Atch 5 - QA Sheet 25 June 2025.xlsx
XLSX spreadsheet 23 KB Posted
- Attached to
- Advanced Meter Reading System (AMRS) Metering Implementation - Randolph AFB Federal contract opportunity
- Solicitation number
- FA8051-25-R-2001
About this file
This file is a Questions and Answers (Q&A) document for an Advanced Meter Reading System (AMRS) Metering Implementation project at Joint Base San Antonio (JBSA) Randolph Air Force Base in Texas. The solicitation (FA8051-25-R-2001) is a 100% set-aside for SBA Certified Economically Disadvantaged Women-Owned Small Business (EDWOSB) Program, managed by the Department of the Air Force Materiel Command Installation and Mission Support Center Installation Contracting Agency.
The Q&A document covers critical details about the meter installation project, including mission-critical buildings (Buildings 8, 28, 55, 100, 399, 379, 494, 675, 700, 740, 860, 879, 902 & 990), power outage coordination requirements, and technical specifications for meter installations. Key technical requirements include using lockable NEMA 4 or NEMA 4X enclosures for communications equipment, coordinating outages 14-21 days in advance depending on facility criticality, and compliance with cybersecurity and federal regulations. The project involves indoor meter installations, communication infrastructure terminating at a patch panel, and coordination with base personnel, with work to be completed between 0730 and 1600 local time, excluding weekends and federal holidays.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA8051-25-R-2001 - Amend3 JBSA Randolph AFB 27 June 2025.pdf | ||
| Atch 1 - JBSA Randolph SOW and Appendices Combined 24 June 2025.pdf | ||
| FA8051-25-R-2001 - Amend2 JBSA Randolph AFB 25 June 2025.pdf | ||
| Atch 7 - Randolph Sign In Sheet.pdf | ||
| Atch 8 - Building 743 Pictures.pdf | ||
| FA8051-25-R-2001 Amend1 JBSA Randolph AFB 12Jun25.pdf | ||
| Atch 5 - QA Sheet.xlsx | XLSX spreadsheet | |
| Atch 4 - Additional Provisions and Clauses.pdf | ||
| Atch 2 - WDOL 13 May 2025.pdf | ||
| FA8051-25-R-2001 - JBSA Randolph AFB 30 May 2025.pdf | ||
| Exhibit 1 - CDRLs.pdf | ||
| Atch 6 - EAL Template.xlsx | XLSX spreadsheet | |
| Atch 3 - Price Proposal Summary Sheet.xlsx | XLSX spreadsheet | |
| Atch 1 - JBSA Randolph SOW with Appendices Combined 2 May 2025.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers
| JBSA RANDOLPH AFB AMRS | ||||
| SOW dated 2 May 2025 | ||||
| QUESTION # | REFERENCE | STATEMENT (Use this column when text is desired to preface a question for Clarity) | QUESTION | GOVERNMENT RESPONSE |
| 1 | General | Are the primary transformers serving the buildings owned by JBSA Randolph AFB or by the utility company? | XFMRs are owned by the utility provider, CPS | |
| 2 | SOW Appendix 1 LEM1 table & Installation Note 3 | "Mission critical, denoted as MC, facilities shall require late night or weekend outages and have longer lead times for power outage scheduling" | No line item in LEM1 table is identified as MC, please confirm there are no Mission Critical buildings on this site. | Buildings 8, 28, 55, 100, 399, 379, 494, 675, 700, 740, 860, 879, 902 & 990 are mission critical |
| 3 | SOW Appendix 1 LEM1 table & Installation Note 4 | "Outside normal duty hour OND shall require late night or weekend outages" | No line item in LEM1 table is identified as OND, please confirm no building has been identified as requiring outside normal duty hour outages at this time. | It is too early to tell if a facility will require OND hours without coordinating the electrical outages. This will have to be determined after contract award. |
| 4 | SOW Appendix 3, 1.3 | "All new communications equipment and metering devices are required to be enclosed in a lockable NEMA 4 or NEMA 4X enclosure" | Please confirm all new electric meter enclosures are required to be NEMA 4 for interior installation. | Per the SOW Appendix 1.3: All new communications equipment and metering devices are required to be enclosed in a lockable NEMA 4 or NEMA 4X enclosure. No other enclosure types are approvable for this project regardless of installation location. Communications equipment must be installed in a separate enclosure than the meter enclosure. |
| 5 | SOW 4.1 vs 4.1.3 | SOW Section 4.1 states "Contractor shall coordinate with the base customer service. CE POC, and facility users for requested power |
outages, a minimum of twenty-one (21) calendar days in advance of the needed outage".
| SOW Section 4.1.3 states "The contractor shall submit the completed form a minimum of fourteen (14) calendar days prior to the requested outage date for non-mission critical facilities. | Confirm the minimum required days for non-mission critical outage request. | It is the contractors' responsibility to attend and present their proposed outages on Wednesdays at 13:00 in the OPS conference room in Hanger 62. These meetings require pre approval from the facility managers of the facilities that will experience an outage. The 21 days Is for mission critical and 14 days for non-mission critical are acceptable if the facility managers approve the outage dates. | ||
| 6 | General | Will CAD drawings be provided after award for design or will the included PDFs serve as only documents to complete design scope? Please confirm. | Per the SOW Section 4.0: Government Furnished Material (GFM) |
The Contractor upon request may be provided with documents, drawings, and general reference material. However, these requests must be submitted directly to CO and the COR and may be refused if deemed unavailable, unnecessary, security sensitive, or outside the scope of work. At this time, the government does not have any CAD files for these facilities.
