This is a Questions and Answers document for solicitation FA706025Q0014, addressing contractor questions about an electronic door lock and access control system installation at three dormitory buildings (55, 72, and 3619) at Joint Base Anacostia Bolling Air Force - District Washington.

Key clarifications include that existing maglocks will not be replaced but will be utilized by new lock systems, vendors must include disposal of removed equipment, and the Government will provide staging areas within each building. The system must be standalone with handheld programming devices and off-line software eliminating network connectivity requirements. Only four exterior doors on Building 55's main structure require replacement (mechanical room doors removed from scope), while dormitory room common areas in Building 55 need multiple resident access but individual rooms require singular access. The solicitation due date was extended to August 15, 2025, with training required for 4 personnel (3 Dorm Leaders and 1 UH Manager). Each building will operate independently with its own client system, requiring a complete solution including PCs. Recommended finish for lever sets is Satin Nickel, Satin Chrome, or similar. The document includes building floor plans and photographs showing current door configurations and exit locations for all three buildings, with exterior doors marked as "Exit" on the plans.

View the file

Other files

File Type Posted
Combined Synopsis Solicitation Dorm Locks Replacement_Amended 15 August 2025.pdf PDF
Amendment 0004_RFQ FA706025Q0014_15 Aug 2025.pdf PDF
FA706025Q0014 - Attachment 8 - Mandatory Pricing Summary_6 Aug 25.pdf PDF
Combined Synopsis Solicitation Dorm Locks Replacement_Amended 6 August 2025.pdf PDF
Amendment 0003_RFQ FA706025Q0014_6 Aug 2025.pdf PDF
FA706025Q0014 - Attachment 2 - Performance Work Statement (PWS) Electronic Door Lock Install _Amended 6 Aug 25.pdf PDF
Combined Synopsis Solicitation - Dorm Locks Replacement.pdf PDF
Amendment 0002_RFQ FA706025Q0014_30 Jul 2025.pdf PDF
FA706025Q0014 - Attachment 7 - Site Visit Instructions_Amended_.pdf PDF
Amendment 0001_RFQ FA706025Q0014_28 Jul 2025.pdf PDF
FA706025Q0014 - Attachment 4 - Evaluation Criteria.pdf PDF
FA706025Q0014 - Attachment 1 - Clauses and Prescriptions Information.pdf PDF
FA706025Q0014 - Attachment 6 - Past Performance Questionnaire.pdf PDF
FA706025Q0014 - Attachment 2 - Performance Work Statement (PWS) Electronic Door Lock Install.pdf PDF
FA706025Q0014 - Attachment 7 - Site Visit Instructions.pdf PDF
FA706025Q0014 - Attachment 5 - Past Performance Fact Sheet .pdf PDF
FA706025Q0014 - Attachment 8 - Mandatory Pricing Summary .pdf PDF
FA706025Q0014 - Attachment 3 - Instructions to Offerors.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q. Will existing maglocks on doors need to be replaced as a part of this requirement?

A. No, existing maglocks will not be replaced, all new locks installed will utilize existing maglocks.

- Q. Will the handicap accessible door on the side of building 72 need to be accessible to residents only?

A. PWS Section 1 Scope has been amended, all changes have been highlighted in yellow.

- Q. Can the Government provide a building map with exterior door locations highlighted for all three buildings?

A. Yes, maps and photos have been added to the solicitation.

- Q. Where will the keys be issued/managed?

A. Dorm keys will be issued and managed independently at each building.

- Q. Is there a requirement for interconnectivity between buildings?

A. No, each building shall operate independently, and necessary equipment will be located within each building.

- Q. Will the Government require quotes to include disposal of existing locks?

A. Yes, vendors shall include disposal of existing equipment that is removed/replaced in their offer.

- Q. Will the Government provide a staging area within each building?

A. Yes, the Government will provide a staging area within each building for use during the performance of the contract.

- Q. Will all exterior doors on building 55 require access control?

A. Only the locks for the four (4) exterior doors of the main building will be replaced. The locks for the mechanical room have been removed from the requirement and will not need to be replaced.

- Q. Will all doors in the mechanical room of building 55 require access control?

A. No, mechanical doors for building 55 have been removed from the requirement.

- Q. Will the push to exit button on the main entrance of building 55 need to remain?

A. Yes, the push-to-exit button will need to remain, and its functionality shall be incorporated into new locking equipment that is installed.

- Q. Will alarms on the exterior doors of building 55 need to be removed, and if so will it be completed by the Government?

A. No, they will remain and be turned off by the Government.

Solicitation: FA706025Q0014

- Q. Are the exterior door locks on building 55 cylindrical or mortise?

A. Cylindrical.

- Q. Will the dormitory room entrance locks leading to kitchen and bathroom common areas within building 55 be required to allow for multiple access for each resident?

A. Yes, dormitory room common areas will be required to allow each individual resident access to the common area and individual rooms within the common area will require singular access.

- Q. Will all exterior door locks for the mechanical room within building 55 need to be replaced?

A. No, mechanical doors for building 55 have been removed from the requirement.

- Q. Will all dormitory room locks within building 3619 for room common areas and individual rooms need to be replaced?

A. No, only the locks leading to kitchen and bathroom common areas will not be required to be replaced.

- Q. Is there network at each building?

A. Offerors should not include networked solutions for this requirement. As stated in PWS Section 2 Paragraph 2.0 Task 1 “The Contractor shall achieve a grade-1lock standard, a standalone handheld programming device, off-line software which eliminates the need for secured network connectivity, regulatory requirements, and manufacturer’s warranty guidelines in the delivery of a quality Electronic Door Lock and access control system.

- Q. Are the buildings connected together by network?

A. No, each building will be Independent

- Q. Are all doors controlled by access control and will they need to interface in any way with that access control system?

A. All doors controlled by access control. Yes, Interface needed

- Q. Where and how will the keys be managed?

A. Each building will have a dorm leader to manage; UH manager will oversee all.

- Q. How many clients will be needed, and where will they be controlled from?

A. Each building will require one client, with each client supporting its own building independently.

- Q. Is there a recommended finish for the lever sets?

A. Satin Nickel, Satin Chrome, or Similar

- Q. Can there be an extension of the RFQ due date of 2 weeks granted?

A. The solicitation has been extended until 15 August 2025, see solicitation details on sam.gov for further details.

- Q. How many people will need to be trained in this system?

A. 4-3 Dorm Leaders and 1 UH Manager.

- Q. Do you need a complete solution, or will the government furnish the P.C.(s)?

A. Complete Solution independently to each building.

Exit

Exit Exit

Exit

EMERGENCY EVACUATION FLOOR PLAN

Exit

JOINT BASE ANACOSTIA BOLLING

AIR FORCE - DISTRICT WASHINGTON

_J

:::J i----------, i

L

====;-' = i J~ F------1

BUILDING NUMBER: 3619