JA-1, Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA6703-17-R-0006_Amend_0002.pdf | ||
| FA6703_17_R_0006_Site_visit_responses.pdf | ||
| FA6703-17-R-0006_Amend_0001.pdf | ||
| Site_visit_sign_in_7_Sep_2017.pdf | ||
| JA-4_Past_Performance_Worksheet.pdf | ||
| JA-13_01300_Submittals_.pdf | ||
| JA-3_PAST_AND_PRESENT_PERFORMANCE_QUESTIONNAIRE[1].pdf | ||
| JA-5_WD_GA170079_14_Apr_17_GA79.pdf | ||
| JA-6_WD_GA170134_28_Apr_17_134.pdf | ||
| JA-14_Seed_Project_Bldg_935_SOW.pdf | ||
| JA-9_DARB_4.pdf | ||
| JA-11_01560_Dobbins_Environmental_Requirements.pdf | ||
| JA-2_Financial.pdf | ||
| JA-10_DARB3.pdf | ||
| JA-8_Consent.pdf | ||
| FA6703-17-R-0006,_Simplified_Acquisition_Base_Engineering_Requirements_Solicitation.pdf | ||
| JA-7_WD_GA170246_6_Jan__17_246.pdf | ||
| JA-12_01010_General_Requirements.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment JA-1 FA6703-17-R-0006
SIMPLIFIED ACQUISITION OF BASE ENGINEERING REQUIREMENTS
SABER
94th MISSION SUPPORT GROUP/CIVIL ENGINEERING FLIGHT
Dobbins ARB, GA
07 November 2016
STATEMENT OF WORK
TABLE OF CONTENTS
Section Contents
1 Project Description
2 General Information
3 Technical Design Support
4 Design/Construction Requirements
5 Superintendence by the Contractor
6 Provisions on Contracting Officer’s Authority
7 Key Personnel
8 Construction Start-Up Period
9 Construction Schedules and Progress Reports
10 Work Clearance Requests
11 Pre-final and Final Inspection
12 Warranty
13 Work in Occupied Areas
14 Coordination with Government Activities
15 Contractor’s Quality Control
16 Interface with Government Personnel
17 Contractor Storage
18 Construction Site Maintenance
19 Contractor Parking
20 Work in Special Security Areas
21 Unauthorized Reconnaissance
22 Flight Line Access
23 Recording and Preserving Historical and
Archeological Finds
24 Smoking in DOBBINS ARB Facilities
25 Completion of Contract
26 Contractor's As-Built Drawings
27 Job Site Verification/Government Furnished
Record Drawings
28 Elevators
29 Identification of Government Furnished Facilities and Property
30 Government Liability
31 Toilet Facilities (Work Related)
32 Transportation of Construction Equipment
33 Damage to Utilities
34 Equipment Data for Warranty/Guarantee Items
35 ADP Support Requirements
36 Daily Work Plan
STATEMENT OF WORK (SOW)
1) PROJECT DESCRIPTION:
a) This is a Firm-Fixed Price indefinite-delivery, indefinite-quantity (IDIQ) contract for construction work on real property facilities at Dobbins Air Reserve Base. The work is required in support of the 94th Mission Support Group
Civil Engineering Flight. Each construction project will be awarded by issuing individual task orders against the basic contract on an as-needed basis. Projects will be in support of real property maintenance, repair, alteration, and new construction, including but not limited to: renovations, new facilities, additions, roofing, paving, and related construction work.
b) Except as otherwise noted as government furnished, the contractor will be required to furnish all facilities, materials, tools, equipment, and personnel necessary to manage the SABER program at Dobbins ARB and design, manage, and accomplish the task orders issued hereunder. The task orders may include a variety of trades including, but not limited to: carpentry, road repair, roofing, excavation, electrical, steam fitting, plumbing, sheet metal, painting, demolition, concrete, masonry, welding, HVAC, and asbestos removal.
2) GENERAL INFORMATION.
a) Hours of Work. Except as otherwise expressly provided in an individual task order, normal duty hours for the performance of this contract are 0730-1630, Monday-Friday, excluding federal holidays. Work may be performed at other times only with written permission of the Contracting Officer. The contractor shall submit a written request with adequate justification at least two workdays in advance of the date the contractor desires to deviate from the normal duty hours. If permission is granted, the will furnish written approval. The contractor shall ensure that the site superintendent keeps a copy (at the work site) of said approval. Such work outside normal duty hours will be at no additional cost to the government.
b) The following technical documents will be used in the execution of work under this contract:
SABER Statement of Work. This document is intended to be a general description of the requirements applicable to the contract.
