This document provides questions and answers related to a Multiple Award Construction Contract solicitation for work at Moron Air Base in Seville, Spain. The solicitation seeks proposals for an Indefinite-Delivery Indefinite-Quantity construction contract with a minimum $500 guarantee and $45 million maximum over five years and two option years. Eligible offerors must be authorized for government construction work in Spain. The seed project is a $500,000 to $1 million renovation of Meeting Hall Building 105 to be awarded as the first task order. Submitted questions clarified requirements for technical proposals, drawings, and specifications in the solicitation and statement of work. The document establishes a revised proposal due date of June 9, 2021 and answers questions on performance periods, required installations, and contract pricing provisions.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Multiple Award Construction Contract (MACC)
Attachment 14
K - Contracting
C - Cost/Pricing
T- Technical
P - Past Experience
Solicitation
Reference (RFP
Section & paragraph)
*Example: Section
L.3.2.2
Document
Reference
(including paragraph, page)
*Example: SOW
Atch 2a
Additional/
Cross Reference Discussion/Comment/Question Govt. Response
K- Contracting Section L.3.1 Atch 5_Instructions, Conditions, & Notices to Offerors or Quoters
Proposals submitted by e-mail or regular mail (other than commercial carriers)
WILL NOT be accepted.
Due to current Covid travel restrictions and to not jeopardize the safety of our employees from risk of infection for Covid due to traveling, Requesting the government to accept proposals via the Electronic submission rather than hand delivered copies.
Due to differing software/program compatabilities, and network limitations, email offers will not be accepted.
K- Contracting Block/Item 8, SF 1442 and
Section L.3.1
Solicitation
FA557521R0004 &
Atch 5_Instructions, Conditions, & Notices to Offerors or Quoters
Delivery Address in Attch 5 L.3.1 & SF 1442 Block 8 are not matching Address in the solicitation is a default address and can't be changed. Follow
Attachment 5, Ssection L, Instructions Instructions, Conditions, & Notices to
Offerors.
K Section L.3.3. Pre-
Proposal Conference/Site
Visit
Attachment+5+Section
+L+Instructions+Condit ions+and+Notices+to+
Offerors+or+Quoters__
11+pgs.__Dated+NA
Due to the large amount of data from this project, I would appreciate the possibility of calling a new visit since more time is necessary for data collection.
No additional site visits will be available for this effort.
K Section 13. ADDITIONAL
SOLICITATION
REQUIREMENTS:
1.-
Solicitation+FA557521
R0004
Request to delay the delivery date scheduled for June 4, since a lot of documentation has to be studied, analyzed and prepared.
The Government will extend the due date until 9 June 2021, 1530 local time.
K Solicitation document, SF1442, Block 13 a page 1 We respectfully request a time extension for the submittal of our proposals. The current proposal due date is June 4th, 2021. The site visit for the Seed Project took place on May
18th, 2021. This leaves Offerors only with 2.5 weeks to verify the actual site conditions and prepare a) a responsible quotation, b) a 35% concept design, and c) a Bill of Quantities
Calculation.
We request that the Government extends the proposals due date through June 25th, 2021.
See above answer.
K Section L.5.2 Section L.5.2 states that volume 2 will be organized by means of a presentation of the following:
1) Table of Contents
2) Summary Page
3) Glossary of Abbreviations and Acronyms
4) Cross Reference (if applicable)
5) Subfactor 1 – Management and Technical approach
6) Subfactor 2 – Past Experience
However, section M (point M2, factor 2) indicates that the technical proposal will take into account 4 subfactores:
Subfactor 1 – Management and Technical Approach
Subfactor 2 – MACC Management
Subfactor 3 – Quality Management Program (QMP)
Subfactor 4 – Past Experience
The subfactors in section M, or those in section L, are valued?
Section L will be corrected to mirror Section M.
K - Contracting
C - Cost/Pricing
T- Technical
P - Past Experience
Solicitation
Reference (RFP
Section & paragraph)
*Example: Section
L.3.2.2
Document
Reference
(including paragraph, page)
*Example: SOW
Atch 2a
Additional/
Cross Reference Discussion/Comment/Question Govt. Response
K
Section M 2 Section 2
Paragraph M2 (point M2, factor 2) states that the technical proposal will take into account 4 subfactors: Subfactor 1
– Management and Technical Approach
Subfactor 2 – MACC Management
Subfactor 3 – Quality Management Program (QMP)
Subfactor 4 – Past Experience
However, in section M.4,it indicates that: “The offeror’s proposal shall be evaluated utilizing the two (2) technical subfactors”
Which one's right?
