering UFC 3-310-01 Seismic Design of Buildings
2.5 Mechanical / Plumbing
ANSI/ASHRAE/ Peak Cooling and Heating Load Calculations in Buildings Except ACCA Standard 183 Low-Rise Residential Buildings ASHRAE 55 Thermal Environmental Conditions for Human Occupancy ASHRAE 62.1 Ventilation for Acceptable Indoor Air Quality ASHRAE 90.1 Energy Standard for Buildings Except Low-Rise Residential
Buildings IECC International Energy Conservation Code IMC International Mechanical Code (as amended by UFC 3-410-01) IPC International Plumbing Code (as amended by UFC 3-420-01) TAFB Mechanical Standard UFC 1-200-02 High Performance and Sustainable Building Requirements UFC 3-400-02 Design: Engineering Weather Data UFC 3-401-01 Mechanical Engineering UFC 3-410-01 Heating, Ventilating, and Air Conditioning Systems UFC 3-410-02 Direct Digital Control for HVAC and Other Building Control
Systems UFC 3-410-04 Industrial Ventilation UFC 3-420-01 Plumbing Systems UFC 3-430-01FA Heating and Cooling Distribution Systems UFC 3-450-01 Noise and Vibration Control
June 3, 2025 | 3
2.6 Electrical
ASHRAE 90.1 Energy Standard for Buildings Except Low-Rise Residential Buildings
NFPA 70 National Electrical Code NFPA 780 Standard for Installation of Lightning Protection Systems TAFB Electrical Standard UFC 3-501-01 Electrical Engineering UFC 3-520-01 Interior Electrical Systems UFC 3-530-01 Interior and Exterior Lighting Systems and Controls UFC 3-575-01 Lightning and Static Electricity Protection Systems AFMAN 32-1065 Grounding and Electrical Systems
2.7 Fire Protection
NFPA 1 Fire Code NFPA 10 Standard for Portable Fire Extinguishers NFPA 13 Standard for the Installation of Sprinkler Systems NFPA 51B Standard for Fire Prevention during Welding, Cutting, and Other
Hot Work NFPA 70 National Electric Code NFPA 72 National Fire Alarm Code NFPA 90A Standard for the Installation of Air-Conditioning and Ventilation
Systems NFPA 241 Standard for Safeguarding Construction, Alteration, and
Demolition Operations TAFB Fire Protection Standard DAFI 32-2001 Fire and Emergency Services (F&ES) Program UFC 3-600-01 Fire Protection Engineering for Facilities UFC 3-601-02 Operation and Maintenance: Inspection, Testing and
Maintenance of Fire Protection Systems UFC 4-021-01 Design and O&M: Mass Notification Systems
4 | June 3, 2025
3. Civil Design Narrative – N/A
4. Architectural Design Narrative The architectural requirements include removal, modification and reinstallation of guardrails from the receiver sleeves at the platform to accommodate the removal and installation of electrical and mechanical equipment. Ladders and handrails are to be painted and where mechanical items are removed, structural items are to be touched up with paint to match existing painted elements. The platform requires 2 fixed ladders to service the platform, one at the northwest corner on the west side of the platform and one on the southwest corner of the platform on the east side of the platform. There is an existing ladder on the west side of the platform. The ladder and all new ladders shall meet all requirements of current codes, base standards and regulations. The existing ladder is to be inspected for code compliance. Both ladders shall have a safety gate and a landing platform. Toe kick plates are to be installed between the guardrail receivers, with exception of the ladder opening locations. All ladders, guard rails and safety gates are to have a Safety Yellow finish. Barriers are to be installed to contain FOD and protect the area below and around the platform.
4.1 General Design Parameters and Assumptions
4.2 Architectural Demolition
4.2.1 To accommodate removal of the existing switchgear/associated transformer section equipment and installation of the new switchgear/associated transformer section, remove the existing guard rails along the east side of the platform. Store removed guardrails on-site for reinstallation. Guardrail receiver sleeves shall remain in place. At the south end, on the east side of the platform, modify the guard rail to accommodate access to a new ladder system down to the main floor.
4.3 Architectural Construction
4.3.1. Designer of Record shall verify all field dimensions.
4.3.2. Barriers are to be installed to contain FOD and protect the area below and around the platform.
4.3.3. After placement of the new switchgear & associated transformer Section on the platform, reinstall guard rails.
4.3.4. At the south end, on the east side of the platform, modify the guard rail to accommodate access to a new ladder system down to the main floor. Attach the remaining southeast corner post to the guard rail along the south side of the platform with new top and mid rails.