SABER Contract Technical Specifications:
a) The Technical Specifications are organized by the International Building Code (IBC) 2015 all specifications are to be used in conjunction with the task order Statements of Objective (SOO) and SOWs and any drawings that may be provided by the government. Some Task orders may require that the specifications use the Unified Facilities Guide
Specifications (UFGS). Government will direct the task orders which need these specifications. When the UFGS are used the contractor shall edit them to suit the actual site application and conditions.
b) The Technical Specifications are generally referenced to RS Mean’s line items, which will serve as the Unit Price
Book (UPB) for this contract. The technical specifications also correspond to the RS Means line items. Some specifications are broad in nature and contain a variety of items; therefore, they may reference several UPB/RS
Means designators. Other specifications will not have UPB/RS Means pricing information; these items are those which are special ordered from the manufacturer or the items involved would be proprietary to each manufacturer’s own equipment.
c) The intent of the Technical Specifications is to furnish concise industrial and/or commercial standards for maintenance, repair, demolition, and construction of government facilities.
iii) Unit Price Book (UPB)
a) The most recent versions of RS Means cost estimating data will serve as the UPB for this contract. The UPB will be updated annually after 1 January and no later than 15 January. The contractor’s proposals for the work described in each task order will be based on the pricing information and the units of measure specified in the UPB. The following RS Means data shall be used:
(1) Facilities Construction Cost Data
(2) Facilities Maintenance and Repair Cost Data
(3) Mechanical Cost Data
(4) Plumbing Cost Data
(5) Electrical Cost Data
(6) Square Foot Cost Data
b) If the government specifies an item, which meets both the RS Means line item description and the characteristics called out in the Technical Specifications the contractor is obligated to furnish that item, regardless of actual cost compared to the RS Means cost.
c) Occasionally, the price and availability of construction materials is severely impacted by natural disasters and/or government actions. Due to the quick onset of such price/availability impact, the RS Means database may not reflect the change. If the government and the contractor agree that a specific commodity or construction material has experienced an unanticipated and unreasonable (+/- 30%) fluctuation in price, an adjustment factor may be negotiated for a specific task order and applied to the RS Means material cost only. This provision may be used to adjust the RS
Means material cost either upward or downward. The basis for the adjustment will be the then-current Consumer
Price Index.
3) TECHNICAL DESIGN SUPPORT:
a) The Contractor's staff shall possess multi-discipline technical expertise and experience. Areas of required technical design competence shall include, but not be limited to: civil, structural, mechanical, and electrical engineering; and drafting/surveying capabilities. The contractor's designs shall comply with the requirements of all building codes listed in the IBC 2015 and applicable UFCs, UFGS as outlined in UFC 1-200-01 core UFCS.
b) The government will provide a Statement of Objectives (SOO), with only basic concept design information for a specific task order. The contractor, using the concept design information, as well as all governing codes and SABER
Specifications, shall provide sufficient design documentation to substantiate the proposed approach for the task. This documentation may include any or all of the following:
(1) Statement of Work (technical description of the task); for the concept submitted prior to negotiation this may be an unedited or abbreviated version, but generally more than an outline.
(2) Work flow chart similar to a PERT diagram; or concept, only the major work items are required prior to negotiation.
(3) Detailed cost estimate; Means Prices cannot be changed. If they are they must be identified as such and will be considered as a non-pre-priced item (NPI).
(4) Justification for any non-pre-priced items (NPIs) to include three (3) quotes;
(6) Drawings; Generally a 35% design but may be more if required in the task order.
c) Typically, minimum design for SABER is up to 35%. However, if the design requires the services of a registered architect or engineer, it is outside the parameters of minimum design. The contractor is responsible for submitting documentation that substantiates the proposed approach.
d) Typically, supporting documents are requested from the contractor. Documents may include a Statement of Work, Program Evaluation and Review Technique (PERT) chart, cost estimates, justification for non- pre-priced items
(NPI), verified as-built drawings, manufacturer’s or technical drawings/schematics for fabrication and assembly of structural elements, form, fit and attachment details for installation of materials/equipment, and design calculations to substantiate proposed layout and sizing of utilities and structural elements (i.e., HVAC loads, lightning, platform support, etc.) . The task order may delete the requirements for documentation in this SOW or add to them as required. The following documents shall be submitted no later than 10 calendar after completion of negotiations.
(1). Completed statement of work.
(2). A schedule of required submittals. Contractor cannot change the submittals required and classifications shown in the UFGS unless the edits are accepted by the Government. Failure to list a submittal that it required in the specifications does not absolve the contractor from submitting that item. At any time during the contract the government may also request submittals not formally requested if it is information that should be available for free, without cost to the government. For example the government can request catalog data, installation instructions, maintenance instructions, and other data that the manufactures has or should have prepared prior to marketing a product and does not charge a fee or at no additional cost.
However the government cannot request shop drawings or documents that are normally sold over the open market, without compensating the contractor unless required in the specifications or negotiations.
(3) A completed schedule, AF3064. All major work elements will be identified.
(4) Material approval submittals; submittals may start 5 days after the submittal schedule is started.
(5) Drawings (completed 35%) Conception drawing will be required at 10 calendar days.
(6) Shop drawings showing basic layout and planning of the work; if drawings are too extensive or complex for submittal in 10 days after NTP then the contractor should negotiate the time during the negotiation phase.
(7) Manufacturer’s or technical drawings/schematics for fabrication and assembly of structural elements;
(8) Form, fit, and attachment details for installation of materials/equipment;
(9) Design calculations to substantiate proposed layout and sizing of utilities and structural elements (i.e., HVAC loads, lighting, platform supports
e) Any specific requirement for the services of a registered architect or professional engineer will be negotiated at the individual task order level and should not be included in the contractor’s coefficient.
