This document package includes a federal contract solicitation and related DD Form 1354 for the transfer and acceptance of Department of Defense real property assets.

The solicitation is for replacing underground storage tanks and related components at a Defense Army and Air Force Exchange Services gas station located at Joint Base Anacostia-Bolling in Washington, D.C. The work includes replacing six under dispenser containment sumps, four 12,000-gallon underground fiberglass reinforced plastic gasoline storage tanks, associated piping, fittings, monitoring systems, and accessories. It also involves removing old tanks and sumps, excavating and backfilling trenches, testing and commissioning the new system, and coordinating work with AAFES personnel. Certified underground storage tank technicians are required to perform the fuel tank work in compliance with environmental regulations. The acquisition is set aside for small businesses with a magnitude between $500,000 and $1,000,000. A bid bond of 20% of the proposal price is required. The solicitation is for a firm-fixed-price contract, and funds are not presently available, so no award will be made until funding is in place.

The DD Form 1354 is used to document the transfer and acceptance of Department of Defense real property assets between DoD components. It includes blocks for identifying details of the assets, transaction type, costs, funding sources, and approvals.

View the file

Other files for this federal contract opportunity

Other files attached to AAFES Underground Storage Tank, newest first.
File Type Posted
ANNEXURE-1- Features of Exhisting Facility Rev_20240510.pdf PDF
Solicitation Amendment FA706024R00040004 SF 30.pdf PDF
2. AF FORM 66-Rev_20240510.xlsx XLSX spreadsheet
1. SOW - AAFES Gas Station-UST, Dispenser & Under dispenser Sump Replacement_20240510.pdf PDF
7. Sections L & M_20240510.pdf PDF
ANNEXURE-2- Form 1354.pdf PDF
ANNEXURE-4- New Tank Sketches.pdf PDF
10. Response-RFI Listing GOV Responses_AAFES UST_20240510.xlsx XLSX spreadsheet
Solicitation Amendment FA706024R00040003 SF 30.pdf PDF
7. Sections L & M.pdf PDF
9. List of Certified UST Contractors - Installers, Removers, and Testers as of March 2024.pdf PDF
Solicitation Amendment FA706024R00040002 SF 30.pdf PDF
Solicitation Amendment FA706024R00040001 SF 30.pdf PDF
Solicitation - FA706024R0004.pdf PDF
7. Sections L & M.pdf PDF
ANNEXURE-3- Environmental Standard.pdf PDF
2. FORM 66 - AAFES UST.xlsx XLSX spreadsheet
8. JBAB Base Access Registration Form.xlsx XLSX spreadsheet
1. SOW - AAFES Gas Station-UST, Dispenser & Under dispenser Sump Replacement.pdf PDF
ANNEXURE-1- Features of Exhisting Facility-11 sheets.pdf PDF
5. Subcontractor Consent.docx DOCX document
6. Wage Determination DC20240001 01_12_2024.pdf PDF
3. Past Performance Information Form.docx DOCX document
4. Financial Reference.docx DOCX document
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PREVIOUS EDITION IS OBSOLETE. Page 1 of 2DD FORM 1354, AUG 2022

TRANSFER AND ACCEPTANCE OF DoD REAL PROPERTY

PAGE

OF

PAGES

1. FROM (Organization Name) 2. DATE PREPARED

(YYYYMMDD)

3. PROJECT/JOB

NUMBER

4. SERIAL NUMBER

5. TO (Organization - Installation Code and Name) 6. RPSUID/SITENAME/

INSTCODE/INSTNAME

7. CONTRACT

NUMBER(S)

7a. RPA PLACED-IN-

SERVICE DATE

(YYYYMMDD)

8. TRANSACTION DETAILS

a. TYPE (X only one box)

ACQUISITION

TRANSFER BETWEEN SERVICES

CAPITAL IMPROVEMENT

INVENTORY ADJUSTMENT

b. WHEN/EVENT (X one)

TOTAL ASSET

PLACED-IN-SERVICE

PARTIAL ASSET

PLACED-IN-SERVICE

c. VERSION (X one)

DRAFT INTERIM FINAL

9.

ITEM

NO.

10a.

FACILITY NO.

10b.

RPUID

11.

CATCODE

12.

CATCODE

DESCRIPTION

13.

CONS

TYPE CODE

14.

SUST

CODE

PRIMARY

15.

UMA

16.

QUANTITY

SECONDARY

17.

UMO

18.

QUANTITY

19.

COST

20.

FUND

SOURCE

21.

FUND

ORG

22.

RPA INT

TYPE

CODE

23.