4.3.5. At the existing ladder on the west side of the platform inspect the ladder for code compliance. Both ladders shall have a safety gate and a landing platform and shall meet all requirements of current codes, base standards and regulations.
4.3.6. Install new safety gates at each platform ladder opening. Openings on platforms are regulated by OSHA paragraphs of §1910.23. OSHA paragraph §1910.23(a) covers floor openings, including access openings at the edge of a platform. The governing requirement is OSHA 1910.23(a)(2).
June 3, 2025 | 5
4.3.7. Install new steel “Toe Boards” between the guardrail receivers per OSHA 1917.122(d) at perimeter of platform for the full length of the guard rails, excluding openings for ladder access entry at the safety gates.
4.3.8. Prior to final installation of the guardrails all ladders, guardrails and safety gates are to have a Safety Yellow finish.
4.3.9. Where mechanical items are removed, structural items are to be touched up with paint to match existing painted elements.
June 3, 2025 | 7
5. Structural Design Narrative – N/A
6. Mechanical Design Narrative Switchgear to be repaired by replacement of same capacity.
Based on the information above, a LCCA was not performed for this project.
6.1 Mechanical Demolition
Demolish two steam condensate tanks on South side of Column W51. Demolish steam piping from units to high horizontal piping that is not in service. Demolish condensate piping from units to vertical IW piping. Replace vertical pipe fittings with new pups with similar material and fittings as existing. Demolish metal members supporting tanks and associated platform.
6.2 Mechanical Construction
None, not applicable.
7. Electrical Design Narrative The electrical requirements for the project include (but are not limited to):
Demolition of existing transformer, tie switch, and secondary side switchgear atop Mezzanine at Post V51
Demolition of primary cable feeders from the switch located at Post P53 to existing tie switch
Demolition of 600V branch circuits from secondary side switchgear to 480V busses Installation of new Transformer, tie switch, and secondary side switchgear Installation of cable feeders from V51 switch to existing switch at Post P53 Installation of 600V branch circuits from secondary side switchgear to 480V buses Installation of Circuit Breaker lifting hoist for switch gear.
Installation of portable and corded remote racking/switch station.
7.1 General Design Parameters and Assumptions
Existing equipment is located on Mezzanine at Post V51in building 3001. The primary side switchgear (tie switch) is powered via switch located at Post P53 (Circuit 24B to V51 – normally closed), is a 3-phase 12470V. The 1000kVA transformer reduces the voltage from 12470V to 480/277V which is then fed through the secondary side switchgear which routes the power to the North & South Bus. The Mezzanine contains the switchgear and transformer slotted for replacement.
Phasing of electrical demolition and installation shall be taken into consideration in both the design and construction phases. All work should aim to minimize disruption to user production output. Construction can occur during normal work hours. Outages must be coordinated with user 21 days in advance and must occur during non-standard working hours, weekends and holidays. Additionally, any work that will require the main aisle to be blocked will need to be done after hours or on weekends or holidays.
Contractor shall perform Voltage Drop calculations for all branch circuits that have excessive lengths; circuit showing excessive voltage drop will be replaced. New branch circuits for this
8 | June 3, 2025 project will not exceed the maximum allowable length and will not produce excessive voltage drop.
7.2 Electrical Demolition
All switchboard and transformer requirements shall be verified in field. De-energize and disconnect 12.47kV cable feeding relevant equipment. During the demolition and installation of gear, the South bus shall be fed from platform V67 equipment, and the North bus shall be fed from platform V91-1 equipment.
The existing primary side switchgear (12.47kV), 1000kVA transformer, and secondary side switchgear (480/277V) shall be demolished. All cable feeding the existing primary side switchgear from switch located at Post P53 shall be demolished along with the 600V branch circuit cables extending from the secondary side switchgear to the North and South 480V bus tap boxes. This includes the Tie Switch and secondary side of the switchgear.
7.3 Electrical Construction
New 3-phase/12.47kV/480V switchgear shall include 1600A main breaker, metering stations (ION 8650 metering stations connected to the CE Community of Interest Network Enclave (COINE) Virtual LAN per Tinker AFB Electrical Standards) and have arc flash prevention in the forms of both remote racking and remote switching. The new Switchgear shall have 1600 A adjustable-trip breaks to feed existing North and South bus feeds. As well as having one (1) spare space for additional future expansion. New switchgear shall include spare 1600A adjustable-trip breaker allowing for redundancy IAW Tinker AFB Standards.
