QA_FA489726Q0025 Renovate Base Chapel (002).pdf

PDF 262 KB Posted

Attached to
Renovate Base Chapel
Solicitation number
FA489726Q0025
Issued by

About this file

This document is a Questions and Answers (Q&A) file for federal contract FA489726Q0025 concerning the renovation of Building 2606 (Base Chapel) at Mountain Home Air Force Base. The solicitation is for design-build services requiring offerors to submit comprehensive quotes by August 24, 2026, covering all Statement of Work (SOW) items and applicable specifications with no design/plan submission required at the quote stage. Detailed design and project plans must be submitted after contract award, with deliverables due at 30%, 60%, 90%, and 100% design milestones, each stamped by a professional engineer. The total contract performance period is 550 calendar days following Notice to Proceed and encompasses both design and construction phases across two 180-day construction phases while the facility remains occupied.

Key project scope includes: HVAC system replacement in Room 111 (hydronic boiler/AHU system with options proposed at 30% design); complete roof replacement (26 squares TPO and 126 squares metal); LED lighting facility-wide replacement; new glazing per UFC 4-010-01 blast-resistant standards; fire alarm/mass notification system replacement (Silent Knight EVS sole-source); fire suppression system facility-wide; new 300 kVA transformer; hazardous materials abatement (ACM, lead, chlordane, mercury, PCBs); structural repairs including glulam beam replacement at patio cover; and mechanical room reconfiguration. Design services, including required in-person design review meetings at Mountain Home AFB, are priced within CLIN 0001. No bid guarantee or performance bond is automatically required for commercial items acquisition under FAR 52.212-1; however, this construction contract requires a bid bond (20% of bid price or $1,000,000 whichever is lower) and performance/payment bonds per RFO Part 28. Quotes must remain firm for 90 calendar days, with an option to revise if funding extends beyond 90 days post-submission. Design milestones are payable as progress against the approved schedule of values with no retainage assumed. Government review will not provide advance timing guarantees, but minimum two-week notice is required for all notifications and 45 days for nuclear density gage testing if needed. The facility must remain operational throughout construction with blackout periods every Sunday, Holy Days, and specified holidays through December 2027 during which construction disturbance shall be non-existent; weekend and after-hours work is permitted at contractor expense.

View the file

Other files

File Type Posted
Solicitation Amendment FA489726Q00250009 SF 30.pdf PDF
Solicitation - FA489726Q00250009.pdf PDF
Solicitation - FA489726Q00250008.pdf PDF
Solicitation Amendment FA489726Q00250008 SF 30.pdf PDF
Solicitation Amendment FA489726Q00250007 SF 30.pdf PDF
Solicitation - FA489726Q00250007.pdf PDF
Solicitation Amendment FA489726Q00250006 SF 30.pdf PDF
Solicitation SF1442 - FA489726Q00250005.pdf PDF
Solicitation Amendment FA489726Q00250005 SF 30.pdf PDF
Site Visit Attendance.pdf PDF
Solicitation - FA489726Q00250005.pdf PDF
Chapel Second Site Visit Attendee List.pdf PDF
Solicitation Amendment FA489726Q00250004 SF 30.pdf PDF
Solicitation - FA489726Q00250004.pdf PDF
Solicitation Amendment FA489726Q00250003 SF 30.pdf PDF
Solicitation Amendment FA489726Q00250002 SF 30 (1).pdf PDF
6.1.5.1 100P Design Drawing Set - Mountain Home Chapel Kitchen Renovation2.pdf PDF
FA489726Q00250001 SF 30 Solicitation Amendment 1.pdf PDF
6.2.2. Specifications_B2606 Fire Alarm Repair.pdf PDF
Solicitation - FA489726Q0025.pdf PDF
6.2.1. Drawings_B2606 Fire Alarm Repair.pdf PDF
SOW_Renovate Base Chapel_B2606.pdf PDF
6.3.1.Base Design Guide Data Sheet-MHAFB DESIGN STANDARDS 2026.pdf PDF
6.1.5. 100 Design Drawing Set - Mountain Home Chapel Kitchen Renovation1.pdf PDF
6.2.3.DA_B2606 Fire Alarm Repair.pdf PDF
DBA ID20260020 05182026.pdf PDF
6.4.1.Specs Intact file - 4.2_01 57 19_MHAFB Env Spec 20220614.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers FA489726Q0025 – B2606 Renovate Base Chapel

1. Can you provide me with a copy of the roofing/waterproofing specifications or direct me to where I can find them?

a. https://www.wbdg.org/dod/ufgs This location has all general guide specs that are editable and are required to incorporate all DoD roofing guidance.

b. https://digital.wbdg.org/versions/78810376-2a03-49cb-b029-086ff48ce1c8 This location is a general roof guidance for DoD that has our two roof styles.