ITEM

REMARKS

24. STATEMENT OF COMPLETION. The facilities listed hereon are in accordance with maps, drawings, and specifications and change orders approved by the authorized representative of the using agency except for the deficiencies listed on the reverse side.

a. TITLE (Construction Agent/Installation Management Organization Accountable Official/RPAO)

b. TRANSFERRED BY (Typed Name and Signature)

c. DATE

SIGNED

(YYYYMMDD)

25. ACCEPTED BY (Typed Name and Signature)

a. TITLE (Installation Management Organization Accountable Official/RPAO)

b. NAME AND SIGNATURE

c. DATE SIGNED

(YYYYMMDD)

26. PROPERTY

VOUCHER

NUMBER

PREVIOUS EDITION IS OBSOLETE. Page 2 of 2DD FORM 1354, AUG 2022

27. CONSTRUCTION DEFICIENCIES (Attach blank sheet for continuations) 28. PROJECT REMARKS (Attach blank sheet for continuations)

INSTRUCTIONS

GENERAL. This form has been designed and issued for acceptance of real property or transfer between the DoD Components.

For detailed instructions on how to fill out this form, please refer to Unified Facilities Criteria 1-300-08.

Existing instructions issued by the DoD Components relative to the preparation of DD Form 1354 are applicable to this revised form to the extent that the various items and columns on the superseded forms have been retained. The DOD Components may promulgate additional instructions, as appropriate.

For detailed information on data inputs and codes, please refer to the latest version of the Real Property Information Model (RPIM) Report and use the RPIM Pick Lists for Block responses:

https://extranet.acq.osd.mil/ie/

SPECIFIC DATA ITEMS.

1. From. Name of the DoD Component.

2. Date Prepared. Date of actual preparation. Enter all dates in YYYYMMDD format (Example:

March 31, 2010 = 20100331).

3. Project/Job Number. Project number on a DD Form 1391 or Individual Job Order Number.

4. Serial Number. Sequential serial number assigned by the preparing organization (e.g.,Item 17.

2010-0001).

5. To. Name and address of the receiving installation, activity, and Service of the Real Property

Accountable Officer (RPAO).

6. RPSUID/SITENAME/INSTCODE/INSTNAME. Site Unique Identifier and name or installation code and name where the constructed facility is located.

7. Contract Number(s). Contract number(s) for this project.

7a. RPA Placed-In-Service Date. The calendar date the asset is accepted for use by DoD.

8. Transaction Details.

a. Type of Transaction. X only one box.

For Acquisition Type, refer to the Acquisition Method Code pick list in RPIM.

b. When/Event. When or event causing preparation of DD Form 1354. X only one box.

c. Version. Draft, interim, or final DD Form 1354. X only one box.

9. Item Number. Use a separate item number for each facility, no item number for additional usages.

10a. Facility Number. An installation specific asset identification number.

10b. RPUID. A unique non-intelligent code to permanently identify an asset.

11. CATCODE. The real property Category Code (CATCODE) that classifies the designed use of the asset (original or current) and corresponds to the largest quantity of the asset that is utilized for a single purpose (RPA Predominant Design Use CATCODE).

12. CATCODE Description. The CATCODE name corresponding with Item 11.

13. Construction (CONS) Type Code. The code represents the Construction Type Code and valid values can be found in the RPIM pick list by the same name. Type of construction will be PERM for Permanent or SEMI for Semi-permanent.

14. Sustainability (SUST) Code. : This code is also known as the Facility Sustainability Code and valid values can be found in the RPIM pick list by the same name. It indicates whether a facility meets the Guiding Principles of Federal Leadership in High Performance and Sustainable Buildings for buildings greater than 10,000 sq. ft. The list of valid values is: 1, 2, 3, 4.

15. UMA. Enter the primary unit of measure accountability for each design use category code for each item of real property.

16.Quantity. Enter the total quantity in the unit of measure accountability specified for each item of real property.

17. UMO. Enter the appropriate unit of measure operational for capacity/configuration as applicable for the design use category code.

18. Quantity. Enter the total quantity of capacity/configuration in the unit of measure operational specified for each item of real property.

19. Cost. Enter the total project cost for each item of real property. UFC 1-300-08 contains additional guidance.

20. Fund Source. Identify the fund source in this column for each real property asset or item. UFC 1-300-08 contains additional guidance.

21. Funding Organization. Identify the organization(s) responsible for funding the acquisition of this real property asset.

22. RPA Interest Type Code. This code represents the RPA Interest Type Code and valid values can be found in the RPIM pick list by the same name. The code is used to identify the type of legal interest that DoD holds in a real property asset.

