140020_ATT11_Submittal Register_v4.pdf

PDF 130 KB Posted

Attached to
TINKER AFB MAC BOA WWYK140020, REPLACE UNIT SUBSTATION AND SWITCHGEAR, COL V51, B3001
Solicitation number
FA813725R0022
Issued by

About this file

The document is a Submittal Register for a federal construction contract at Tinker Air Force Base. The project involves replacing the unit substation, primary switch, and secondary switchgear in Building 3001, Column V51, with the contract number WWYK140020. The register details 67 specific submittal requirements across multiple specification sections, including preconstruction submittals, design data, product data, certificates, and closeout documents.

Key submittal requirements include providing a Health and Safety Plan, Construction Phasing Plan, Baseline Construction Schedule, Design Quality Control Plan, Operation and Maintenance Manuals, Working As-Built Drawings, and weekly Contract Progress Reports. Contractors must submit various documents such as entry access lists, safety meeting records, hazardous material usage reports, and training documentation. Most submittals are classified for Government review, with specific timing requirements, such as providing documents within 10 days of Notice to Proceed or monthly throughout the construction period.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line

Acti vity

Transm ittal #

Specification

Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval

Needed

By

Material

Needed

By

Action

Code

Date Of

Action

Date FWD to

APPR / Auth

Date RCD From

CONTR

Date FWD To

Other Revwr

Date RCD

From Other

Reviewer

Action

Code

Date Of

Action

Mailed To

CONTR/ Date

RCD From

APPR

Authority Remarks

1 00 70 00 01 Preconstruction Submittals Entry Access List 1.6 G

2 00 70 00 01 Preconstruction Submittals Key Issue Receipt 1.3.12.1

3 00 70 00 06 Test Reports Pre-Construction Testing Record 1.3.11 G

4 00 70 00 07 Certificates Welding, Cutting and Brazing Permit 1.4 G

5 00 70 00 07 Certificates Framed Instructions 1.8

6 00 70 00 11 Closeout Submittals Key Return Receipt 1.3.12.1

7 00 71 00 01 Preconstruction Submittals Health and Safety Plan 1.3 G

8 00 71 00 01 Preconstruction Submittals Internal Combustion Engines Plan 1.3.5 G

9 00 71 00 01 Preconstruction Submittals Entry Authority List 1.5.2

10 00 71 00 01 Preconstruction Submittals Vehicle Entry Authority List 1.5.2 G

11 00 71 00 01 Preconstruction Submittals Equipment and Material Storage 1.5 G

12 00 71 00 01 Preconstruction Submittals Contractor Offices and Plants 1.5 G

13 00 71 00 01 Preconstruction Submittals Designated Waste and Disposal Areas 1.5 G

14 00 71 00 01 Preconstruction Submittals Construction Phasing Plan 1.5 G

15 00 71 00 07 Certificates Safety Meetings 1.3

16 00 71 00 07 Certificates FOD Awareness and Prevention Training 1.4

17 00 72 00 01 Preconstruction Submittals AF Form 3952 Chemical/Hazardous

Material Request/Authorization

1.4 G

18 00 72 00 01 Preconstruction Submittals Spray Painting Plan 1.9 G

19 00 72 00 01 Preconstruction Submittals Environmental Management System

Awareness Training 1.1

20 00 72 00 03 Product Data Affirmative Procurement Documentation or Green Statement

1.3.10 G

Provide only one. Reference specification for additional information

21 00 72 00 07 Cerificates Monthly Hazardous Material Usage

Report

1.4 G

Provide 1st week of each month during construction

22 00 72 00 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data

Sheets 1.4

23 00 72 00 - Attch 3a 08 Manufacturer's Instructions Material Data Sheets B.3

24 00 72 00 - Attch 5 01 Preconstruction Submittals Construction Debris Analysis Plan 1.2.3 G

25 00 72 00 - Attch 5 07 Certificates Monthly Debris Management Report 2 G Provide 1st week of each month during construction

26 01 32 16.00 20 01 Preconstruction Submittals Baseline Construction Schedule 1.2 G Provide within 10 days of NTP.

27 01 32 16.00 20 01 Preconstruction Submittals Baseline Design Schedule 1.2 G Provide within 10 days of NTP.