Section M.4 will be corrected to state (4) subfactors.
K
It's needed a site visit to clarify building utility connections
No additional site visit will be conducted.
C RFP Section M
Paragraph M.1.3.3
Step 1
Attachment 3a
Paragraph 2
Attachment 3a Solicitation Details (1 pg.) Dated N/A, paragraph 2 states that the magnitude of this project is between $500,000 and $1,000,000 U.S. Dollars.
We would like to confirm if the Total Evaluated Price entered by the offeror for the Seed
Project exceeds the maximum of $1,000,000 will determine that the solicitation proposal is evaluated or will otherwise render the proposal unawardable.
The price alone will not render any proposal "unawardable".
C Solicitation document, Section B Supplies or
Services and Prices/Cost page 4 of 59 Are Offerors expected to provide pricing in the CLINs in this Section? No, follow the instructions in Attachment 5, Ssection L, Instructions Instructions, Conditions, & Notices to Offerors.
P Section L, para. L.5.3.4.
Subfactor 2 – Past
Experience
Can the Offeror be credited with experience from a teaming partner? Yes, but you must adhere to the instructions under L.5.3.4.2.
C Section B, Item 1 Page 4 Section L, page 55 Description of Supplies Services states that "Task orders will be solicited and awarded in Euros only."
However, clause 52,215-1 Instructions to Offerors-Competititve Acquisition. 2017-01 states in subparagraph (c) (5) that "Offerors shall submit proposals in response to this solicitation in
English, unless otherwise permitted by the solicitation, and in U.S.
dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.
Provision FAR 52.225-17 will be added.
T section L.5.3.1.1
In section L.5.3.1.1(c, it indicates that: Bill of Quantities Calculation.
Provide an in-depth bill of quantities calculation consisting of position number, description, quantity, and supporting rationale for each line item
IAW SOW paragraph 1.5.3 . This section does not exist
Utilize Blank Cost Estimate Form
T section L.5.3.1.1(c)
The document to be developed in section L.5.3.1.1(c) Bill of Quantities
Calculation Should it be priced, or is it only necessary to make measurements of each of the indicated units?
Bill of Quantities Calculation must be priced
K - Contracting
C - Cost/Pricing
T- Technical
P - Past Experience
Solicitation
Reference (RFP
Section & paragraph)
*Example: Section
L.3.2.2
Document
Reference
(including paragraph, page)
*Example: SOW
Atch 2a
Additional/
Cross Reference Discussion/Comment/Question Govt. Response
T
Taking into account the measurements that need to be made for 35% of the concept design, Are SEED PROJECT sheets available in editable format?
We normally do not provide editable drawings to bidders before the project is awarded. Exceptionally, as we are asking for a 35% design, we attach the AutoCAD drawing of the buillding itself
T
Taking into account the requirements in the elaboration and development of 35% of the concept design, we request a postponement of the delivery date, in order to be able to make these documents in a convenient way to both the USG and DOR.
The Government will extend the due date until 9 June 2021, 1530 local time..
T
In drawing HA401, section A indicates that only two sections of walls septum are demolished, the section next to the stage is not demolished.
But on the floor of the building of the same drawing it is indicated its demolition. Which one's right?
As required in para. 2.1.3 of SoW, the ACM is afecting all the lateral splayed walls as marked in the layout. There is also part of this item the removal of the ACM, that including the supporting brick walls, of the back side of the auditorium. New version of Drawing HA401 showing the affected surfaces.
T
Section L.5.3.1.1(c)
It is indicates that it will be delivered Bill of Quantities Calculation.
Provide an in-depth bill of quantities calculation consisting of position number, description, quantity, and supporting rationale for each line item
IAW SOW paragraph 1.5.3.
However, in section M.4.1.1. Subfactor 1: Management and Technical
Approach of Seed Project indicates that:
Bill of Quantities Calculation. Provide an in-depth bill of quantities calculation consisting of position number, description, quantity, and supporting rationale for each line item. The line items shall be based on the blank Cost Estimate Form included in the seed project package documents
Which one would be right?
Utilize Blank Cost Estimate Form
T L.5.3.1.1.a; L.5.3.1.1.b
L.5.3.1.1. a) and b) describes what is required on the 35% concept design, and no outline specifications are required, while in the scope of work, table 5.5 they are requested. Please clarify, if they are requested and if so, if they are inside the 35 pages of narratives limited in Table 1.2. Vol II.