4) DESIGN/CONSTRUCTION REQUIREMENTS:
a) Except as otherwise directed by the contracting officer, all design and construction accomplished pursuant to this contract shall comply with the 2015CY or the latest version of the all the applicable Building Codes, Regulations and
Standards and with the SABER Technical Specifications. The contracting officer, prior to construction start-up, shall approve any exceptions in writing. Applicable Codes, Regulations and Standards, include, but are not limited to:
International Building Code
International Existing Building Code
International Mechanical Code
International Plumbing Code
International Fuel Gas Code
International Energy Conservation Code
International Electrical Code
National Electrical Code
Life Safety Code - 101
National Fire Code
Uniform Federal Accessibility Standards
Air Force Instruction—AFI 32-1023, Design And Construction Standards And
Execution of Facility Construction Projects
Unified Facilities Criteria (http://www.wbdg.org/ccb)
Air Force Engineering Technical Letters (http://www.wbdg.org/ccb)
ANSI/ASHRAE IESNA 90.1, Energy Standard for Buildings except Low-Rise Residential
Buildings (I-P Edition), 2010 or latest version.
ANSI/ASHRAE IESNA 62.1 Ventilation for Acceptable Indoor Air Quality, 2010 or latest version.
Dobbins Air Reserve Base Design Guide latest version.
b) If there is a conflict between codes, regulations and specifications, the most stringent requirements shall apply at all times.
5) SUPERINTENDENCE BY THE CONTRACTOR:
a) The contractor shall employ a sufficient number of construction superintendents to adequately oversee all work under this contract. When work is being performed, the assigned superintendent or an appointed alternate shall be available at any work site within 15 minutes of notification. The superintendent is responsible for the proper coordination and timeliness of the work and for the proper workmanship of all trades. The ability of the superintendent, based on his knowledge and experience, is essential to the proper execution of the work, as is his ability to communicate and direct the efforts of those performing the work.
b) Not later than one week prior to the start of work on any task order, the contractor shall submit in writing to the contracting officer, or designated representative, the name of the individual(s) to serve as project superintendent(s) and the individual’s qualifications Pursuant to FAR 52.236-6; if personal change the contractor shall re-submit.
6) PROVISIONS ON CONTRACTING OFFICER’S AUTHORITY:
a) No person other than a contracting officer shall have authority to modify the terms of this contract or any task order issued hereunder. The contracting officer is the only person authorized to approve changes in any of the requirements under this agreement or any task order issued hereunder and not withstanding any provisions contained elsewhere in this contract, the said authority remains solely with the contracting officer. The contractor will not take direction from anyone other than the contracting officer or his/her representative. In the event the contractor effects any such changes at the direction of any person other than the contracting officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.
b) The contractor shall ensure all personnel and subcontractors employed under this contract are informed of the contracting officer’s authority as indicated in paragraph “a” above.
7) KEY PERSONNEL:
a) Each existing/proposed key personnel capability must indicate the following minimum levels of expertise:
1. Owner - no less than three (3) years’ experience in their respective field
2. Project Manager - no less than five (5) years’ experience in their respective field
3. Site Superintendent/Supervisor - no less than five (5) years’ experience in their respective field
4. AutoCAD Technician - Experience of the Drafting Technician must show training in an accredited drafting program and no less than two (2) years applied experience in generating and modifying construction drawings using AutoCAD software
b) The contractor shall provide and maintain a cellular telephone system for all key personnel throughout the period of this contract. The contractor shall ensure each project manager and superintendent is able to communicate with the government via cellular telephone at all times during normal duty hours and when working outside normal duty hours.
8) BASIC CONTRACT CONSTRUCTION START-UP PERIOD:
a) The first 30 calendar days following basic contract award shall be designated as a start-up period, after which the contractor shall have all equipment and personnel in place to fully execute the requirements of this contract.
9) CONSTRUCTION SCHEDULES AND PROGRESS REPORTS
a) In accordance with FAR Clause 52.236-15, Schedules for Construction Contracts:
i) All Construction schedules will be submitted on an AF Form 3064, Contract Progress Schedule. Work elements listed on the AF Form 3064, Contract Progress Schedule will be listed in CSI Master Format. When a project consists of multiple facilities, and/or is divided into phased construction within a single task order, these instances shall be considered as task order phases. The contractor shall provide for approval to the CO a separate AF FM 3064 for each phase and its apportioned project percentage. In addition, the contractor shall include an accumulative AF
FM 3064 summarizing all phases of the task order to equal 100%.
ii) At the contracting officer’s discretion, a critical path management (CPM) schedule may be required in addition to the AF Form 3064. When required, the contractor shall develop and submit this schedule using Microsoft Project software.
iii) For all task orders requiring the schedule in paragraph (i) above, the contractor shall submit a monthly progress report. At the Government’s discretion, the contractor may be required to submit bi-weekly progress reports. Progress reports will be submitted on an AF Form 3065, Contract Progress Report.
