Attachment 18 - SOW Additions and Deletions, Phase 3-5

View the file

Other files for this federal contract opportunity

Other files attached to Base Wide CCTV - Phase 3-5, newest first.
File Type Posted
Solicitation_Amendment_FA700019RA0020004_SF_30.pdf PDF
Attch_06_-_Wage_Determination_-_Building_10_May_2019.pdf PDF
Solicitation_Amendment_FA700019RA0020003_SF_30.pdf PDF
Attch_18__-_SOW_Additions-Deletions_(Rev1),_Phases_3-5,_14_Mar_19.pdf PDF
Camera_support.pdf PDF
Base_Wide_CCTV_RFI's_-_20_Mar_19.pdf PDF
Attch_06_-_Wage_Determination_-_Building_22_February_2019.pdf PDF
Attch_19_-_Phase_1a_1b_2_CCTV_RFI_as_of_25_Jan_18_reference_only.pdf PDF
Solicitation_Amendment_FA700019RA0020002_SF_30.pdf PDF
ROOF_WARRANTY_Mar._2019.xlsx XLSX spreadsheet
Site_Visit_Minutes_FA7000-19-R-A002_Base_wide_CCTV_phase_3-5.pdf PDF
Attch_2_Email_to_Attendees.pdf PDF
Attch_1_CCTV_attendance_sheet.pdf PDF
Solicitation_Amendment_FA700019RA0020001_SF_30.pdf PDF
Attch_01_-_SOW_XQPZ150702L_CCTV_Phases_3-4-5,_Rev1.pdf PDF
Attch_08_-_USAFA_Environmental_Standards_2018_Final.pdf PDF
Attch_11_-_Drawings_150702L^Phase5.pdf PDF
Attch_14_-_Utility_Locates_and_Legend.pdf PDF
Attch_15_-_HWSW_10_Jan_19.XLSX XLSX spreadsheet
Attch_01_-_SOW.pdf PDF
Solicitation_-_FA700019RA002.pdf PDF
Attch_06_-_Wage_Determination_Building.pdf PDF
Attch_03_DVRs.xlsx XLSX spreadsheet
Attch_17_-_Financial_Reference.doc DOC document
Attch_09_-_Drawings_150702L^Phase3.pdf PDF
Attch_02_Cameras.xlsx XLSX spreadsheet
Attch_13_-_Bldg_2163_to_Prkg_&_Parade_Fld.pdf PDF
Attch_12_-_G002_Typical_All_Phases_Rev_1.pdf PDF
Attch_16_-_Experience_Form.docx DOCX document
Attch_04_-_Erosion_Control_Revegetation_and_Tree_Care_Standards_-_January_2019.pdf PDF
Attch_10_-_Drawings_150702L^Phase4.pdf PDF
Attch_07_-_Specifications_15-0702L.pdf PDF
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USAF ACADEMY CCTV, PHASES 3-5

ADDITIONS & DELETIONS TO ORIGINAL DESIGN

ATTACHMENT 18

CCTV SOW GENERAL REQUIREMENTS

1. Any new cameras, DVRs, and equipment must integrate seamlessly with the existing Milestone XProtect, Expert Edition Video Management System

2. No requirement for any bid options for the Santa Fe Trail design in Phase 5.

3. No technology in hardware/software may come from China.

4. Ensure all outdoor camera brackets and camera housings match the color of the facility finish or poles to ensure a seamless look. Roof-top camera brackets are required to match the design and profile of the roof-top camera brackets currently installed on Harmon Hall, Bldg 2304.

PHASE 3 CHANGES

5. Replace three PTZ cameras in the current design with three Axis Q6000-E Mk II Panoramic and Axis

Q6128-E PTZ Network cameras or equal cameras with similar characteristics. Refer to Phase 3 Design sheet C-103, keyed notes 1, 2, & 3. Upgrading PTZ cameras with panoramic cameras with PTZ capability for two rooftop cameras overlooking the Cadet Terrazzo on Fairchild Hall, Bldg 2354, and one overlooking the Cadet Parade Field, Fairchild Annex, Bldg 2355. All other requirements in the design remain.

