This document outlines requirements for a firm fixed price construction contract to complete repairs and renovations to Building 1648 at Naval Air Station Fort Worth Joint Reserve Base in Texas. Work will be done in phases to maintain critical flight operations and includes floor plan changes, additional fixtures, separate locker rooms, fire sprinklers, mechanical and electrical modifications. Temporary cooling will be provided until final phase is complete. The pre-bid site visit is scheduled for March 30th and questions are due by April 7th. Proposals are due April 18th and will be evaluated using a lowest price technically acceptable approach. The contract value is estimated between $1,000,000 to $5,000,000. The work must be completed prior to the base's incoming F-35 mission. The Department of the Air Force Reserve Command is the contracting agency.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Narrative Amendment Date 20220328
DDPM200009, Repair Armament MX Shop B1648 – F-35
The following changes to the drawing shall be incorporated into the B1648 renovation project to provide temporary cooling for room 103 until room 105 renovation is competed and turned over to the customer.
SHEET C-101: Add the following:
Provide and install, without impeding phased operations, to maintain cooling in room 103:
- Temporary 200A 3 phase electrical service near room 103 east windows with breakers to match HVAC power requirement
- Temporary 200A 3 phase feed between transformer to north of building and the temporary service
- Two temporary HVAC package units (10-tons, 100% outside air each), duct through both windows (remove windows, duct through window opening, and seal penetration)
C-101
Transformer
Windows for temporary cooling
Temporary Electrical Service
Keep temporary cooling operational until the final contract phase.
Remove temporary equipment, service, and feed at end of the renovation. Restore windows, transformer, site and related building modifications before project completion.