iv) The contractor shall not begin on-site work on a task order until the contracting officer has approved the proposed schedule
10) WORK CLEARANCE REQUESTS:
a) The contractor shall obtain a properly approved and coordinated AF Form 103, Base Civil Engineering Work
Clearance Request(s), prior to performance of any work on each task order requiring digging, boring, or any other earth disturbance. A copy of the completed AF Form 103 shall be submitted to 94th MSG/CE. Before initiating earth work, the contractor shall prepare and coordinate an AF Form 103, Work Clearance Permit with an 8.5” X 11” site map indicating the location of the required earth disturbance and/or any other digging requirements. The government will provide information on which offices shall coordinate on the AF Form 103. The contractor shall hand carry the
AF Form 103 to the coordinating offices and obtain the appropriate signature from each office indicated.
b) The government has fourteen (14) calendar days to issue an initial work clearance, and the clearance shall be valid for thirty (30) calendar days. It is the responsibility of the contractor to maintain all locates and markings after initial locate, failure to do so may cause delays due to no compliance and resubmittal time for AF Form 103 Government will view as new request See c)
(c) The contractor shall notify the Civil Engineering representative in writing to request a renewal of a digging permit. The government has 7 calendar days to issue a renewal to a digging permit. If the digging permit is more than 60 calendar days old, a renewal will not be issued and the contractor shall request a new digging permit.
d) The procedures set forth for government-owned utilities shall not apply to utilities that are governed by the
Utilities Protection Center (UPC) under the auspices of the State of Georgia. UPC utilities on Dobbins ARB include television cable, telephone cables, data cables, etc. Procedures for utilities governed by the UPC shall be followed in accordance with Georgia House Bill No. 1651, dated April 4, 1990. The contractor is required to obtain a UPC digging permit prior to digging on Dobbins ARB. The government is not responsible for issuing or monitoring UPC digging permits.
e) Once a digging permit is issued, the contractor shall hand dig and locate all marked utilities within 5 feet of the area to be worked on. If the contractor damages any of the items indicated, the contractor shall promptly repair the damage and return the item to its original workable condition. The contractor shall fill all holes with suitable materials IAW Attachment 2 specifications prior to project completion.
f) The contractor shall insure that the locations of all underground utilities, once located and marked by the government, are adequately maintained to preclude remarking by government personnel. If, during the life of the digging permit, the contractor or his subcontractor removes utility markings the contractor shall be responsible for replacing all markings.
g) The contractor shall immediately notify the government technical representative and the CO in the event that utility damage occurs. If damage to utilities is due to contractor non-compliance with permit instructions or contract requirements, repairs required shall be at the contractor’s expense. Fiber optic cables, which cannot be repaired to meet the minimum allowable decibels, shall be replaced at the contractor’s expense.
h) Flagging and/or paint markings placed to locate underground utilities shall be removed prior to the final inspection.
11) PRE-FINALS AND FINAL INSPECTION:
a) Prior to requesting an inspection from the government, the contractor shall ensure an internal quality control check has been accomplished. The contractor shall request a pre-final inspection of each task order when the project has been determined through the contractor’s quality control program to be ready for inspection. This request will be forwarded in writing to the inspector, with a copy to the contract administrator. The contractor should give the inspector 2-3 workdays to coordinate this inspection.
b) At the government’s discretion, an operations and maintenance inspection may be conducted as a first step in the pre-final inspection process. This inspection may include commissioning of electrical and mechanical systems, a functional demonstration training class, an on-site review of material and equipment maintenance procedures, and similar inspections and reviews for maintenance and operations coordination.
c) The contractor shall submit a written request for final inspection to the contracting officer, with the following attachments:
i) Corrected "as-built" drawings on blue line prints and CADD diskette.
ii) Completed AF Form 1354, Transfer and Acceptance of Military Real Property, three hard copies.
iii) A report certifying that there are no known outstanding discrepancies and that any punch list developed as a result of the pre-final has been cleared.
d) Any request for final inspection shall be submitted a minimum of five (5) working days prior to the desired date, unless waived by the contracting officer. Final inspection should be scheduled to occur prior to the specified contract completion date.
e) Final inspections will be conducted by the contracting officer or her/his authorized representative, the Civil
Engineering Project Engineer and Inspector, the contractor, the using agency representative, and other Dobbins ARB stakeholders. The contractor within the time limit specified by the contracting officer, in any event PRIOR to the scheduled completion date will correct discrepancies noted on the “punch list”.
f) The provisions herein are supplemental to those contained in FAR 52.246-12 Inspection of Construction.
12) WARRANTY:
a) The contractor shall provide a minimum one-year warranty on all work in accordance with FAR Clause
52.246-21, Warranty of Construction. The contracting officer will notify the contractor of warranty issues. After being notified of a problem, the contractor shall investigate the issue and respond within
24 hours. If the contractor believes the issue is not warranty related, the contractor may request a fact finding visit with the contracting officer and SABER Project Manager. If the fact-finding meeting determines the issue is warranty related, the contractor shall repair the item within 48 hours, or as determined by the contracting officer. If the manufacture’s standard warranty exceeds one year, then this warranty and all information shall be passed on, however the contractor has no responsibility to manage the manufactures warranty beyond one year.
b) All warranty work will be performed by the contractor to the complete satisfaction of the contracting officer in accordance with the applicable specifications.
c) The contractor is responsible for ensuring subcontractors fulfill warranty requirements on their work. All manufacturer warranties for equipment, roofing, etc. installed under an individual task order shall be submitted to the contracting officer in accordance with Specification 01300.
