Revised_Attachment_2 _Sample_Project_Statement_of_Work _8Sep15.pdf
PDF 76 KB Posted
- Attached to
- Multiple Award Painting IDIQ Federal contract opportunity
- Solicitation number
- FA5270-15-R-0005
About this file
Revised Attachment 2 Sample Project Statement of Work para 4.2.1 dated 8Sep15
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised_Attachment_1 _Specification_01_01_00__1.6_-_Subcontractor_Revised31Aug15.pdf | ||
| Revised_Attachment_1 _Specification_09_90_00_3.1.1_-_Landscaping_Revised11Sep15.pdf | ||
| Revised_Attachment_5 _AF_Form_3052 _Estimate_Breakdown_for_Sample_Projects _11Sep15.pdf | ||
| Amendment_3.pdf | ||
| Revised_Attachment_3a _Sample_Project_Exterior_Paint_Drawings _by_adding_B400_Floor_Plan _11Sep15.pdf | ||
| Exterior_Color_Guidance_11Sep15.pdf | ||
| Request_for_Information_02.pdf | ||
| Amendment_2.pdf | ||
| 1.1_SPEC_01_01_00_-_General_Requirements_2.3.1.pdf | ||
| Request_for_Information_01.pdf | ||
| Amendment_1.pdf | ||
| Attachment_6.pdf | ||
| Attachment_4.pdf | ||
| Attachment_3b.pdf | ||
| Attachment_7.pdf | ||
| Solicitation.pdf | ||
| Attachment_3a.pdf | ||
| Attachment_5.pdf | ||
| Attachment_1.pdf | ||
| Attachment_8.pdf | ||
| Attachment_2.pdf |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 3 LXEZ1226592 & LXEZ101595 (8 Sep 15)
STATEMENT OF WORK
(Rev.1)
Project No & Title: LXEZ 12-26592 - PAINT EXTERIOR, AREA 4, KAB
LXEZ 10-1595 - PAINT INTERIOR FLOOR, WALLS, B266
Location: Kadena Air Base, Okinawa, Japan
1.0 General Scope:
The Contractor shall furnish all tools, equipment, materials, testing, labor and personnel necessary to plan, manage, supervise and construct the project to paint exterior surfaces for 19 buildings in Area 4 and interior of building 266 at Kadena Air Base. The work includes surface preparation, weatherproofing, caulking, sealing and other related incidental work necessary to complete the project in accordance with the approved specifications. The Contractor shall accomplish the work in conformance with current codes and regulations, not specifically stated elsewhere in this project statement of work to provide a complete and useable facility upon completion. The scope of work is further defined in the Description of Work section.
2.0 Project Schedule and Time Constraints:
2.1 Completion of Work: The Contractor shall be required to complete the entire work, ready for use, not later than 260 calendar days after the date of Notice to Proceed (NTP). Proposed schedule shall include material submittal review procurement and construction. The Contractor shall submit a Project Schedule at the pre-construction conference and shall resubmit updates as necessary until project completion.
2.2 Construction Schedule: The Contractor shall determine the most efficient work plan to minimize inconvenience to the building occupants.
2.3 Start Work Notification: Before starting on-site work the Contractor shall notify the Contracting Officer and the Project Manager in writing, thirty (30) calendar days prior to on-site work starting. After approval of on-site work, the Contractor shall provide written notice to all building managers affected by the project within a minimum of Fourteen (14) calendar days before starting on-site work.
2.4 Construction Access: The Contractor shall be allowed to work from 0730 to 1730, Monday through Friday, excluding U.S. Federal holidays, and other days specifically designated by the Contracting Officer.
2.5 Performance Time: The Contractor shall begin performance within five (5) calendar days after receiving the Noticed to Proceed (NTP) for construction.
Schedule Shall Be Completed Within
a) Material Submittals: 20 calendar days
b) Government Material Review: 15 calendar days
c) Procurement of Materials: 30 calendar days
d) Construction Time: 180 calendar days (150 CD for Exterior and 30 CD Interior)
e) Unfavorable Weather 15 calendar days
Construction Subtotal 260 calendar days
1277814460U Typewritten Text
FA5270-15-R-0005
Attachment 2
Page 2 of 3 LXEZ1226592 &
3.0 Construction Requirements:
3.1 As-built drawings will be provided to the Contractor for reference in their present form. The Government bears no responsibility for the accuracy of these drawings. Actual field investigation and survey of the facility must be conducted by the Contractor to ascertain existing conditions before start.
3.2 Project construction inspections and acceptance will be completed by 18CONS/LGCC, 718 CES/CENM and other agencies as necessary.
3.3 Daily Reports: Contractor shall provide daily progress reports to the Government. There will be no photos or any media recording of this project. Photo or media recording of the project must be by approval and coordinated with 718 CES/CENMA.
3.4 The Contractor shall notify the government of any weather delays within 48 hours of inclement weather that caused any work delay. An extension to the construction completion date may be provided if the total amount inclement work days exceeds the estimated unfavorable weather days listed in para 2.5 (e).
3.5 The time for construction completion includes final clean-up of the premises.
4.0 Description of Work:
4.1 Paint Exterior, Area 4, KAB
4.1.1 The following facilities will be painted:
Item BLDG# Facility Type
1 300 TLF
2 302 TLF
3 306 TLF
4 310 OFFICER'S CLUB STORAGE
5 313 OFFICER'S CLUB
6 325 TLF
7 328 DORM VAQ
8 329 DORM VAQ
9 331 VOQ
10 334 CHILD CARE CENTER
11 335 ELEC PWR S BLD
12 400 COMM FACLTY
13 428 GYMNASIUM
14 435 ARTS AND CRAFTS CENTER
15 451 BASE LIBRARY
16 455 RECREATION CENTER
17 80402 UTIL VAULT (UNUSED)
18 80403 UTIL VAULT
19 80446 UTIL VAULT
Page 3 of 3 LXEZ1226592 &
4.1.2 Complete surface preparation, to include but not be limited to: cleaning by power washing, repairing damaged surfaces, sealing, and caulking.
4.1.3 Apply primer as required to repaired areas.
4.1.4 Paint entire exterior of buildings to include any surface currently painted, as well as decorative/CMU wall enclosures, and trash enclosures.
4.1.5 Apply two coats of finish paint. Primary color, trim color and finish (texture) shall match existing.
4.1.6 Building number shall be repainted/stenciled per base standard.
4.2 PAINT INTERIOR FLOOR, WALLS, B266
4.2.1 The following rooms will be painted: 102, 103, 104, 105, 106, 107 and 108. Paint entire interior of facility to include all walls, ceilings, floor, and any surface currently painted.
4.2.2 Complete surface preparation, to include but not be limited to cleaning, scraping and repairing damaged surfaces.
4.2.3 For walls and ceilings, apply primer as required to repaired areas and then apply two coats of finish paint.
Primary color, trim color and finish (texture) shall match existing.
4.2.4 The floor coating shall be an epoxy based, durable and completely waterproof system that provides a smooth finish.
5.0 Government Furnished Equipment of Materials: None
File details come from the government source that posted it. Updated .