Attachment_3_Statement_of_Need_8.22.19.doc
DOC document 49 KB Posted
- Solicitation number
- FA560619RA003
About this file
Attachment 3 Statement of Need 8.22.19
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation_Amendment_2.pdf | ||
| Attachment_2_Flooring_IDIQ_Database_8.29.19.xlsx | XLSX spreadsheet | |
| Section_L_Flooring_IDIQ_8.22.19.pdf | ||
| Attachment_4_Past_Performance_Questionnaire_PPQ_8.22.19.docx | DOCX document | |
| Section_M_Flooring_IDIQ_8.22.19.pdf | ||
| Flooring_IDIQ_Questions.docx | DOCX document | |
| Solicitation_Amendment_1.pdf | ||
| Attachment_6_Past_Performance_Questionnaire_PPQ_German_8.22.19.docx | DOCX document | |
| Attachment_2_Flooring_IDIQ_Database_8.22.19.xlsx | XLSX spreadsheet | |
| Attachment_3_Statement_of_Need.doc | DOC document | |
| Attachment_2_Flooring_IDIQ_Database.xlsx | XLSX spreadsheet | |
| Attachment_3_Statement_of_Need.doc | DOC document | |
| Attachment_5_PPI.docx | DOCX document | |
| Solicitation_-_FA560619RA003.pdf | ||
| Attachment_1_General_Provisions.pdf | ||
| Attachment_4_PPQ.docx | DOCX document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Spangdahlem Air Force Base
STATEMENT OF NEED
Contract No.: RFQ# FA560619RA003 Project # 1031882
INSTALL SPORTS FLOOR IN WEIGHTLIFTING ROOM IN BLDG 152
The intent of this project is to install a sports floor which meets the special requirements of weight lifting in the Combat Fitness Room in Bldg. 152 located at Spangdahlem Air Base, with the line items described below based on the joint measurement with the contractor, from the 15 August 2019 site visit.
Contractor is to provide all materials, transportation, labor and equipment necessary.
Any hazardous material required to perform subject work requires prior approval before delivered on base.
After receiving the Notice to Proceed the Contractor must begin work within 10 calendar days, and must complete it within 58 calendar days.
The Contractors’s measurement was taken in the presence of the Government Inspector and has been verified to be accurate.
Item numbers correlate to Flooring IDIQ Database spreadsheet.
| Item |
| Description |
| Qty |
| Unit |
| Unit Cost |
| Total |
| 0001AE |
| Remove elastic floor covering |
| 176 |
| m² |
| 0001AH |
| Apply waterbased primer |
| 176 |
| m² |
| 0001CK |
| Deliver and install Screed UZIN NC 195 self trending cement leveling compound, 3 - 40 mm thick for interior |
| 176 |
| m² |
| 0001AT |
| Deliver/install Doellken baseboards |
| 57.5 |
| lfm |
| 0001CM |
| Existing screed prime w/ 2K waterbased primer |
| 176 |
| m² |
| 0001CU |
| Deliver/install self-adhesive shoulder |
| 57.5 |
| m² |
| 0001DU |
| Deliver/install Birch multiplex boards |
| 176 |
| m² |
| 0001DV |
| Deliver/install “Everroll Weightlayer Floor Plates” |
| 176 |
| m² |
| NPI |
| Reinforced ramp made of stainless steel chequer plate, manufactured according to NFPA requirements, delivered and professionally installed, as height compensation from existing floor to newly installed sports floor in the area and across the entire width of the roller shutter and also as transition plate to adjacent room (formerly gymnastics room). |
Ausgesteifte Rampe aus Edelstahl-Riffelblech, gemäß Anforderungen nach NFPA anfertigen, liefern und fachgerecht montieren, als Höhenausgleich von bestehendem Boden zum neu zu instalierenden Sportboden im Bereich und über die gesamte Breite des Rolltores und ebenso als Übergangsblech zum Nebenraum (ehemals Gymnastikraum).
| 1 |
| each |
TOTAL