13) WORK IN OCCUPIED AREAS:
a) The buildings in this contract include a wide range of facility types and occupancies. They may or may not be occupied when SABER work is in progress inside them. All work in occupied facilities shall be coordinated through the contracting officer and the assigned project inspector. It is the contractor's responsibility to take whatever measures are necessary to assure the protection of occupant's assets, furnishings, equipment, etc., and to perform the work so as to cause minimal disruption of ongoing activities in occupied areas. All coordination shall be accomplished a minimum of five (5) working days in advance of anticipated on-site start date.
b) Delivery of materials and equipment shall be made with a minimum of interference to government operations and personnel.
14) COORDINATION WITH GOVERNMENT ACTIVITIES:
a) The contractor shall adhere to the requirements of each individual user organization. Any infringement on the normal working conditions (i.e. closing a hallway) shall be coordinated with the inspector at least 24 hours in advance.
b) If it becomes necessary to interrupt the using agency's work activities in buildings and/or areas for construction purposes, permission to do so shall be requested in writing to the contracting officer not less than five (5) working days in advance. Written requests for street closings will be submitted to the contracting officer for approval ten (10) working days prior to closing of the street. The contracting officer shall coordinate requests with the Base Civil
Engineer.
c) Work in connection with this contract which require temporary outages of any utility services (electrical, water, gas, Fire Detection etc.) close down or limit (as determined by the contracting officer) normal activities in the building, construction area, or other affected areas, shall normally be performed by the contractor at a time other than regular work periods of the organization occupying the facility. Requests for utility outages shall be submitted in writing to the contracting officer for approval at least ten (10) working days in advance. Requests shall show date the outage is required, time period for the outage, and specific utility system involved. Government personnel will accomplish shut down of existing utility systems IF and ONLY IF contractor personnel are available at the time.
Once a utility outage is arranged and work starts, the work shall go on until the affected utility is restored and normal activities can resume.
15) CONTRACTOR’S QUALITY CONTROL
A) GENERAL. The contractor is responsible for quality control and shall establish and maintain an effective quality control system in compliance with the Contract Clause entitled “Inspection of Construction.” and DIVISION 01
GENERAL REQUIREMENTS SECTION 01 45 00.00 10 QUALITY CONTROL The quality control system shall consist of plans, procedures, and Daily Reports to also include organization necessary to manage all delivery orders to produce products, which comply with the contract requirements. The system shall cover all construction operations, both on site and off site, and shall be keyed to the proposed construction sequence.
b) REFERENCES. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
ASTM D 3740 (1994a) Minimum Requirements for
Agencies Engaged in the Testing and/or inspection of Soil and Rock as Used in
Engineering Design and Construction
ASTM E 329 (1993W Agencies Engaged in the Testing and/or Inspection of materials Used in
Construction
c) CONTRACTOR’S QUALITY CONTROL PLAN. Within 15 work days after award of the contract, the contractor shall furnish for review and acceptance by the government a Quality Control (QC) Plan proposed to implement the requirements of the Contract Clause entitled “Inspection of Construction.” The plan shall identify personnel, procedures, control, instructions, test, records, and forms to be used. Construction will be permitted to begin only after acceptance of the QC Plan or acceptance of an interim plan applicable to the particular feature of work to be started.
d) ACCEPTANCE OF PLAN.
Government acceptance of the contractor’s plan is required prior to issuance of a notice to proceed on any task order.
The government reserves the right to require the contractor to make changes in its QC Plan and operations including removal of personnel, as necessary, to obtain the quality specified.
e) Notification of Changes.
After acceptance of the QC Plan, the contractor shall notify the CO in writing of any proposed change. Proposed changes are also subject to acceptance by the contracting officer.
f) Coordination Meeting.
After the pre-performance conference and prior to acceptance by the government of the QC Plan, the contractor shall meet with the contracting officer and the Design & Construction Chief or authorized representative and discuss the contractor’s quality control system. The QC Plan shall be submitted a minimum of 15 calendar days prior to the
Coordination Meeting. During the meeting, a mutual understanding of the system details shall be developed, including the forms for recording the QC operations, control activities, testing, administration of the system for both on site and off site work, and the interrelationship of contractor’s management and control with the government’s quality assurance. Minutes of the meeting shall be prepared by the contractor and signed by the contracting officer, the Design & Construction Chief, and the contractor. The minutes shall become a part of the contract file. There may be occasions when subsequent conferences will be called by either party to reaffirm mutual understandings and/or address deficiencies in the QC system or procedures, which may require corrective action by the contractor.