28 01 32 16.00 20 07 Certificates Monthly Updates 1.4 Provide 1st week of each month during construction, or as directed by CO

29 01 32 16.00 20 07 Certificates 3-Week Look Ahead Schedule 1.6 Provide weekly with the Contract Progress

Report

30 01 33 00 01 Preconstruction Submittals Submittal Register 1.8 G

31 01 33 16.00 10 01 Preconstruction Submittals Design Quality Control Plan 1.5.1 G

32 01 33 16.00 10 01 Preconstruction Submittals Initial Design Conference 1.5.2.2

33 01 33 16.00 10 01 Preconstruction Submittals Preconstruction Conference 1.5.2.3

34 01 33 16.00 10 01 Preconstruction Submittals DCM Procedures 3.5.1 G

35 01 33 16.00 10 01 Preconstruction Submittals Submittal Register 3.8.4 G

36 01 33 16.00 10 05 Design Data Design and Code Checklists 1.7.1 C

37 01 33 16.00 10 05 Design Data Interim Design Submittals 3.2.1 R

38 01 33 16.00 10 05 Design Data Conference Documentation 3.7.3

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES

APPROVING AUTHORITY

TITLE: Tinker AFB General Requirements Specification (Div 00-01)

SUBMITTAL REGISTER

JOB NAME: WWYK140020 -- WO 52142, REPLACE UNIT SUBSTATION & SWITCHGEAR, COL V51, B3001

LOCATION: Post V51, B3001

CONTRACT NO:

CONTRACTOR:

Submittal Register_v3_03/07/22

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

Line

Acti vity

Transm ittal #

Specification

Section

SD

# Submittal Description Item Submitted Paragraph #

Classification:

GOVT or A/E

Reviewer Submit

Approval

Needed

By

Material

Needed

By

Action

Code

Date Of

Action

Date FWD to

APPR / Auth

Date RCD From

CONTR

Date FWD To

Other Revwr

Date RCD

From Other

Reviewer

Action

Code

Date Of

Action

Mailed To

CONTR/ Date

RCD From

APPR

Authority Remarks

(d)

CONTRACTOR

ACTION

CONTRACTOR SCHEDULE

DATES

APPROVING AUTHORITY

39 01 33 16.00 10 05 Design Data Final Design Submittals 3.8 R

40 01 33 16.00 10 05 Design Data Design Complete Documents 3.9 C

41 01 33 16.00 10 11 Closeout Submittals DD Form 1354 3.8.5 A

42 01 45 00.00 10 01 Preconstruction Submittals Quality Control (QC) Plan 3.2 G

43 01 45 00.00 10 01 Preconstruction Submittals Additional Requirements for Design

Quality Control (DQC) Plan

3.2.2 G

44 01 45 00.00 10 05 Design Data Discipline-Specific Checklists 3.2.2

45 01 45 00.00 10 05 Design Data Design Quality Control 3.9.1

46 01 45 00.00 10 06 Test Reports QC Documentation 3.9 Provide weekly with the Contract Progress

Report

47 01 50 00 01 Preconstruction Submittals Request for Contractor Staging Area 1.1 G

48 01 50 00 01 Preconstruction Submittals Photographic Record 1.3

49 01 78 00 03 Product Data Warranty Letter 1.7.1

50 01 78 00 03 Product Data Warranty Tags 1.7.3

51 01 78 00 08 Manufacturer's Instructions Instructions 1.7.1

52 01 78 00 10 Operation and Maintenance Data Operation and Maintenance Manuals 3.4 G Provide (2) electronic sets (optical media) and

(1) hard copy

53 01 78 00 11 Closeout Submittals Working As-Built Drawings 3.1 G Provide (2) electronic sets (optical media) and

(2) hard copies

54 01 78 00 11 Closeout Submittals Record Drawings 3.3 G Provide (2) electronic sets (optical media) and

(1) hard copy

55 01 78 00 11 Closeout Submittals DD FORM 1354 3.6 G

56 01 78 00 11 Closeout Submittals Checklist for DD FORM 1354 3.6 G

57 01 78 23 10 Operation and Maintenance Data Operation and Maintenance Data 1.2 G Provide 30 days prior to scheduled Training

58 01 78 23 10 Operation and Maintenance Data O&M Database 1.3 G

59 01 78 23 10 Operation and Maintenance Data Training Plan 3.1.1 G Provide 30 days prior to scheduled Final

Inspection

60 01 78 23 10 Operation and Maintenance Data Training Content 3.1.2 G Provide 14 days prior to scheduled Training

61 01 78 23 10 Operation and Maintenance Data Training Outline 3.1.3 G Provide 14 days prior to scheduled Training

62 01 78 23 11 Closeout Submittals Validation of Training Completion 3.1.6 G

63 SOW 07 Certificates Contract Progress Report(s) 2.4 G

Provide weekly throughout life of contract.

Utilize AF Form 3065, Contract Progress Report

(or equal)

64 SOW 01 Preconstruction Submittals B3001 Visitor Badge Issue Receipt 1.3.7

65 SOW 11 Closeout Submittals B3001 Visitor Badge Return Receipt 1.3.7

66 26 23 00 3 Product Data Switchgear 1.4.1 G

67 26 23 00 2 Shop Drawings Switchgear 1.4.2 G