23. Item Remarks. Remarks pertaining only to the item number identified in Item 9; show cost sharing.

24. Statement of Completion. Typed name, signature, title, and date of signature by the responsible transferring individual or agent. In the case of a real property acceptance action this is signed by the DoD Construction Agent. In the case of a real property transfer this is signed by the Installation Management Organization.

25. Accepted By. Typed name, signature, title, and date of signature by the Installation Management Organization RPAO or accepting official.

26. Property Voucher Number. Next sequential number assigned by the RPAO in voucher register.

27. Construction Deficiencies. List construction deficiencies in project during contractor turnover inspection.

28. Project Remarks. Project level remarks and continuation of blocks.

https://extranet.acq.osd.mil/ie/

PREVIOUS EDITION IS OBSOLETE.

Page of

DD FORM 1354, AUG 2022

TRANSFER AND ACCEPTANCE OF DoD REAL PROPERTY TRANSFER AND ACCEPTANCE OF DoD REAL PROPERTY

OF

OF

8. TRANSACTION DETAILS

8. TRANSACTION DETALS

a. TYPE (X only one box)

b. WHEN/EVENT (X one) B. WHEN/EVENT (X one)

c. VERSION (X one)

9. ITEM NO.

9. ITEM NO.

10a. FACILITY NO.

10. A. FACILITY NO.

10b. RPUID

10. B. RPUID

11. CATCODE

11. CATEGORY CODE

12. CATCODE DESCRIPTION

12. CATCODE DESCRIPTION

13. CONS TYPE CODE

13. TYPE CODE

14. SUST CODE

14. SUST. CODE

PRIMARY

AREA

15. UMA

15. PRIMARY UM

16. QUANTITY

16. PRIMARY UM QUANTITY

SECONDARY

OTHER

17. UMO

17. SECONDARY UM

18. QUANTITY

18. SECONDARY QUANTITY

19. COST

19. COST

20. FUND SOURCE

20. FUND SOURCE

21. FUND ORG

22. INTEREST CODE

22. RPA INT TYPE CODE

22. INTEREST CODE

23. ITEM REMARKS

23. ITEM REMARKS

24. STATEMENT OF COMPLETION. The facilities listed hereon are in accordance with maps, drawings, and specifications and change orders approved by the authorized representative of the using agency except for the deficiencies listed on the reverse side.

24. STATEMENT OF COMPLETION. The facilities listed hereon are in accordance with maps, drawings, and specifications and change orders approved by the authorized representative of the using agency except for the deficiencies listed on the reverse side.

b. TRANSFERRED BY (Typed Name and Signature) A. TRANSFERRED BY (Typed Name and Signature)

25. ACCEPTED BY (Typed Name and Signature) A. TRANSFERRED BY (Typed Name and Signature) DD1354, "TRANSFER AND ACCEPTANCE OF DoD REAL PROPERTY" 6.2.0.20160331.1.924316.921890

INSTRUCTIONS

INSTRUCTIONS

GENERAL. This form has been designed and issued for acceptance of real property or transfer between the DoD Components.

For detailed instructions on how to fill out this form, please refer to Unified Facilities Criteria 1-300-08.

Existing instructions issued by the DoD Components relative to the preparation of DD Form 1354 are applicable to this revised form to the extent that the various items and columns on the superseded forms have been retained. The DOD Components may promulgate additional instructions, as appropriate.

For detailed information on data inputs and codes, please refer to the latest version of the Real Property Information Model (RPIM) Report and use the RPIM Pick Lists for Block responses: https://extranet.acq.osd.mil/ie/

SPECIFIC DATA ITEMS.

1. From. Name of the DoD Component.

2. Date Prepared. Date of actual preparation. Enter all dates in YYYYMMDD format (Example: March 31, 2010 = 20100331).

3. Project/Job Number. Project number on a DD Form 1391 or Individual Job Order Number.

4. Serial Number. Sequential serial number assigned by the preparing organization (e.g.,Item 17. 2010-0001).

5. To. Name and address of the receiving installation, activity, and Service of the Real Property Accountable Officer (RPAO).

6. RPSUID/SITENAME/INSTCODE/INSTNAME. Site Unique Identifier and name or installation code and name where the constructed facility is located.

7. Contract Number(s). Contract number(s) for this project.

7a. RPA Placed-In-Service Date. The calendar date the asset is accepted for use by DoD.

8. Transaction Details.

a. Type of Transaction. X only one box.

For Acquisition Type, refer to the Acquisition Method Code pick list in RPIM.

b. When/Event. When or event causing preparation of DD Form 1354. X only one box.

c. Version. Draft, interim, or final DD Form 1354. X only one box.