Notice the additional UFC references within the UFC 3-110-03.

c. https://nibs-s3-wbdg3-production.s3.us-east- 1.amazonaws.com/FFC/AF/AFIFS/MHAFB_IFS_Final.pdf This location has additional guidance specific to Mountain Home AFB

2. Confirming existing fire alarm system to be completely removed and replaced.

Current occupancy will allow for no system to be in place during construction – or will we be required to have the system operational during construction?

a. The system will be permitted to be off line throughout the duration of both phases 1 & 2 of the project.

3. Confirming you do not want the existing brick planter to be demolished – only weatherproofed per the SOW document.

a. Confirmed. See SOW para 3.2.2.2.5. Exterior, brick planter outside window 102A. Do not demolish the planter. Do repair the planter per SOW.

4. The SOW states to propose new system options to replace the boiler, tank, and pump in Room 111. The next page states to demolish AHU-1 and AHU-2. The outdoor units also state are to be demolished. Confirming that the new mechanical system is a design build and seeking clarification as to whether or not that design is to be submitted as a package on 24 Aug 2026 or if we are supposed to price the system and deliver plans by the 30% milestone if selected as the GC?

- No designs are required with your submission package. Price the system and deliver the plans by the 30% milestone (or whichever time is directed by the SOW if stated differently).

5. Do you want the abatement included in the Sustainment and Repair number or separate from that number?

a. Split the abatement cost that is associated with the Sustainability work and include that abatement breakout cost with the Sustainability cost.

https://www.wbdg.org/dod/ufgs https://digital.wbdg.org/versions/78810376-2a03-49cb-b029-086ff48ce1c8 https://nibs-s3-wbdg3-production.s3.us-east-1.amazonaws.com/FFC/AF/AFIFS/MHAFB_IFS_Final.pdf https://nibs-s3-wbdg3-production.s3.us-east-1.amazonaws.com/FFC/AF/AFIFS/MHAFB_IFS_Final.pdf

b. Split the abatement cost that is associated with the Modernization and Repair work and include that abatement breakout cost with the associated with the Modernization and Repair cost.

6. I am not finding the as-built drawings listed in the SOW on the SAM.gov site – how would I access those documents?

- Please send a request directly to the listed Contracting Officers

(jeremiah.burns.1@us.af.mil, natasha.lizama.1@us.af.mil) for any missing/unprovided documentation.

7. Would you be able to clarify what is required for submission? My design team has asked if a set of plans for the project along with budgets is what is required or if you want a hard number for the SOW items and our plans would follow that?

- There is no design/plan submission required with your quote. Quotes should be comprehensive, meaning your price shall cover all SOW items and applicable specifications. Plans are not required at this stage. Detailed design and project plans are to be submitted after the contract is awarded.

- Formatting and Content: There is no required format or content other than completing page 2 of the solicitation document (Standard Form 1442). However, quotes will be evaluated based on the factors listed in clause 52.212-2 (on page 37 of the solicitation document). You may submit any documentation necessary to demonstrate superior quality and past performance.

8. Is there a bid form that is required for submission?

- There is no required format or content other than completing page 2 of the solicitation document (Standard Form 1442). However, quotes will be evaluated based on the factors listed in clause 52.212-2 (on page 37 of the solicitation document). You may submit any documentation necessary to demonstrate superior quality and past performance.

9. The solicitation states that funds are not presently available for this effort and no award will be made under this solicitation until funds are available. What exactly is required on 24 Aug 2026 – assuming each GC is to submit a preliminary set of plans with estimates of the proposed work for consideration? Or are we to submit a number to complete the work without a plan set for the work described in the SOW?

Meaning, is the base looking for cost estimates to determine if the project will move forward or is this a hard bid situation that will be awarded in the future based on the submitted number if the project moves forward.

mailto:jeremiah.burns.1@us.af.mil mailto:natasha.lizama.1@us.af.mil

- The government is not looking for cost estimates to determine if the project will move forward. The decision to move forward will be based solely on Department of War prioritization and availability of funds.

10. Section M identifies Past Performance as an evaluation factor but does not state a recency period, a required number of references, or a relevancy standard. Absent direction, offerors intend to submit up to three (3) projects completed within the past seven (7) years that demonstrate renovation of an occupied, continuously operating facility of comparable complexity. Please confirm this approach is acceptable. Section M, FAR 52.212-2(a), p.37

- Recency – defined as 6 years for construction contracts.

