Attachment_10_Past_Performance_Information.pdf
PDF 14 KB Posted
- Attached to
- Expert Scientific and Analytical Support (ESAS) 2 Federal contract opportunity
- Solicitation number
- FA7022-17-R-0002_Final
About this file
Attachment 10 - Past Performance Information
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 8
PAST PERFORMANCE INFORMATION
Provide the information requested in this form for each contract/program (citation) being described. Provide frank, concise comments regarding your performance on the contracts you identify. Provide a separate completed form for each contract/program submitted.
A. Offeror Name (Company/Division): ____________________ CAGE Code: ____________________ DUNS Number: ____________________ (NOTE: If the company or division performing this effort is different than the offeror or the relevance of this effort to the instant acquisition is impacted by any company/corporate organizational change, note those changes. Refer to the "Organizational Structure Change History" you provided as part of your Past Performance Volume.)
B. Program Title: ___________________________________
C. Contract Specifics:
1. Contracting Agency or Customer _____________________________________________
2. Contract Number __________________________
3. Contract Type __________________________
4. Period of Performance __________________________
5. Initial Contract Cost/Price _________________ 6. Current/final Contract Cost/Price _________________
7. Annual Contract $ Value _________________
8. If Amounts for 5 and 6 above are different, provide a brief description of the reason
D. Brief Description of Effort as __Prime or __Subcontractor (Please indicate whether it was development and/or production, or other acquisition phase and highlight portions considered most relevant to current acquisition)
E. Completion Date:
1. Original date: ____________________
2. Current Schedule: ____________________
3. Estimate at Completion: ____________________
4. How Many Times Changed: ____________________
5. Primary Causes of Change: ________________________________________________________________
F. Primary Customer Points of Contact: (For Government contracts, provide current information on all three individuals.
For commercial contracts, provide points of contact fulfilling these same roles.)
1. Program Manager: Name ____________________ Office ____________________ Address ____________________ Telephone ____________________
2. Contracting Officer: Name ____________________ Office ____________________ Address ____________________ Telephone ____________________
3. Administrative Name ____________________ Contracting Officer Office ____________________ Address ____________________ Telephone ____________________
Attachment 8
G. Address any technical (or other) area about this contract/program considered unique.
H. For each of the applicable subfactors under the Technical Capability factor in Section M, illustrate how your experience on this program applies to that subfactor.
I. Specify, by name, any key individual(s) who participated in this program and are proposed to support the instant acquisition. Also, indicate their contractual roles for both acquisitions.
J. Include relevant information concerning your compliance with subcontracting plan goals for small disadvantaged business (SDB) concerns, monetary targets for SDB participation.
K. Include relevant information concerning your compliance with FAR 52.219-8, Utilization of Small Business Concerns, on the contract you are submitting.
L. Identify whether a subcontracting plan in accordance with FAR 52.219-9, Small Business Subcontracting Plan, was required by the contract you are submitting. If one was required, identify, in percentage terms, the planned versus achieved goals during contract performance. If goals were not met, please explain.
M. Describe the nature or portion of the work on the proposed effort to be performed by the business entity being reported here. Also, estimate the percentage of the total proposed effort to be performed by this entity and whether this entity will be performing as the prime, subcontractor, or a corporate division related to the prime (define relationship).
N. Identify any Earned Value Management (EVM) or similar metrics required to track contract performance. If such metrics were required for this contract, provide the summary level data.