New 1000kVA transformer shall be equipped with a cooling fan and appropriate ventilation.
A new run of 12.47kV cable from the V51 spare switches (located on same platform) to primary side switchgear and P53 and 600V cable from secondary side switchgear to North and South cable tap boxes shall be installed.
Designer is to provide an electrical distribution coordination study for the relevant equipment, as well as a fault current analysis and arc flash calculations (with detailed labels for all new equipment installed under this contract), which shall be performed using Easy Power software. Available fault current at the secondary terminals shall be provided for the new transformer.
A remote-control cabinet shall be installed and located on the plant floor: Purpose is to function as on installed at Post V67.
Ensure a circuit breaker lifting hoist is part of switchgear.
Provide portable and corded remote racking /switch station for the switchgear is required.
New branch circuits shall be supplied from the secondary side switchgear to the North and South bus Cable tap boxes.
Fire Protection / Life Safety Design Narrative – N/A
June 3, 2025 | 9
8. Intrusion Detection System (IDS) Design Narrative – N/A
9. Access Control System (ACS) Design Narrative – N/A
10. Communications Design Narrative – N/A
11. Phasing Plan
Contractor shall coordinate with Civil Engineering/TEPA to schedule any outages or main aisle blockages. While under construction, North and South buses shall be fed from North Substation V91-1 and South Substation V 69, respectively to minimize the impact to production.
10 | June 3, 2025
Appendix A Acronyms and Abbreviations
June 3, 2025 | 11
A Ampere(s)
AABC Associated Air Balance Council
ACCA Air Conditioning Contractors Association
ACI American Concrete Institute
ACS Access Control System
ACT Acoustic Ceiling Tile
AFB Air Force Base
AFF Above Finished Floor
AFI Air Force Instruction
AHJ Authorities Having Jurisdiction
AHU Air Handling Unit
AISC American Institute of Steel Construction
ANSI American National Standards Institute
ASCE American Society of Civil Engineers
ASHRAE American Society of Heating, Refrigeration and Air-Conditioning Engineers
ASTM American Society for Testing and Materials
BTHU British thermal unit
BUR Built-Up Roof
CAC Common Access Card
CBT Computer Based Training
CCTV Closed Circuit Television
CIPS Cyberspace Infrastructure Planning System
CMU Concrete Masonry Unit
COMM Communications
DB Dry Bulb
DoD Department of Defense
DX Direct Expansion
E East
EBI Enterprise Building Integrator
EMI Electromagnetic Interference
EMT Electrical Metallic Tubing
FCI Fire Control Instruments
FCU Fan Coil Unit
12 | June 3, 2025
FF-L Federal Specification
FPS Feet Per Second
FT Feet
GSA General Services Administration
HR Hour(s)
HSS Hollow Structural Section
HVAC Heating, Ventilation and Air Conditioning
IAW In Accordance With
IBC International Building Code
IC Intelligence Community
ICD Intelligence Community Directive
ICS Intelligence Community Standard
IDS Intrusion Detection System
IEBC International Existing Building Code
IECC International Energy Conservation Code
IMC International Mechanical Code
IN Inches
IPC International Plumbing Code
IT Information Technology kVA Kilovolt-Ampere
LAN Local Area Network
LED Light Emitting Diode
MOD Motorized Damper
N North
NEBB National Environmental Balancing Bureau
NFPA National Fire Protection Association
NIPR Non-Secure Internet Protocol Router
PSF Pounds per Square Foot
RF Radio Frequency
RFI Radio-Frequency Interference
SIPR Secure Internet Protocol Router
SMACNA Sheet Metal and Air Conditioning Contractors' National Association
S South
June 3, 2025 | 13
STC Sound Transmission Class
TAFB Tinker Air Force Base
UFC Unified Facilities Criteria
UPS Uninterruptible Power Supply
V Volts
VAV Variable Air Volume
W West
WB Wet Bulb
WG Water Gauge
§ Subsection
°F Fahrenheit
June 3, 2025 | 15
Appendix B
Civil Calculations and Cutsheets
June 3, 2025 | 17
Appendix C
Architectural Calculations and Cutsheets
June 3, 2025 | 19
Appendix D
Structural Calculations and Cutsheets
June 3, 2025 | 21
Appendix E
Mechanical / Plumbing Calculations and Cutsheets
Appendix F
Electrical Calculations and Cutsheets
Appendix G
Fire Protection Calculations and Cutsheets