- Relevancy – must demonstrate renovation of an occupied, continuously operating facility of comparable complexity.

11. Please confirm the Government will consider past performance where the offeror performed as a first-tier subcontractor, as well as the relevant performance of proposed teaming partners and the design partner, as this experience is directly applicable to the requirement. Please also confirm that previously completed PPQs may be submitted where the same project has already been evaluated by the client.

Section M, FAR 52.212-2(a), p.37

- The government will consider past performance where the offeror acted as a first-tier subcontractor. However, the government is not obligated to consider past performance of “proposed” teaming partners unless an official teaming arrangement, letter of commitment, or letter of intent can be provided by the proposed teaming partner or subcontractor. Previously completed PPQs may also be submitted.

12. Section M does not identify a required past performance submission format. Please confirm the Government will rely on CPARS and SPRS records where available, and that where CPARS is not available the offeror may substitute a completed PPQ or a client reference letter. Section M, p.37; DFARS 252.204-7024, p.35

- Confirmed. The government will rely on CPARS, SPRS records, or any other reasonably available method at its disposal to evaluate past performance.

13. Section L does not prescribe a volume structure, page limits, or a delivery method.

Please confirm that offerors may organize the submission at their discretion — proposed as separate Quality, Past Performance, and Price volumes — that no page limitation applies, and that electronic submission in PDF by email to the Contracting Officer and Contract Specialist satisfies the requirement in SF 1442 Block 13a. Section L, p.35; FAR 52.212-1

- Confirmed. Offerors are granted broad latitude in how they organize their submission. However, all requirements, terms, and conditions dictated within the 1442 must be acknowledged and satisfied (i.e. acknowledgment of amendments, bid guarantees, offer acceptance period, price, offeror information, reps and certs, etc.)

14. The solicitation describes the requirement as construction only (SF 1442 Block 10, CLIN 0001), while SOW paragraph 3.2 requires a Design-Build effort with 30%, 60%, 90%, and 100% for-construction submittals stamped by a professional engineer.

Please confirm the SOW governs. Please also confirm whether design services, including the required in-person design review meetings at MHAFB, are to be priced within CLIN 0001 or established as a separate line item, and confirm that design deliverables are payable as progress payments upon Government acceptance of each milestone. SF 1442 Block 10, p.1; Section B CLIN 0001, p.4; SOW paras 3.1 and 3.2

- SOW governs in this instance. There are portions of work requiring construction only (design is provided by the government), and portions of work requiring design-build.

- Design services are to be priced in CLIN 0001. CLIN 0001 should include comprehensive pricing, inclusive of all statement of work and specification requirements.

15. SOW 3.2.1 requires a professional engineer on staff with a minimum of 10 years' experience in all disciplines associated with the work. Please confirm this may be satisfied by the offeror's design team collectively — a licensed Engineer of Record supported by discipline-specific licensed engineers — rather than by a single individual holding 10 years in every discipline. Please also confirm that identifying the A/E firm at time of offer by teaming agreement or letter of intent is sufficient, with individual resumes, licenses, and stamps provided after award. SOW paras 3.2.1, 3.2.1.1; Section M, p.37

a. Confirmed, “a licensed Engineer of Record supported by discipline-specific licensed engineers — rather than by a single individual holding 10 years in every discipline.”

b. Para 3.2.1.1 is the Design portion of the Design-Build technical evaluation prior to award but after offers are submitted. This is a general statement made in reference to section M.

c. A letter of intent or teaming agreement at the time of offer is sufficient.

d. Para 3.2.1 is a performance requirement and is applicable after award.

e. Para 3.2.1.1 is an evaluation factor to be considered for award and should therefore be submitted with the offeror’s quote.

16. Section M evaluates the qualifications of the proposed project manager, superintendent, engineer, and architect but does not state minimum experience levels or required certifications. Please confirm that no minimum thresholds apply beyond those stated in the SOW, that an individual may serve in more than one role where qualified, and that only these four roles are evaluated — with the Site Safety and Health Officer and Quality Control Manager identified after award. Section M, FAR 52.212-2(a), p.37; SOW para 4.7

a. Minimum required certifications for the A-E firm and design deliverable is stated in the SOW. Professional seal for the entire design submittal package.

b. It is recommended that the PM have 2years min on government projects of similar size and scale. PM should have a construction management degree or better or experience equivalent to the 2-year period and degree.

