Attachment_3_Statement_of_Need.doc

DOC document 47 KB Posted

Attached to
Spangdahlem Air Base 52d Fighter Wing Flooring IDIQ Contract
Solicitation number
FA560619RA003
Issued by

About this file

Attachment 3 - Statement of Need

View the file

Other files

File Type Posted
Solicitation_Amendment_2.pdf PDF
Attachment_2_Flooring_IDIQ_Database_8.29.19.xlsx XLSX spreadsheet
Section_L_Flooring_IDIQ_8.22.19.pdf PDF
Attachment_3_Statement_of_Need_8.22.19.doc DOC document
Attachment_4_Past_Performance_Questionnaire_PPQ_8.22.19.docx DOCX document
Section_M_Flooring_IDIQ_8.22.19.pdf PDF
Flooring_IDIQ_Questions.docx DOCX document
Solicitation_Amendment_1.pdf PDF
Attachment_6_Past_Performance_Questionnaire_PPQ_German_8.22.19.docx DOCX document
Attachment_2_Flooring_IDIQ_Database_8.22.19.xlsx XLSX spreadsheet
Attachment_2_Flooring_IDIQ_Database.xlsx XLSX spreadsheet
Attachment_3_Statement_of_Need.doc DOC document
Attachment_5_PPI.docx DOCX document
Solicitation_-_FA560619RA003.pdf PDF
Attachment_1_General_Provisions.pdf PDF
Attachment_4_PPQ.docx DOCX document
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Spangdahlem Air Force Base

STATEMENT OF NEED

Contract No.: RFQ# FA560619RA003 Project # 1031882

INSTALL SPORTS FLOOR IN WEIGHTLIFTING ROOM IN BLDG 152

The intent of this project is to install a sports floor which meets the special requirements of weight lifting in the Combat Fitness Room in Bldg. 152 located at Spangdahlem Air Base, with the line items described below based on the joint measurement with the contractor, from the 15 August 2019 site visit.

Contractor is to provide all materials, transportation, labor and equipment necessary.

Any hazardous material required to perform subject work requires prior approval before delivered on base.

After receiving the Notice to Proceed the KTR must begin work within 10 calendar days, and must complete it within 58 calendar days.

The KTR’s measurements and cost estimate was taken in the presence of the Government Inspector and has been verified to be accurate!

Item numbers correlate to Flooring IDIQ Database spreadsheet.

Item
Description
Qty
Unit
Unit Cost
Total
0001AE
Remove elastic floor covering
176
m²
0001AH
Apply waterbased primer
176
m²
0001AK
Increase surcharge for filling compound
176
m²
0001AT
Deliver/install Doellken baseboards
57.5
lfm
0001CM
Existing screed prime w/ 2K waterbased primer
176
m²
0001CU
Deliver/install self-adhesive shoulder
57.5
m²
0001DU
Deliver/install Birch multiplex boards
176
m²
0001DV
Deliver/install “Everroll Weightlayer Floor Plates”
176
m²

TOTAL

52 CES/CEOM