This document package includes a Contract Data Requirements List (CDRL) and details for Solicitation Number FA810623R1000.

The CDRL outlines reporting requirements for a contractor providing Contractor Operated and Maintained Base Supply (COMBS) services for the T-6A/B/D Texan II aircraft. Requirements include management systems data, quality control procedures, and maintenance instructions. Delivery will be to the T-6 Program Office and AFLCMC/WLDJ on dates ranging from contract award through 2023.

Solicitation FA810623R1000 is for COMBS services at multiple Air Force bases, requiring inventory management, distribution, and maintenance for the T-6 aircraft. The solicitation is issued by the Air Force Materiel Command Lifecycle Management Center at Tinker Air Force Base. Responses are due by June 2023, with award anticipated in late 2023. Pricing will be fixed-price with a period of performance from 2024-2028. The solicitation is unrestricted with no set-aside provisions. The incumbent contractor was not specified.

View the file

Other files

File Type Posted
COMBS IV Team Updates to Vendor Question 10-16-23.pdf PDF
COMBS IV Team Updates to Vendor Questions 10-5-23 - 10-12-23.pdf PDF
FA8106-23-R-1000-Amendment 0003.pdf PDF
PWS_COMBS IV_26 SEPTEMBER 2023 (1).pdf PDF
Final COMBS IV Section L 20 September 2023.pdf PDF
PRICING MATRIX T-6 COMBS IV - Protected (V10) - 18 Sep 23.xlsx XLSX spreadsheet
COMBS IV Team Updates 11 Sept. to Vendor Questions 8-25-2023 through 9-25-2023 -RT.pdf PDF
FA8106-23-R-1000-0003.pdf PDF
T-6 COMB IV Vendor Questions No 1.pdf PDF
CBA Patuxent.pdf PDF
PRICING MATRIX T-6 COMBS IV - Protected (V9) - 28 Aug 23.xlsx XLSX spreadsheet
Revised COMBS IV Section M 17 August 2023.pdf PDF
CBA Corpus Christi.pdf PDF
Revised COMBS IV Section L 17 August 2023.pdf PDF
CBA Columbus.pdf PDF
CBA Pensacola-Whiting Field.pdf PDF
CBA Sheppard.pdf PDF
CBA Laughlin.pdf PDF
FA8106-23-R-1000 Amend 0002.pdf PDF
Wage Determinations T-6 COMBS IV.pdf PDF
FA8106-23-R-1000-0001 dated 7 August 2023.pdf PDF
PRICING MATRIX T-6 COMBS IV - Protected (V8) - Updated CLIN Structure - 27 July 2023.xlsx XLSX spreadsheet
Final COMBS IV Section L 27 July 2023.pdf PDF
Final COMBS IV Section M 27 July 2023.pdf PDF
PWS_COMBS IV_27 July 2023 (FINAL).pdf PDF
GFP Inventory 27 July 2023.xlsx XLSX spreadsheet
PPI_Tool_Download_Instruction.docx DOCX document
FA8106-23-R-1000 27 July 2023.pdf PDF
COMBS IV CDRL Package - 27 July 2023.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

For the best experience, open this PDF portfolio in

Acrobat X or Adobe Reader X, or later.

Get Adobe Reader Now!

http://www.adobe.com/go/reader

PREVIOUS EDITION MAY BE USED.DD FORM 1423-1, FEB 2001 PagesPage of

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188 OMB Approval Expires 20221130

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

TDP TM OTHER

D. SYSTEM/ITEM E. CONTRACT/PR NO. F. CONTRACTOR

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE

7. DD 250 REQ

8. APP CODE

9. DIST STATEMENT

REQUIRED

10. FREQUENCY

11. AS OF DATE

12. DATE OF FIRST SUBMISSION

13. DATE OF SUBSEQUENT

SUBMISSION

16. REMARKS

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft Final

Reg Repro

15.TOTAL

17. PRICE GROUP

18. ESTIMATED

TOTAL PRICE

G. PREPARED BY H. DATE I. APPROVED BY J. DATE

16. REMARKS (Continued)

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoD 5010.12-M for detailed instructions.)