16) INTERFACE WITH GOVERNMENT PERSONNEL
When numerous construction tasks are ongoing, the contractor shall host a bi-weekly meeting, and more frequently as required by the government, with the contract administrators, government inspectors, and engineers to address the status of all projects in progress. The meeting shall cover the progress of all work with regard to their respective project schedule, any problems encountered and corrective actions taken and anticipated delays, if any. The contractor shall provide minutes of the meetings to the contracting officer and the Design and Construction Flight
Chief within 2 workdays after the meeting. Agreements or understandings made during meetings are not final; they must be followed up with memorandums of understanding, change orders, or other documents from the government to be binding. In all cases no agreement can be binding without the approval of the contracting officer.
17) CONTRACTOR STORAGE
a) The contractor is solely responsible for securing equipment and/or materials used in the performance of this contract and stored on base. The contractor assumes the risk and responsibility for loss or damage to government-furnished property.
b) Cover material stored within the area of contract operations and protect against mechanical and climatic damage or loss. The contractor may NOT leave equipment or materials on any roof (or tower) without prior approval from the
CO. Store equipment removed in performance of work where directed by the CO or his/her representative, and re-use in work as required by drawings and specifications. Equipment temporarily removed shall be protected, cleaned and replaced equal or better than its condition prior to starting work. Tie down all materials stored in an open area to prevent damage to government property particularly during unusual weather conditions, e.g., tornadoes, high winds.
c) If the contractor cannot be notified of impending severe weather conditions or does not take appropriate action to secure materials and/or equipment, the government may secure the equipment and/or materials and bill the contractor for the incurred cost.
d) The contractor shall repair or replace, at his/her expense, any damage to government property that occurs as a result of negligence. Do not store construction debris in the outside storage area or hold in this area for resale.
e) On all storage trailers and buildings, clearly post a notice of who to contact in case of emergency.
f) The contractor shall remove all materials, equipment, and temporary buildings prior to termination of contract and final payment. Any materials, equipment, or temporary buildings discovered after contract final acceptance shall become the property of the government and disposed of as abandoned property.
18) CONSTRUCTION SITE MAINTENANCE
a) Store all supplies and equipment for each task order on the project site when practicable so as to prevent theft or mechanical/climatic damage. The contracting officer will determine storage areas. Site shall be maintained in a neat and orderly manner. Fencing and visual screening will be required for outside construction sites to maintain a safe and neat appearance. Contractor shall not leave equipment or materials on any roof (or tower) unless prior approval has been obtained from the contracting officer.
b) Cover equipment that is to remain in place within the area of contract operations and protect it against damage or loss. Store equipment that is removed in performance of work where directed or reuse in work as required by drawings and specifications. Equipment temporarily removed shall be protected, cleaned and replaced equal to or better than its condition prior to starting work. Security for equipment or material that is to be reused and is removed for temporary storage shall be the sole responsibility of the contractor.
c) BARRICADES AND FENCING:
i) Indoor Barricades: The contractor shall furnish, install, maintain and remove adequate barricades, dust protection and warning signs to isolate the construction area from other occupied building areas, and to block direct access by unauthorized people.
ii) Outdoor Barricades: The contractor shall furnish, install, maintain and remove adequate barricades, warning signs and warning lights to isolate the construction area from unauthorized people.
iii) Fencing: When the site is in the vicinity of pedestrian and/or vehicular thoroughfare, the site perimeter shall be fenced. At a minimum, the fencing shall be heavy-duty plastic mesh construction barriers or a CO-approved equivalent. The CO may direct the contractor to use fencing in any area where he/she determines that people need additional protection from the site.
iv). The contractor shall identify and barricade all open trenches and excavations at the end of each workday. When in the vicinity of traveled ways (pedestrian and vehicular), the contractor shall place flashing lights on the barricades with a spacing not to exceed 25 linear feet. The CO may direct the contractor to use flashing lights when he/she determines that an open trench or excavation requires additional visibility. Contractor to comply with latest version
29 CFR OSHA 1926 or USACE EM 385 1-1.
v) Site Security: In occupied facilities, the contractor shall close up all exterior wall and roof openings resulting from the work in the facility at the end of each work day. The closures shall remain in place when the contractor is not actively working on the site to include day, night, weekends and holidays. The contractor is also responsible to protect and secure material and equipment on site. The government is not liable for the theft, vandalism or damage of any contractor supplies or equipment left unattended or unprotected on the job site.
vi) Each project site shall be cleaned up at the end of each day. All debris (whether blown in or contractor generated) on the job site shall be picked up and disposed of properly. All materials shall be neatly stacked and secured to prevent wind gusts from blowing materials around base. If the contracting officer or his authorized representative deems the project site is unsafe or unsightly the contractor may be instructed to halt construction and clean up the site.
d) Unless otherwise approved by the contracting officer, all contractor generated refuse and waste shall be hauled daily to a government-designated dumpster location on or off base. Waste will be disposed of in accordance with specification section 01560. The Construction site shall be kept neat, orderly, and safe for workmen at all times.
Contractor shall submit all weight tickets as detailed in specification 01560.
e) The contractor shall store all refuse in appropriate trash containers on the job site. If a dumpster is to be used the location of the dumpster shall be as directed by the contracting officer. The contractor’s dumpster shall be removed prior to final inspection. The contractor shall repair any damage the dumpster causes to government property.
f) If the contractor uses trucks to remove refuse from the job site the refuse shall be covered and secure prior to leaving the job site. If any materials are observed falling off the trucks, the truck shall be stopped and reloaded to prevent damage to any other vehicles caused directly/indirectly by falling debris. The contractor shall bear the monetary responsibility to repair all damage associated with falling debris.
g) The base refuse contract supplies dumpsters for government-produced refuse only. The contractor shall not dump refuse from any SABER project in the government dumpsters. If the contracting officer discovers SABER refuse in government dumpsters, he may instruct the contractor to immediately remove the refuse, or have government resources remove it at the contractor’s expense.
i) All mud, dirt, debris, foreign objects, or spills of any kind from the contractor's operations (including subcontractors and suppliers) on streets and parking lots, used as access to the work or staging areas, shall be cleaned off the same day. Taxiways, runways, parking aprons and hard surfaces, used as access to the work or staging areas, shall be kept clean at all times.
h) Equipment and vehicles to be used on base shall be safe and in good operating condition. The contracting officer, or designated representative, reserves the right to inspect any on-base equipment and reject such equipment if he/she considers it unsafe, in poor operating condition, or inappropriate for work. Contractor shall notify the contracting officer of any contractor equipment that is broken down on Dobbins ARB roads. Every effort should be made to move broken down equipment to the nearest parking lot before leaving it.
j) Contractor is responsible for submitting to the Government an Accident Prevention Plan. This plan shall be incompliance with either AFI 91-203 and OSHA guide lines or USACE EM-385-1-1.
19) CONTRACTOR PARKING
Contractor vehicles and equipment will ONLY be parked in a designated area. The contractor will not be permitted to park or run vehicles on grass areas. Only equipment required in direct performance of the work will be permitted to enter grass areas. Any damage done to lawns or shrubs will be repaired or replaced by the contractor at no additional cost to the government. At certain facilities/locations on Dobbins ARB, the contractor may be required to load or off-load material and equipment and park elsewhere.
20) WORK IN SPECIAL SECURITY AREAS:
a) Government will either escort or approve Contractor escort as required for access to secure areas while working on construction projects at Dobbins ARB.
b) The following security regulations will apply to construction projects on Dobbins ARB complex:
i) Director of Central Intelligence Directive (DCID) 6/9 (Dated Nov 2002) and Annexes A-G
ii) Unified Facilities Criteria (UFC) 4-010-01 (DoD Minimum Antiterrorism Standards for Buildings)
c) All contractor personnel shall be escorted at all times in a controlled/restricted area by an escort furnished by the government or contractor approved escort. Work requiring escorts will be scheduled 15 calendar days prior to starting work unless the contracting officer waives this requirement. Escorts provided by the government will only be provided during normal working hours.
d) Projects in a secured area may require a local agency check by the Base Security Police of the contractor, his employees, and all sub-tier contractor prior to commencement of on-site work. The contractor should allow approximately 30 calendar days to accomplish this check.
21) UNAUTHORIZED RECONNAISSANCE:
The contractor shall inform all personnel working under his/her jurisdiction (including subcontractor and visiting supplier personnel) that access to areas outside of the immediate work area (excluding cafeterias and restrooms near the work site, direct haul and access routes, Contracting and Civil Engineering offices, and points of supply and storage) is prohibited. Circulation of said personnel will be limited to official business only. Persons engaged in unauthorized reconnaissance of other contractor's or government activity will be referred to the contracting officer for disposition. Infractions involving possible compromise of national security will be turned over to the Air Force
Office Special Investigation (AFOSI) for disposition.
22) FLIGHT LINE ACCESS:
a) No personal vehicles will be allowed inside the flight line. Personnel walk-in access is by AF identification card.
b) All personal vehicles shall be parked in authorized parking lots.
c) Contractor vehicles shall be allowed access to flight line if required in the performance of the work as follows:
i) The contractor shall request permission, thru the contracting officer, with the Chief of Airfield Management
(CAM). Contractor who will operate vehicles on the airfield shall be given a driving briefing/training by the CAM.
Before operating any contractor vehicle on the flight line.
ii) Each vehicle shall have a company sign (minimum size 6 inches by 18 inches) on both front doors and all personnel shall have AF identification cards. The vehicles shall also have strobes affixed to the top of each vehicle.
The contractor is responsible for providing all strobes, and flight line flags.
iii) Supplier vehicles delivering materials to site shall be escorted by company vehicle.
d) The contractor shall clean debris from the runway surface as he proceeds with the work for applicable task orders.
The “clean as you go concept” is necessary to ensure a clean surface is available if there is an aircraft emergency.
23) RECORDING AND PRESERVING HISTORICAL AND ARCHEOLOGICAL FINDS:
All items having any apparent historical or archeological interest, which are discovered in the course of any construction activities, shall be carefully preserved. The contractor shall leave the archeological find undisturbed and shall immediately report the find to the contracting officer so that the proper authorities may be notified.
24) SMOKING IN DOBBINS ARB FACILITIES:
There shall be no smoking inside government facilities. This rule applies to all facilities, whether occupied or not, under construction/renovation or not. Butts shall not be left on the ground at any construction site. The contractor shall strictly inform/enforce these rules regarding his employees, suppliers, and subcontractors.