9. Item Number. Use a separate item number for each facility, no item number for additional usages.

10a. Facility Number. An installation specific asset identification number.

10b. RPUID. A unique non-intelligent code to permanently identify an asset.

11. CATCODE. The real property Category Code (CATCODE) that classifies the designed use of the asset (original or current) and corresponds to the largest quantity of the asset that is utilized for a single purpose (RPA Predominant Design Use CATCODE).

12. CATCODE Description. The CATCODE name corresponding with Item 11.

13. Construction (CONS) Type Code. The code represents the Construction Type Code and valid values can be found in the RPIM pick list by the same name. Type of construction will be PERM for Permanent or SEMI for Semi-permanent.

14. Sustainability (SUST) Code. : This code is also known as the Facility Sustainability Code and valid values can be found in the RPIM pick list by the same name. It indicates whether a facility meets the Guiding Principles of Federal Leadership in High Performance and Sustainable Buildings for buildings greater than 10,000 sq. ft. The list of valid values is: 1, 2, 3, 4.

15. UMA. Enter the primary unit of measure accountability for each design use category code for each item of real property.

16.Quantity. Enter the total quantity in the unit of measure accountability specified for each item of real property.

17. UMO. Enter the appropriate unit of measure operational for capacity/configuration as applicable for the design use category code.

18. Quantity. Enter the total quantity of capacity/configuration in the unit of measure operational specified for each item of real property.

19. Cost. Enter the total project cost for each item of real property. UFC 1-300-08 contains additional guidance.

20. Fund Source. Identify the fund source in this column for each real property asset or item. UFC 1-300-08 contains additional guidance.

21. Funding Organization. Identify the organization(s) responsible for funding the acquisition of this real property asset.

22. RPA Interest Type Code. This code represents the RPA Interest Type Code and valid values can be found in the RPIM pick list by the same name. The code is used to identify the type of legal interest that DoD holds in a real property asset.

23. Item Remarks. Remarks pertaining only to the item number identified in Item 9; show cost sharing.

24. Statement of Completion. Typed name, signature, title, and date of signature by the responsible transferring individual or agent. In the case of a real property acceptance action this is signed by the DoD Construction Agent. In the case of a real property transfer this is signed by the Installation Management Organization.

25. Accepted By. Typed name, signature, title, and date of signature by the Installation Management Organization RPAO or accepting official.

26. Property Voucher Number. Next sequential number assigned by the RPAO in voucher register.

27. Construction Deficiencies. List construction deficiencies in project during contractor turnover inspection.

28. Project Remarks. Project level remarks and continuation of blocks.

CurrentPage:
PageCount:
Enter current page number.:
Enter total number of pages.:
1. FROM (Organization Name):
2. DATE PREPARED (YYYYMMDD):
3. PROJECT/JOB NUMBER :
serialNum:
5. TO (Organization - Installation Code and Name):
6. RPSUID/SITENAME/ INSTCODE/INSTNAME:
7. CONTRACT NUMBER(S):
serviceDate:
Select for ACQUISITION BY CONSTRUCTION: 0
Enter Acquisition type.:
Select for TRANSFER BETWEEN SERVICES: 0
Select for CAPITAL IMPROVEMENT: 0
Select for INVENTORY ADJUSTMENT: 0
Select for TOTAL ASSET PLACED-IN-SERVICE: 0
Select for PARTIAL ASSET PLACED-IN-SERVICE: 0
Select for DRAFT: 0
Select for INTERIM: 0
Select for FINAL: 0
9. ITEM NUMBER:
10. A. FACILITY NUMBER:
10. B. RPUID - REAL PROPERTY UNIQUE IDENTIFIER:
11. CATEGORY CODE :
12. CATCODE DESCRIPTION- CODE NAME WHICH DESCRIBES FACILITY USAGE:
13. CONS TYPE CODE - TYPE OF CONSTRUCTION. PERM FOR PERMANENT, SEMI FOR SEMIPERMANENT:
14. SUSTAINABILITY CODE:
15. PRIMARY UMA:
16. PRIMARY QUANTITY:
17. SECONDARY UMO:
18. CONFIGURATION QUANTITY:
19. COST:
20. FUND SOURCE:
21. FUNDING ORGANIZATION:
22. RPA INTEREST CODE:
23. ITEM REMARKS:
A. TITLE (DPW/RPAO):
B. NAME:
B. SIGNATURE:
C. DATE SIGNED (YYYYMMDD):
26. PROPERTY VOUCHER NUMBER:
27. CONSTRUCTION DEFICIENCIES (Attach blank sheet for continuations):
28. PROJECT REMARKS (Attach blank sheet for continuations):