DD FORM 1423-1 (BACK), FEB 2001

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.

DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13;

Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.

DRAFT

SAMPLE

PREVIOUS EDITION MAY BE USED.

DD FORM 1423-1, FEB 2001

Pages

PREVIOUS EDITION MAY BE USED.

DD FORM 1423-1, FEB 2001

Pages

DRAFT

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoD 5010.12-M for detailed instructions.)

DD FORM 1423-1 (BACK), FEB 2001

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188 OMB Approval Expires 20221130

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

C. CATEGORY:

14. DISTRIBUTION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft

Final

Reg

Repro

15.TOTAL

G. PREPARED BY

I. APPROVED BY

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

C. CATEGORY:

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data

Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.

DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in

Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in

Item 4; Clarification of submittal dates in Items 12 and 13;

Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.

9.0.0.2.20120627.2.874785

DD Form 1423-1, "CONTRACT DATA REQUIREMENTS LIST (1 Data Item) "

Click this button to save this form.:

Click this button to print this form.:

Click this Reset button to erase data from all fields.:

Enter total page numbers.:

A. CONTRACT LINE ITEM NUMBER:

EXHIB:

Select for "TDP.": 0

Select for "TM.": 0

Enter specification for "Other.": MGMT

SYS: T-6 PROGRAM OFFICE COMBS SERVICES

PR: FA8106-24-

CONF:

TextField2: B026

TextField2: Unique Identification (IUID) Marking and Verification Report

TextField2: IUID

TextField2: DI-MGMT-81858

TextField2: PWS 1.3.8.f

TextField2: AFLCMC/WLDJ

TextField2: LT

TextField2: A

TextField2: D

TextField2: Monthly

TextField2: BLK 16

TextField2: 5th/Month

TextField2:

Block 4: Contractor shall submit in the most recent version of MS Excel and data IAW PWS requirements.

Blocks 12 and 13: Contractor shall submit first monthly report NLT five (5) calendar days at the end of the first full month after start of full contract performance. Contractor shall submit subsequent reports NLT five (5) calendar days after the end of each month.

TextField2: AFLCMC/WLDJ

TextField2: Josh Butler

TextField2: 23 JUN 2023

Total draft copies is automatically calculated.:

Total final regular copies is automatically calculated.: 1

Total final regular copies is automatically calculated.: 1

Total final reproducible copies is automatically calculated.:

DecimalField1:

G. PREPARED BY (Signature):

I. APPROVED BY (Signature):

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government

Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.

DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13;

conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any

PREVIOUS EDITION MAY BE USED.

DD FORM 1423-1, FEB 2001

Pages

PREVIOUS EDITION MAY BE USED.

DD FORM 1423-1, FEB 2001

Pages

DRAFT

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoD 5010.12-M for detailed instructions.)

DD FORM 1423-1 (BACK), FEB 2001

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188 OMB Approval Expires 20221130

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

C. CATEGORY:

14. DISTRIBUTION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft

Final

Reg

Repro

15.TOTAL

G. PREPARED BY

I. APPROVED BY

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

C. CATEGORY:

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data

Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.

DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in

Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in

Item 4; Clarification of submittal dates in Items 12 and 13;

Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.