c. The QC Manager must be an individual with a minimum of 10 years combined experience in the following positions: Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction Contracts which included the major trades that are part of this Contract. The individual must have at least 2 years experience as a QC Manager. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification, safety compliance, and sustainability

d. The Contractor Quality Control (CQC) System Manager and Alternate CQC System Manager are required to have completed the Construction Quality Management (CQM) for Contractor’s course. If the CQC System Manager's certificate has expired, retake the course to remain current.

e. This project has several disciplines with multiple crews working simultaneously. Dual hatting for the QCM as the superintendent should be very limited and as a temporary substitution for no more than 5 consecutive days and not more than 3 occurrences in a 1-year period. The superintendent may temporarily serve a dual role as QCM for no more than 5 consecutive days and not more than 3 occurrences in a 1-year period. The Superintendent and QCM may dual hat as SSHO if both are qualified as

SSHO.

f. SSHO minimum requirements,

i. certified in the OSHA 30 Construction safety course, and

ii. 5-years of construction/industry safety experience or 3 yr CSP or safety and health degree and

g. Design specification will be reviewed for the above recommendations, and must have the provision for alternate CQC staff (QCM, SSHO, Superintendent) for the primary personnel unable to perform their assigned roles that may exceed 5 consecutive days and 3 occurrences within a 1-year period.

17. SOW 3.2.2.1 requires HAZTOX sampling, analysis, and abatement of all suspect materials (ACM, lead/TCLP, chlordane-contaminated soils, mercury, PCBs), with sampling performed after award but abatement required before any other work may proceed. Quantities and concentrations are therefore unknown at the time of offer.

Offerors request that the Government establish a not-to-exceed allowance or a separate bid item for abatement so that all offers are priced on a common basis. If no allowance is established, please confirm that conditions or quantities exceeding those disclosed in the solicitation will be addressed by equitable adjustment to price and period of performance. SOW paras 3.2.2.1, 4.3.1

- Conditions/quantities exceeding those disclosed in the solicitation, and conditions not reasonably discovered during the contractor’s site investigation, will be treated as unforeseen site conditions as appropriate. Contractors should quote to conditions that are known at the time solicitation. Unforeseen site conditions that arise following quote submission will be reviewed and addressed by equitable adjustment.

18. SOW 3.2.2.13 directs removal of the entire steam system and replacement with a hydronic system or packaged unit(s), with options to be proposed at the 30% design milestone. Since the system type is undetermined at time of offer, please confirm that offerors may price a stated basis of design and identify it in the proposal, and that a Government-directed selection of a different system at the 30% milestone will be addressed by equitable adjustment.

a. “with options to be proposed at the 30% design milestone” – Is intended to clean up unnecessary duct work, lines, wires, or supports for the new equipment and overall system.

b. offerors may price a stated basis of design and identify it in the proposal, and that a Government-directed selection

c. Scope of Work is to deliver hydronic boiler/AHU system.

d. Alternate systems at 30% are welcomed; if the alternate system after the

30% review is determined to be a benefit to the government, the system may be approved, or not.

e. Recommend the design of the alternate system include initial cost, expected life cycle, replacement cost, operations and maintenance cost, salvage cost (if applicable) for review and determination at the 30% design milestone.

19. SOW 3.2.2.5 provides approximate roof quantities (26 squares TPO to be replaced with fully adhered PVC; 126 squares metal to be replaced with new metal) and states design criteria shall be determined by the contractor per UFC 3-110-03.

Please confirm these quantities are Government-furnished for pricing purposes, and confirm that replacement or structural reinforcement of the existing 1/2-inch sheathing deck noted on the 1990 as-built (Sheet A-8), if required by code or discovered during demolition, is outside the base scope and will be addressed by equitable adjustment. SOW paras 3.2.2.5, 3.2.2.5.1, 3.2.2.6, 3.2.2.7

a. The quantities for square are approximate and for bidding purposes only.

b. The decking was observed to be wood sheathing on Phases 1 and 2 from inside the building looking up. No observations were available on phases 3 and 4.

c. Roof sheathing appears in some as built drawings, see also answer to question 21 below for As built drawings.

20. SOW 2.2 requires the chapel to remain open and occupied across two 180-day construction phases, and 2.2.6 lists recurring blackout periods (every Sunday plus Holy Days and holidays through December 2027) during which construction disturbance shall be non-existent. Please confirm that Saturday and after-hours work is authorized at no additional cost to the Government to maintain schedule, and confirm that the blackout periods in 2.2.6 — together with any additional special events or operational restrictions directed after award — constitute excusable delay that will not count against the 550-calendar-day period of performance or result in liquidated damages. SOW paras 2.2, 2.2.5, 2.2.6; FAR 52.211-12, p.17

- Weekend and after-hours work can be coordinated ahead of time if required.