6. Contractor shall provide one 4x4 video wall with the following minimum requirements to Bldg 2304, Crisis Action Team Location, Harmon Hall:

Sixteen (16) 55” 4K Input Capable Premium LED Monitor with the following minimum characteristics:

o Resolution: 1920x1080 o Input/Output: HDMI 1/1, DVI 1/1, DP 1/0, VGA 1/0, RS232 1/1, Audio o Brightness: 700cd/m2, o Bezel: Extreme Narrow Bezel o Features: Built-in scaler to spread 1 image across up to a 15x15 display configuration;

RS-232 Control Management S/W; Pixel Shift, Deinterlacing, Noise Reduction, Auto Power Recovery, Remote Control, Metal Chassis.

One (1) Video Wall Mounting System with the following minimum characteristics:

o Easy wall mounting with xyz directional control and tilt for maximum serviceability.

One (1) FHD Multi-Viewer System with the following minimum characteristics:

o Inputs / Outputs: 12 HDMI / 16 HDMI o Output Resolution: 2560x1600 o Feature: MS Windows Server OS, Rack Mountable 4RU Enclosure, Redundant Power Supply, Mouse, Keyboard, Pre-loaded Video Wall Software

Others:

The video wall system shall be integrated with the existing audio system and Milestone XProtect, Expert Edition Video Management System. The video wall minimum capabilities will include presenting checklists, PowerPoint Presentations, Cable TV, and CCTV video images in multiple screens, or one large image.

The maximum distance between the multi-viewer system and the video wall shall be 60 feet.

Contractor will remove two existing LED TVs/mounts, and return to the Govt. The contractor will remove two ceiling mounted projectors, replace ceiling tile to match existing ceiling tile.

Return projectors to the Govt.

Contractor will provide training to a maximum of 10 individuals for two hours on the operation of the video wall. In addition, contractor will provide an easy step-by-step user guide on the system.

Contractor will install power outlets to operate the video wall with coordination with the government.

PHASE 4 CHANGES

7. Replace two PTZ cameras in the current design with one Axis Q6000-E Mk II Panoramic and Axis

Q6128-E PTZ Network cameras or equal cameras with similar characteristics. Refer to Phase 4 Design sheet C-101, keyed notes 2. Upgrading PTZ cameras with a panoramic camera with PTZ capability for Holaday Athletic Center, Bldg 2164, rooftop overlooking the Cadet Athletic Fields. All other requirements in the design remain.

8. Replace one PTZ camera with one Axis Q6000-E Mk II Panoramic and Axis Q6128-E PTZ Network cameras or equal cameras with similar characteristics. Refer to Phase 4 Design sheet C-101, keyed notes 3. Upgrading PTZ camera with a panoramic camera with PTZ capability for NW corner of Cadet Gym, Bldg 2170, overlooking the Cadet Athletic Fields. All other requirements in the design remain.

9. Contractor is not required to install five new concrete poles in Phase 4 around Falcon Stadium. Refer to Phase 4 design, design sheet CU 102, keyed notes 1, 2, 3, & 7. All other design requirements remain.

10. Add eight Axis Q6000-E Mk II Panoramic and eight Axis Q6152-LE PTZ Network cameras or equal cameras with similar characteristics to cover cadet area parking lots (see attachment 13 in advertisement). Install new cameras to existing light poles in the area. Install any fiber, cabling, switches from Bldg 2163, Charlie 1 Guard House to make the cameras operational. Integrate new cameras into the over-all Falcon Eye Network, and provide a six-month playback recording capability.

See additional information below—provide communication equipment identified or equal equipment with similar characteristics:

Description Model Manufacture Qty

Panoramic Camera Q6000‐E Axis Communications 8

PTZ Camera Q6152‐LE Axis Communications 8

PTZ Attachment Kit T94A01C Axis Communications 8

Camera Pole Mount T91L61 Axis Communications 8

Camera Pole Bracket T91B47 Axis Communications 8

Outdoor Media Converter Cabinet T98A18‐VE Axis Communications 8

Cabinet Pole Bracket T95A67 Axis Communications 8

Cabinet Lock Kit T98A‐VE Axis Communications 8

Midspan T8120 Axis Communications 8

Small Form‐Factor Pluggable (SM Fiber) T8611 Axis Communications 16

CCTV Utility Pole N/A N/A 1

24 Port Switch JGS524 Netgear 1

Category 6 Cable (outdoor) N/A N/A 1000ft

Description Model Manufacture Qty

Open Trench per/ft 2500

Directional Boring per/ft 800

2" SDR11 Bore Pipe

SDR‐13.5‐

2000758510 DRLNE 5000

24x36x24 Quazite Hand Hole PG243BA24 QUAZITE 9

24x36x24 Quazite Lid PG2436HH0012 QUAZITE 9

Mule Tape Reel CUL 67684 PULL LINE 2

48SM SASJ Fiber FEDH1A1J12HB048E3 DRAKA 1300

24SM SASJ Fiber FEDH1A1J12HB024E3 DRAKA 1000

6SM SASJ Fiber HIT 61459‐6 HITACHI 4000

2ru FDP RTC2U‐6APBL OCC 2

FDP Splice Kit W/trays RS2U2T OCC 2

LC/SM Adapter Plate 6112SMDLC OCC 12

12SM 3M Pigtails P6LCUPC123MP OCC 12

Pole Mount FODP OCO12NX OCC 8

LC Quick Connect Connectors RFCLC8‐LCSM OCC 40

Fiber Splice Case 8006560 PLP Coyote 2

Fiber Splice 36 Trays 80805514 PLP 3

Fiber Splice Case 8006622 PLP Coyote Pup 1

Fiber Splice 24 Trays 80806033 PLP 2

Fiber Marking Tape PST‐FOBLNK‐PAN Panduit 1

11. Remove monitoring station and related equipment from Field House, Bldg 2169. Refer to Phase 4

Design, Design Sheet TY 110, keyed notes 1. All other design requirements remain.

12. Remove two monitoring stations and related equipment at Cadet Gym, Bldg 2170. Refer to Phase 4 Design, Design Sheet CU 601, Key Notes 1.

13. Replace two PTZ cameras in current Phase 4 Design with two Axis Q6000-E Mk II Panoramic and two Q6128-E PTZ Network cameras or equal cameras with similar characteristics. Refer to Phase 4 Design Sheet TY 124, Keyed Notes 4. Upgrading PTZ cameras with a panoramic camera with PTZ capability for SE and NE rooftop corners of Falcon Stadium Press Box, Bldg 4900, overlooking Falcon Stadium and parking lots. All other requirements in the design remain.

PHASE 5 CHANGES

14. Add monitoring location to the Phase 5 Design to South Gate, Bldg 8484, with two 27 inch monitors and related software/hardware. Monitoring location will only view cameras in the South Gate area and Large Vehicle Inspection location, Bldg 8488. Refer to Design Sheet CU 604. Integrate the ability to view cameras to the three guard booths at the South Gate.

15. Add monitoring location to the Phase 5 Design to North Gate, Bldg 9006, with two 27 inch monitors and related software/hardware. Monitoring location will only view cameras in the North Gate area. Refer to Design Sheet CU 605. Integrate the ability to view cameras to the two guard booths at the North Gate.

16. Integrate four existing cameras in the South Gate Canopy to the Phase 5 design into the overall CCTV system.

17. Integrate four existing cameras in the North Gate Canopy to the Phase 5 design into the overall CCTV system.

18. Add monitoring location to the Phase 5 Design, Bldg 9206, 306 FTG. Current location has monitoring capability of existing airfield cameras. Add two 27” desk monitor 4K LEDs with required software/hardware for an operational viewing location. Add one wall-mounted or ceiling mounted 55” 4K LED monitor to replace two existing 32 inch ceiling mounted monitors. Integrate the two new monitors to view the same CCTV airfield images. Remove the two 32 inch monitors and repair any ceiling tile if required. Return 32 inch monitors to the Govt. This viewing location will only view airfield cameras.

19. Add monitoring location to the Phase 5 Design, Bldg 8137, Security Forces Investigations. Add two 27” 4K LED monitors and related software/hardware to provide a complete operational system that can view, playback, and download any CCTV camera images across USAFA.

20. In Phase 5, replace existing analog cameras at Bldg 8024 (Security Forces Squadron) tied to the existing Falcon Eye system. Upgrade four exterior cameras on the four corners of the building with Axis P5515-

E PTZ Dome Network Cameras or equal cameras with similar characteristics. Upgrade three interior analog cameras with Axis P3225-LV MKII Network Cameras or equal cameras with similar characteristics. Add one Axis P3225-LV MKII Network Camera or equalcamera with similar characteristics to the Security Forces Guardmount room to provide a full view of this room. Provide any network infrastructure to upgrade existing cameras and integrate into the Falcon Eye network with a 30-day recording playback capability.

21. Contractor is not required to install three new concrete poles in Phase 5 around General Officer housing.

Refer to Phase 5 Design, design sheet CU 102, Key Notes 1. All other design requirements remain.

22. No bid option required for the Santa Fe CCTV.