9.0.0.2.20120627.2.874785

DD Form 1423-1, "CONTRACT DATA REQUIREMENTS LIST (1 Data Item) "

Click this button to save this form.:

Click this button to print this form.:

Click this Reset button to erase data from all fields.:

Enter total page numbers.:

A. CONTRACT LINE ITEM NUMBER:

EXHIB:

Select for "TDP.": 0

Select for "TM.": 0

Enter specification for "Other.": MISC

SYS: T-6 PROGRAM OFFICE COMBS SERVICES

PR: FA8106-24-

CONF:

TextField2: B027

TextField2: Certificate of Compliance

TextField2: Master Repair/Overhaul Parts Listing

TextField2: DI-MISC-81356A/T

TextField2: PWS 1.3.12.1.d

TextField2: AFLCMC/WLDJ

TextField2: LT

TextField2: BLK 16

TextField2: D

TextField2: Annual

TextField2: BLK 16

TextField2: BLK 16

TextField2:

Block 4: Contractor shall submit in the most recent version of MS Excel and data IAW PWS requirements.

Blocks 12 and 13: Contractor shall deliver the first draft NLT nintey (90) calendar days after start of full contract performance. The Contractor shall submit the subsequent deliverable NLT thirty (30) calendar days after Government approval. The Contractor shall submit annual updates no later than 15 July of each year. In the event there are no changes to the Master Repair/Overhaul Parts Listing, the Contractor shall submit a letter stating there are no changes to the most recent submittal.

TextField2: AFLCMC/WLDJ

TextField2: Josh Butler

TextField2: 23 JUN 2023

Total draft copies is automatically calculated.: 1

Total draft copies is automatically calculated.: 1

Total final regular copies is automatically calculated.: 1

Total final regular copies is automatically calculated.: 1

Total final reproducible copies is automatically calculated.:

DecimalField1:

G. PREPARED BY (Signature):

I. APPROVED BY (Signature):

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government

Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.

DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13;

conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any

PREVIOUS EDITION MAY BE USED.

DD FORM 1423-1, FEB 2001

Pages

PREVIOUS EDITION MAY BE USED.

DD FORM 1423-1, FEB 2001

Pages

DRAFT

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoD 5010.12-M for detailed instructions.)

DD FORM 1423-1 (BACK), FEB 2001

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188 OMB Approval Expires 20221130

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

C. CATEGORY:

14. DISTRIBUTION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft

Final

Reg

Repro

15.TOTAL

G. PREPARED BY

I. APPROVED BY

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

C. CATEGORY:

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data

Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.

DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in

Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in

Item 4; Clarification of submittal dates in Items 12 and 13;

Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.

9.0.0.2.20120627.2.874785

DD Form 1423-1, "CONTRACT DATA REQUIREMENTS LIST (1 Data Item) "

Click this button to save this form.:

Click this button to print this form.:

Click this Reset button to erase data from all fields.:

Enter total page numbers.:

A. CONTRACT LINE ITEM NUMBER:

EXHIB:

Select for "TDP.": 0

Select for "TM.": 0

Enter specification for "Other.": MISC

SYS: T-6 PROGRAM OFFICE COMBS SERVICES

PR: FA8106-24-

CONF:

TextField2: B028

TextField2: Technical Report - Study/Services

TextField2: Reliability Availability and Maintainability

TextField2: DI-MISC-80508B/T

TextField2: PWS 1.3.12.1.g

TextField2: AFLCMC/WLDJ

TextField2: LT

TextField2: A

TextField2: D

TextField2: Monthly

TextField2: BLK 16

TextField2: 5th/Month

TextField2:

Block 4: Contractor shall submit in the most recent version of MS Excel and data IAW PWS requirements.

a. Delete Paragraph 2.a.

Blocks 12 and 13: Contractor shall submit first monthly report NLT five (5) calendar days at the end of the first full month after start of full contract performance. Contractor shall submit subsequent submittals NLT five (5) calendar days after the end of each month.

TextField2: AFLCMC/WLDJ

TextField2: Josh Butler

TextField2: 23 JUN 2023

Total draft copies is automatically calculated.:

Total final regular copies is automatically calculated.: 1

Total final regular copies is automatically calculated.: 1

Total final reproducible copies is automatically calculated.:

DecimalField1:

G. PREPARED BY (Signature):

I. APPROVED BY (Signature):

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government

Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.

DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13;

conformance with Government requirements, and the required to perform additional work to conform to Government without conforming to Government requirements, and the contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any

PREVIOUS EDITION MAY BE USED.

DD FORM 1423-1, FEB 2001

Pages

PREVIOUS EDITION MAY BE USED.

DD FORM 1423-1, FEB 2001

Pages

DRAFT

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoD 5010.12-M for detailed instructions.)

DD FORM 1423-1 (BACK), FEB 2001

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

Form Approved OMB No. 0704-0188 OMB Approval Expires 20221130

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.

C. CATEGORY:

14. DISTRIBUTION

14. DISTRIBUTION

a. ADDRESSEE

b. COPIES

Draft

Final

Reg

Repro

15.TOTAL

G. PREPARED BY

I. APPROVED BY

CONTRACT DATA REQUIREMENTS LIST

(1 Data Item)

C. CATEGORY:

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: TDP - Technical Data

Package; TM - Technical Manual; Other - other category of data, such as "Provisioning,""Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support.

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Signature of preparer of CDRL.

Item H. Date CDRL was prepared.

Item I. Signature of CDRL approval authority.

Item J. Date CDRL was approved.

Item 1. See DoD FAR Supplement Subpart 4.71 for proper numbering.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government.

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref.

DoDD 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-of date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in

Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in

Item 4; Clarification of submittal dates in Items 12 and 13;

Explanation of reproducible copies in Item 14.; Desired medium for delivery of the data item.

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.

b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.

Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.

c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government's right to use the data shall be governed by the pertinent provisions of the contract.

9.0.0.2.20120627.2.874785

DD Form 1423-1, "CONTRACT DATA REQUIREMENTS LIST (1 Data Item) "

Click this button to save this form.:

Click this button to print this form.:

Click this Reset button to erase data from all fields.:

Enter total page numbers.:

A. CONTRACT LINE ITEM NUMBER:

EXHIB:

Select for "TDP.": 0

Select for "TM.": 0

Enter specification for "Other.": MGMT

SYS: T-6 PROGRAM OFFICE COMBS SERVICES

PR: FA8106-24-

CONF:

TextField2: B029

TextField2: Acquisition and Sustainment Data Package (ASDP) Material Improvement Project (MIP) Report

TextField2: Deficiency Report

TextField2: DI-MGMT-80258C/T

TextField2: PWS 1.3.15.e

TextField2: AFLCMC/WLDJ

TextField2: LT

TextField2: A

TextField2: D

TextField2: BLK 16

TextField2: BLK 16

TextField2: BLK 16

TextField2:

Block 4: DID is tailored as follows:

a. Contractor shall submit in the most recent version of MS Excel and data IAW PWS requirements.

b. Paragraph 3.a: Clarify Contractor shall establish MIP number sequentially for each year

c. Paragraph 3.b: Clarify "Service Report (SR) number" to mean "Deficiency Report number"

d. Paragraph 3.c: Clarify "SR originator" to mean "Failure Location"

e. Paragraph 3.d: Delete Mission Designator Series (MDS)

f. Paragraph 3.e: Clarify to mean identify condition status of material at time of failure

g. Paragraph 3.m: Clarify to mean corrective actions taken to prevent reoccurrence.

Block 10, 12 and 13: Contractor shall submit within 30 calendar days for CAT I PQDRs and 60 calendar days for CAT II PQDRs, after receipt of investigation direction. If a final PQDR response cannot be provided 30 calendar days after PCOL receipt, updates are required every 30 calendar days until the final response is provided.

TextField2: AFLCMC/WLDJ

TextField2: Josh Butler

TextField2: 23 JUN 2023

Total draft copies is automatically calculated.:

Total final regular copies is automatically calculated.: 1

Total final regular copies is automatically calculated.: 1

Total final reproducible copies is automatically calculated.:

DecimalField1:

G. PREPARED BY (Signature):

I. APPROVED BY (Signature):

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .