FA6703_17_R_0006_Site_visit_responses.pdf
PDF 646 KB Posted
- Attached to
- Base SABER contract Federal contract opportunity
- Solicitation number
- FA6703-17-R-0006
About this file
Responses to questions after site visit on 7 Sep 2017
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA6703-17-R-0006_Amend_0002.pdf | ||
| FA6703-17-R-0006_Amend_0001.pdf | ||
| Site_visit_sign_in_7_Sep_2017.pdf | ||
| JA-4_Past_Performance_Worksheet.pdf | ||
| JA-13_01300_Submittals_.pdf | ||
| JA-3_PAST_AND_PRESENT_PERFORMANCE_QUESTIONNAIRE[1].pdf | ||
| JA-5_WD_GA170079_14_Apr_17_GA79.pdf | ||
| JA-6_WD_GA170134_28_Apr_17_134.pdf | ||
| JA-14_Seed_Project_Bldg_935_SOW.pdf | ||
| JA-1_Statement_of_Work.pdf | ||
| JA-9_DARB_4.pdf | ||
| JA-11_01560_Dobbins_Environmental_Requirements.pdf | ||
| JA-2_Financial.pdf | ||
| JA-10_DARB3.pdf | ||
| JA-8_Consent.pdf | ||
| FA6703-17-R-0006,_Simplified_Acquisition_Base_Engineering_Requirements_Solicitation.pdf | ||
| JA-7_WD_GA170246_6_Jan__17_246.pdf | ||
| JA-12_01010_General_Requirements.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Responses for FA6703‐17‐R‐0006 Site Visit Questions
1. The solicitation does not exclude any portions of RS Means. Are all line items in the designated modules available for use?
Response: All modules are available for use.
2. Are As‐Built drawings of building 935 available for our use for this solicitation? Are CAD files available?
Response: There are not any as‐built drawings or CAD files available.
3. The roof of building 935 appears to be integral with the gutter. The SOW indicates the patching of the roof and removal and replacement of the gutters. Is the intent to match existing, install new external gutters, or is at the discretion of our design?
It is assumed that it is the intent to demolish and replace the downspouts as well. Please confirm.
Response: New gutters are required. The downspouts are to be replaced.
4. Is there a roof inspection available? It is unknown to what extent the roof/insulation will need to be repaired prior to the installation of the polymeric coating. Can a percentage value be attributed to this repair to insure our proposal is consistent with the expectations of 94th
Mission Support Group?
Response: A roof inspection is not available. Assume 40% repair
5. The SOW indicates the removal of existing landscaping surrounding the building and replace with dirt and pine straw. We assume that a planting curb 2 feet from the building face completely surrounding the building is the intent of this SOW. Or is it the intent for the
Contractor to remove all shrubs and grass between the building and nearest sidewalk/road/parking lot, complete. Please confirm.
Response: Two sides of the building have landscaping. The existing beds are to have landscaping/weeds removed and replaced with pine straw. Any existing grass that is disturbed by construction shall be replaced. Pictures of the beds are below (they are the South and West sides of the building.
6. The SOW for the Seed Project includes a mold test and ‘remediate as necessary’. Is it the intent that our proposal for the SEED project should include assumed abatement? Mold Abatement per OSHA, the EPA and ANSI can be extremely expensive. Please confirm whether our RS Means proposal should include any mold abatement.
Response: Mold is present is the building and shall be abated.
7. The Seed project SOW indicates ‘demolish and replace 600 square feet of solid walls’. Is the intent for all interior walls to be demolished other than the latrine/breakroom/mechanical room walls?
Response: All walls are not to be demolished. The 600 square feet does not include work to the restrooms/breakroom.
8. Will the MONACO system be hard wired or addressable via antennae?
Response: The system will be addressable via antennae.
9. It is assumed that the SOW does not include any utilities outside the building footprint
(transformer, water/FP Riser, BFP, communication wire, etc.). Please confirm.
Response: It does not include utilities outside the footprint.