About this file

This document contains questions and answers related to solicitation number FA5209-19-R-A006 for an Indefinite-Delivery/Indefinite-Quantity Multiple Award Construction Contract to provide general construction services at U.S. Army and Air Force installations in Honshu, Japan and Yokota Air Base. The solicitation seeks proposals from contractors to award up to ten contracts with a minimum value of $2,000 each and a maximum combined value of $990 million over a one-year base period and nine one-year options. A pre-proposal conference will be held on June 13, 2019 to discuss the solicitation and conduct a site visit. Questions are due by June 7 and June 20, and Past Performance Questionnaires are due by June 28. Initial proposals must be submitted by July 10, 2019. The answers provided extend the proposal due dates by two weeks to June 15 for questions and to June 15 for Past Performance Questionnaires in response to contractor requests.

View the file

Other files

File Type Posted
FA520919RA006 Amendment 0006.pdf PDF
23 RFP Atch J4a(PPQCoverletter) Amend 0006.pdf PDF
1. The MACC Pre-proposal Conference Briefing Slides.pdf PDF
Pre-proposal Conf Minutes FA520919RA006 - 18 May 21.pdf PDF
27 Atch J7a Question No. 48 Geotechnical Investigation Report for B906.pdf PDF
21 RFP AtcJ3d13_B907LeadPaintReport.pdf PDF
4 Atc J2b AFGP.pdf PDF
1 Solicitation Amendment - FA520919RA0060005.pdf PDF
25 RFP Atch J5 EnvelopeLabel(OF-17).pdf PDF
16 RFP AtcJ3d8_B907AsBuilt (Sprinkler).pdf PDF
23 RFP Atch J4a(PPQCoverletter) Amend 0005.pdf PDF
30 Atch J7d Question No. 38 MACC Mock Project Comm.jpg JPG image
12 RFP AtcJ3d4_B907AnnexAsBuilt.pdf PDF
19 RFP AtcJ3d11_B907AnnexConceptPlan(Com).pdf PDF
8.RFP AtcJ3c2(TaxExemp_Mock).docx DOCX document
22 RFP AtcJ3d14_AbestosSurveyReport.pdf PDF
13 RFP AtcJ3d5_B907AnnexAsBuilt(Elec).pdf PDF
9 RFP AtcJ3d1_Spec15011.pdf PDF
29 Atch J7c Question No. 40 AMRS spec.pdf PDF
17 RFP AtcJ3d9_B907AnnexDemoPlan.pdf PDF
10 RFP AtcJ3d2_EnvProtection.pdf PDF
11.RFP AtcJ3d3_DispRec.xlsx XLSX spreadsheet
15 RFP AtcJ3d7_B906AsBuilt.pdf PDF
5 RFP AtcJ3a MockSOW.pdf PDF
6 RFP AtcJ3b(SOW Addendum).pdf PDF
28 Atch J7b Question No. 33 Fire Alarm B907 Annex.pdf PDF
14 RFP AtcJ3d6_B907AnnexAsBuild (Arch).pdf PDF
26 RFP Atch J6 QAs - FA520919RA006.pdf PDF
24 RFP Atch J4b(PPQ).docx DOCX document
18 RFP AtcJ3d10_B907AnnexConceptPlan.pdf PDF
3 Atc J2a ArmyGP.pdf PDF
2 Atc J1 Other Req 30 Apr 21.pdf PDF
7.RFP AtcJ3c1(MockSectionB).xlsx XLSX spreadsheet
20 RFP AtcJ3d12_B907WaterFlowTR.pdf PDF
RFP_Atch_J5c_3rdQ&A.XLSX XLSX spreadsheet
RFP_Atch_J4a(PPQCoverletter)(rev2).pdf PDF
Amend0004.pdf PDF
1_Amend0003.pdf PDF
4_RFP_Atc_J-5b_2ndQA.XLSX XLSX spreadsheet
1_Amend0003.pdf PDF
2_Ament2_Atc_J1_Other_Req.pdf PDF
3_RFP_Atc_J-5a_1stQA.XLSX XLSX spreadsheet
25_EnvelopeLabel(OF-17).pdf PDF
Amend0002.pdf PDF
Atch_1_Attendance_List.pdf PDF
Atch_2_MACC_PreProposalSV_Briefing_Slides.pdf PDF
Pre-proposal_Site_Vist_Conf_Minutes.pdf PDF
25_EnvelopeLabel(OF-17).pdf PDF
Amedment_0001.pdf PDF
23_RFP_Atch_J4a(PPQCoverletter)(rev).pdf PDF
Show 40 more

Latest 50 of 66 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

No. reference Questions (Should include Specification Section or Drawing Reference) Answers

1 SF1442 amendment Please provide for amendment document 001 to 004. In order to avoid any confusions, the Amendment 0005 has been issued in form of "Conformed Document" for providing the latest information to all offerors. Therefore all changes have been incorporated from previous amendments. Please submit another request to the Government should you wish for which changes were incorporated under each amendment.

2 term of solicitaion At least 2 more weeks is required for integration of calculation.

Is it possible to extend the RFP closing date?

RFP close date has been extended for 2 weeks, from 1 Jun 21 to 15 Jun 21. Please see the amendment 0006.

3 General Provisions

1.19 Key Personnel Clarifications

Regarding QCM and SSHO, due to the influence of COVID- 19,NAVFAC provided QC and SSHO trainings have not been conducted at the moment and qualifications of some our QCM and SSHO have been expired. Since many construction locations are included in this solicitation, we are concerned about the insufficient numbers of certified QCM and SSHO.

In that case, can we possible to negotiate with the Government about construction schedule and qualifications

The certification of QCM shall conform to the paragraph 1.19.3 SECTION 01 11 10 of Army General Provisions.

The CQC manager shall have a minimum of five (5) years of similar work experience as a CQC Manager on Construction quality control similar to this contract, and 1st Class Certified Construction Engineer (1 kyu Sekou Kanri Gishi) which is applicable discipline of task order project.

Per paragraph 1.19.4, b SECTION 01 11 10 of Army General Provisions, the Japan Construction Occupational Safety and Health Association (JCOSHA) provides the construction safety course "Kouji Shunin" or "Course for Construction Site Managers", which is an acceptable equivalent to the 30 hours OSHA Construction Safety Course.

4 23 RFP Atch J4a(PPQCoverletter) Amend 0005

Regarding PPQ attachment J-4, government requested response by 1st June 2021.

Is it possible to extend the response date for 2 weeks?

PPQ close date has been extended for 2 weeks, from 1 Jun 21 to 15 Jun 21. Please see the amendment 0006.

QUESTION & ANSWER FORM

FOR

FA520919RA0060005

Indefinite-Delivery/Indefinite-Quantity (IDIQ) Multiple Award Construction Contract (MACC), U.S. Army Installations within Honshu, Japan and Yokota Air Base and its Geographically-Separated Units (GSUs), Japan

File details come from the government source that posted it. Updated .