Drawings and a narrative will suffice
K - Contracting
C - Cost/Pricing
T- Technical
P - Past Experience
Solicitation
Reference (RFP
Section & paragraph)
*Example: Section
L.3.2.2
Document
Reference
(including paragraph, page)
*Example: SOW
Atch 2a
Additional/
Cross Reference Discussion/Comment/Question Govt. Response
T L.5.3.1.1.b
L.5.3.1.1. b) requires the minimum components of the concept drawings.
It is requesting "calculations". Which are these calculations to include in the drawings?, and if they should not be included in drawings and yes in the narrative, are they limited in page number by Table 1.2 Vol. II?
Provide a summary of any calculations and a narrative description of methodology utilized. Yes 35 Pages remains.
T L.5.3.1.1.b
L.5.3.1.1. b) requires the minimum components of the concept drawings.
It is required "construction phasing". Is going to be the building in use during the construction?
As stated in SOW, "The construction phase shall consider the phasing plan required to perform works with minimum interferences to Base operations and security, including a Construction Phasing Plan"
T SOW 2.3.9
SOW 2.3.9. states "Provide installations necessary for the building operation as a theater/cinema or Meeting Hall to include, but not limited to, public addressing system, sound system, stage lighting system, video projection, etc." This is a very open item,. Can you be more specific? Type of sound system? How many functions of stage lighting? Are the stage curtains included? The stage curtains motorization are included? Which type of control system?
See response to previous question on this same topic. Stage curtains motorization is included, as part of the interior electrical distribution renovation under SOW Part
3, parag. 2.3.2. Currently courtains are not motorized.. Control of motorization shall be basic-type (open/close with limit switches). Also existing manual gear to control the courtains need to be repaired to work properly. Stage curtains are not included to be replaced.
T RFP Section J
Attachment 3 Seed Project
No. QUUG+06-1003, Renovate Meeting Hall
Bldg. 105 Statement of
Work (SOW) 86 pgs.
Dated 24 Dec 2020
Attachment 3
Seed Project
Paragraph 2.3.9
(Page 11 of 86)
Attachment 3 Seed Project SOW, WORK DESCRIPTION paragraph 2.3.9 requires provision of several installations necessary for the building operation to include, but not limited to, public addressing system, sound system, stage lighting system, video projection, etc.
We request a more specific list of installations that have to be provided, which are necessary for the building operation (i.e. stage lighting, etc.). There may be more installations necessary for the building operation, and which are not mentioned. We believe that all required installations required to be part of the building operation should be anticipated in the RFP for a proper quotation.
Minimum installations to be considered for this design/build project include:
- Public addressing system.
- Video projection system.
- Digital movie player.
- Movie screen system.
- Movie sound system.
- Stage lighting system.
- Music/Voice sound equipment.
Project must include consideration for space, thermal & electrical load requirements for all the systems above, including pre-installation for such. Actual equipment purchase and installation of such equipment is not part of this project, but installation after this project completion must be made feasible with the project design/construction. For instance, the installaton of distributed loudspeakers for
K - Contracting
C - Cost/Pricing
T- Technical
P - Past Experience
Solicitation
Reference (RFP
Section & paragraph)
*Example: Section
L.3.2.2
Document
Reference
(including paragraph, page)
*Example: SOW
Atch 2a
Additional/
Cross Reference Discussion/Comment/Question Govt. Response
T Section 11 and
4. PROJECT PHASING:
1.-
Solicitation+FA557521
R0004 and
Attachment+3+Seed+P roject+No.+QUUG+06-
1003,+Renovate+Meeti ng+Hall+Bldg.+105+St atement+of+Work+(SO
W)__86+pgs.__Dated+
24__Dec__2020
As we have seen in the Solicitation form, the total performance period (design + construction) would be 362 calendar days. On the other hand, it is stated in the attachment 3 (page 12) that the total performance period is 520 calendar days. We kindly request you to clarify what the rigth total performance period would apply.
Period of performance is 520 calendar days.
K - Contracting
C - Cost/Pricing
T- Technical
P - Past Experience
Solicitation
Reference (RFP
Section & paragraph)
*Example: Section
L.3.2.2
Document
Reference
(including paragraph, page)
*Example: SOW
Atch 2a
Additional/
Cross Reference Discussion/Comment/Question Govt. Response
K - Contracting
C - Cost/Pricing
T- Technical
P - Past Experience
Solicitation
Reference (RFP
Section & paragraph)
*Example: Section
L.3.2.2
Document
Reference
(including paragraph, page)
*Example: SOW
Atch 2a
Additional/
K - Contracting
C - Cost/Pricing
T- Technical
P - Past Experience
Solicitation
Reference (RFP
Section & paragraph)
*Example: Section
L.3.2.2
Document
Reference
(including paragraph, page)
*Example: SOW
Atch 2a
Additional/