Attachment 5 for Draft RFP Instruction for 10 Design.

View the file

Other files for this federal contract opportunity

Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA5270-14-R-0019

Attachment #5 5 March 2014 Based on scope of project, the 10% design proposal shall include the following:

Site

Preliminary Site Plan (includes project boundaries, building orientation, location of streets -existing and proposed, parking lot layouts, service entrances, stormwater management, utility services, paving, curbing, walks).

Site Paving, Grading, Drainage Plan if contours are provided in the RFP technical specifications and requires this plan as a Proposal submission.

Typical road and parking lot sections.

Pavement Design Analysis.

Typical utility trench detail (with select backfill)

Preliminary Landscaping Plan (including kind, size and type trees, shrubs and ground covering).

Outline Specifications (includes preliminary specifications on all sitework items, including paving sections, earthwork, utilities, fire protection supply systems, miscellaneous site improvements).

Architectural

Preliminary Floor Plans (includes all levels and all rooms, furniture, preliminary equipment, doors, windows, special doors, shelves, vanities, counters, built-in cabinets and any special design features).

Preliminary Life Safety Plan and code analysis.

Enlarged Floor Plans as required to explain design solutions.

Roof Plan (includes roof slope and drainage).

Preliminary Cross Sections (indicating building heights, structures, general construction).

Preliminary Exterior Elevations (includes material indications, windows, doors, signs, etc.).

Typical Wall Sections (includes general construction and insulation).

Preliminary Finish Schedule.

Preliminary Door Schedule.

Details of special construction.

Outline Specifications (includes all architectural elements).

Structural

Codes to be used for design, complete design loads, and material strengths.

Special structural requirements including specific load conditions and deviations from the national code.

Preliminary Foundation and Framing Plans (includes typical foundations, floor and roof framing).

Outline Specifications (describing all structural elements and systems including soil compaction for foundations).

Descriptions of any deviation to structural system furnished by the Government.

Plumbing

Preliminary Plumbing Plans (includes plumbing fixtures, diagram of mains for water supply, sanitary waste and compressed air system).

Outline Specifications (describing all systems and major equipment).

HVAC

Preliminary HVAC Plans (includes single line diagrams indicating zoning, distribution, capacities of equipment and central plant layout, if applicable).

FA5270-14-R-0019

Attachment #5 5 March 2014

Outline Specifications (describing all systems and major equipment).

Fire Protection

Preliminary Fire Protection Plans (includes site, fire system, densities, and occupancy/hazardous classification for each area).

A description of the control system such as activation of the system, interlocks with HVAC system and connection to detection and alarm system.

Define the type of Automatic Fire Detection that will be provided.

Outline Specifications (describing all systems and major equipment).

Electrical

Preliminary Electrical Plans (includes typical lighting and power layout, handicap requirements, fire alarm, telephone and sound systems, site lighting, service type and size).

Outline Specifications (includes all electrical items and electrical/electronic systems).

Define any hazardous area by class, division, and group as defined in the National Electrical Code, and indicate type of equipment proposed for use in the area.

Electronic Security Systems, Utility Monitoring and Control System have a integration and implementation plan ensuring operation with existing systems and equipment.