25) COMPLETION OF CONTRACT:
At the conclusion of this contract, the contractor shall be required to vacate any and all areas provided to him including office area and individual work sites. If provided, the contractor shall return the office area to its original condition, and shall do so within 14 calendar days of being notified by the contracting officer, or the conclusion of this contract, whichever comes first.
26) CONTRACTOR'S AS-BUILT DRAWINGS:
a) During the progress of the work, the contractor shall maintain at the job site two marked up set of record drawings, which clearly shows all changes and corrections from the layouts shown on the project drawings. The marked up set of record drawings will be made available for viewing when requested by the contracting officer’s representative and/or Project Inspector. The contractor shall enter such changes and corrections on contract or record drawings promptly. The record drawings shall also indicate, in addition to all changes and corrections, the actual location of all subsurface utility lines encountered. In order that the location of these lines and appurtenances may be determined the record drawings shall show, by offset dimensions to two permanently fixed surface features, the end of each run including each change in direction. Valves, splice boxes, and similar appurtenances shall be located by dimensioning along the utility run from a reference point. The average depth below the surface of each run shall also be recorded.
b) At the time final inspection is requested, the contractor shall submit to the contracting officer one copy of "as-built" prints and one set of drawing files showing the aforementioned data. A final inspection will not be scheduled unless "as-built" drawings and files are submitted with the request for final inspection.
c) All drawings submitted by the contractor shall be created from Computer Aided Design and Drafting (CADD) software in accordance with requirements stated in Section 10, "Computer Requirements". The contractor shall furnish one drawing file for each drawing sheet submitted (multiple drawing sheets per drawing file will not be accepted).
d) The contractor shall submit one (1) set of media (i.e. CD-ROM disk) containing the computer drawing files for each project. In general, the contractor shall provide all data necessary to display, edit and plot the files produced for each project. The external label on the media shall indicate the save set name, the date of creation, the disk volume number, a description of the disk contents (project name and project number), and the name and phone number of firm who created the disk.
e) Any costs associated with providing as-built drawings, as required above, will be included in the coefficient.
27) JOB SITE VERIFICATION/GOVERNMENT FURNISHED RECORD DRAWINGS
a) The government agrees to provide access to all known and relevant drawings the contractor may need to develop a task order cost proposal. The contractor shall contact the project engineer or project inspector assigned to each task order to schedule an appointment to review the government record drawings. Upon request the contractor will be provided one (1) copy of any record drawing that is relevant to the work required.
b) The integrity of these drawings is not guaranteed, and the contractor shall field verify all items on the drawings prior to preparing a cost proposal.
c) The existing dimensions and locations shown on the applicable drawings are for approximation purposes only.
Failure to verify the dimensions, conditions, and locations will be at the contractor's risk and shall not relieve the contractor from accomplishing the work required by the contract at the price awarded by the government. THE
GOVERNMENT DOES NOT GUARANTEE THE ACCURACY OR ADEQUACY OF EXISTING AS-BUILT
DRAWINGS. It is the contractor's responsibility to verify all as-built conditions prior to submission of a cost proposal and/or issuance of each task order.
28) ELEVATORS
a) Any temporary use of an existing elevator shall be by arrangement through the contracting officer and subject to his/her controls. Such use will be of an intermittent nature. The contractor shall provide and maintain suitable and adequate protection covering for the elevator machinery, the hatchway entrance, and the interior of elevator during the period of temporary use. Loads in excess of the rated capacity of the elevator will not be permitted.
b) The government will bear the cost of electrical current for the operation of the elevator. On completion of the work, the contractor shall remove the protection coverings, together with any resultant dirt and debris, and leave the equipment in a condition equal to or better than that in which it was found.
29) IDENTIFICATION OF GOVERNMENT FURNISHED FACILITIES AND PROPERTY
a) CONTRACTOR ON-BASE FACILITIES:
i) The government will provide approximately 800 SF of office space in Building 812 at Dobbins ARB for establishing a SABER management office. Contractor is responsible for providing storage space. One class C telephone will be available for on base calls. All other telephone connections and service will be at the expense of the contractor. The contractor shall be responsible for normal housekeeping and janitorial functions inside and outside this space as outlined in Base Regulations and as directed by the contracting officer. Such functions include sweeping, mopping, dusting, and any other operations necessary to present a neat and orderly appearance at all times.
All rubbish and waste materials shall be removed daily and be placed in approved containers outside the building where designated. The contractor will have access to the use of one bulk refuse container at each location for non-construction waste and debris, which will be emptied by the government’s refuse contractor.
ii) Outside storage area: The government will provide, without cost to the contractor, space at or near BLDG 501, located at Dobbins ARB GA. The outside space is approximately 400 SF for the location of a dumpster for construction debris dumping and disposal. Compliance with the OSHA and other applicable laws and regulations for the protection of the contractor’s employees is exclusively the obligation of the contractor. The government will assume no liability for the contractor’s compliance or noncompliance with such requirements. The Contracting officer shall approve any modification to the area in writing before any changes are initiated.