| 7 | General | When trenching through roadways and driveways, is concrete a suitable replacement material? | Base requirement is to return conditions of site to equal or better before trenching was done. For example concrete will not be suitable if trenching across an asphalt parking lot took place. |
| 8 | SOW Appendix 1 LEM1 table | Building 172 is provided in the floorplans however is not included in Appendix 1 Table LEM1. Will this building be added to the table? | Bldg. 172 is fed from Bldg. 171 and will not be added to the scope. |
| 9 | General | Are there any exterior MDPs that will require boring vs standard trenching? | As this is a design build contract, it is the due diligence of the contractor to determine if directional boring will be required. |
| 10 | General | Will the site walk sign in sheet be provided to everyone? | Yes, attached |
| 11 | General | Please confirm all abasement of asbestos or lead base paint will be performed by others and is not to be included in this pricing effort. | Abatement is not guaranteed to have been completed nor is it part of this contract. Contractor should avoid. This potential is also typically addressed in a site safety plan. |
| 12 | General | Please provide photos that were captured during the site walk for locations inaccessible by all parties. | Yes, attached |
| 13 | Are any of the proposed meter sites (and/or corresponding comms rooms) considered SCIFs and/or areas where escorts are required? If so, will there be limitations on electronic devices that can be brought into those work areas? | Yes, restrictions on electronic devices varies as each controlled access facility may have its own list of allowed electronic devices. 502 CS/SCXP (Project Management) will be your POC for any secure areas and/or SCIFS and will coordinate entry/work to be accomplished ahead of the projected start time. | |
| 14 | Assuming these new meter installations are to communicate to a local EEDRS AMRS server and the Air Forces MDMS systems, does the existing system have an ATO in place? | Yes | |
| 15 | Will the contractor be required to perform new system/device cyber-security credentialing in accordance with UFGS Div. 25 typical requirements? | Per the SOW Appendix 8 Section 2.0: 2.0 Applicable Documents |
The contractor shall identify and comply with all applicable federal, state and local laws; statutes, Executive Orders, Department of Defense/Air force manuals, handbooks, regulations and policies. The Contractor shall comply with the National Institute of Building Science’s whole Building Deign Guide Construction Criteria Base (CCB) Unified Facility Criteria (UFC) and all of the related libraires. The Unified Facilities Guidebook Specifications (UFGS) is the mandatory starting point for all specifications and shall not be deleted, materially modified, or made less stringent without Government approval. It is the contactors’ responsibility to identify and comply with all applicable requirements.
| 16 | Will the contractor be required to have cyber-security subject matter experts who have the usual and customary cyber-security credentials (Level 2, etc.)? | No |
| 17 | Will the project have any limitations on field work hours? E.G. can meter installation work be performed on weekends or during "after hours" if those time periods are more convenient for the scheduling of any outages that maybe required? | Per the SOW Section 5.14: Duty Hours/Base Access |
The Contractor shall complete work between the hours of 0730 and 1600 local time excluding Saturdays, Sundays, and Federal Holidays. Any work outside of these hours must be pre-coordinated with the COR at the base. Inclement weather, operational delays, and security related delays might affect the Contractor’s work periods. All commercial vehicles requiring access on the base will require inspection.
| 18 | As part of the proposal, will a SF30 or SF1449 be required to be submitted with the technical and price proposals? | A SF30 or SF1449 will not be required. Please see paragraph 7 of FA805125R2001. | |
| 19 | Atch 1 - JBSA Randolph SOW with Appendices Combined 2 May 2025.pdf | Where do the meters need to report? | The communication infrastructure is to end at the back of the patch panel and a patch cord is to be delivered to the 502 CS for each meter. |
| 20 | Atch 1 - JBSA Randolph SOW with Appendices Combined 2 May 2025.pdf | Where do the meters report: Do we need to supply a separate software package? | No |
| 21 | Atch 1 - JBSA Randolph SOW with Appendices Combined 2 May 2025.pdf | Where do the meters report: Is it going to report to the existing BAS/Scada system? | No |
| 22 | Does the network for the meters reside on COINE V2? This info is required for ATO purposes | Yes | |
| 23 | Atch 1 - JBSA Randolph SOW with Appendices Combined 2 May 2025.pdf | Please confirm there are no RMF cybersecurity documentation responsibilities for the contractor associated with this project | Correct, there are no RMF cybersecurity documentation responsibilities for the contractor |
| 24 | Atch 1 - JBSA Randolph SOW with Appendices Combined 2 May 2025.pdf | Please confirm which building locations require an outdoor NEMA 4X enclosure. If none, we will assume all locations are to be mounted indoors. | All meters are to be located indoors. |