However, the decision to perform work after hours is the contractor’s and the government will not be liable for additional associated costs.

- Blackout periods listed in para 2.2.6 should be accounted for and do not constitute government-caused delays. Any additional special events or restrictions directed after award will be coordinated ahead of time and may constitute government-caused delays, which could provide the contractor with additional time/compensation.

21. SOW 6.1 lists the 1955, 1958, 1966, and 1990 as-built drawing sets as available upon request. Please provide all as-built sets, the MHAFB AutoCAD .dwt template and layer states, and the specs-intact .SEC files referenced in paragraphs

3.2.1.4.1.2 and 3.2.1.4.2.2 as soon as practicable and extend the question deadline accordingly if they are released after 7 Aug 2026. Please also confirm the as-built drawings are provided for information only and that existing conditions materially differing from the as-builts will be addressed by equitable adjustment. SOW paras 6.1, 6.3, 6.4; Section J attachment list, p.27

- All documents listed “available upon request” must be requested via email to the listed contracting officers in the SAM.gov solicitation post.

22. The solicitation indicates that funds are not presently available for this award.

Please confirm whether FAR 52.232-18, Availability of Funds, applies and identify the anticipated fiscal year and date of funding availability. Please also confirm the Government's anticipated award date, the period for which offerors will be required to hold pricing firm (proposal acceptance period), and that the Government will permit offerors to revise price prior to award — or issue an amendment allowing revised pricing — if award occurs more than 60 calendar days after the 24 Aug 2026 submission date, given current escalation in materials and subcontractor pricing over a 550-calendar-day period of performance. SF 1442 Blocks 12/13a, p.1;

Section B CLIN 0001, p.4; FAR 52.232-18; FAR 52.212-1(c)

- 52.232-18 does not apply. The government is aiming to award this calendar year

(FY26) but that is based on availability of funds. If funds are not received this fiscal year, the government may award early FY27 (based on availability of funds and quote validity).

- Quotes must be good for 90 calendar days. If funding is received more than 90 days following receipt of quote, offerors will be given the chance to review/revise their quotes.

23. Existing drawings (Structural): Will we have access to the 1955, 1958, 1966, and 1990 roof/HVAC record drawings, including Sheet A-8 referenced for the patio-cover glulam beam and roof framing?

a. All available As-Built drawings are available, see also answer to question 21 above for As built drawings.

i. Roof and GluLam – See zip file 1.4_Base Chapel Repair Roof_HVAC.zip for MHAFB-DV-10965 (A-6) through MHAFB-DV-10968

(A-9) on are currently the only drawings available. There are details for the glu lam beam and adjacent members.

ii. See zip files for all other available as built drawings:

• Original Construction “1.1_Org CNS 22APRIL1955 AsBuilt.zip”

• 1958 Addition – “1.2_ADD1 11DECEMBER1958 AsBuilt.zip

• 1966 Addition – “1.3_ADD2 22APRIL1966 AsBuilt.zip”

• 1990 Repair Roof/HVAC – “1.4_Base Chapel Repair

Roof_HVAC.zip

• 2018 Kitchen remodel, FAC 2606 – “1.5_Chapel Kitchen

Renovation, B2606”

24. Existing-building evaluation (Structural): Is the structural scope limited to the elements directly modified by the project, or is a broader evaluation of the existing roof, floor, foundation, diaphragm, or lateral-force-resisting systems required?

a. Yes, LFR is required where additions and alterations affect load bearing components of the facility, all in scope work.

b. Current code applies to all load bearing additions and alterations. A design analysis with a narrative and calculations at each design milestone, based upon and citing current codes and requirements as of the 35% Design milestone. IBC, AFI, and UFC are required.

c. Example, raising the height of railing per SOW para 3.2.2.8.12 not a load bearing element, but code for railing height is a code requirement. No calculations may be needed but the Design analysis will need to touch on why the railing needs to be modified per code and what is proposed athletically. If the Design analysis is not sufficient for any design milestone, GOV review comments will indicate the missing data.

d. Example, SOW para 3.2.2.4 GLB carries a load from several, point load components, transferring the load to the columns to the foundation to the soil, all load bearing, all require a design analysis with the narrative and calculations, and proposed work. If the Design analysis is not sufficient for any design milestone, GOV review comments will indicate the missing data.

e. The responsibility for all codes and requirements fall upon the stamped Design and the elements listed in the SOW para 3.2.1. The Design analysis is required to include a full structural analysis as determined by the DOR as described in the SOW.

25. Glulam beam (Structural): Is the structural engineer expected to evaluate only the replacement beam, connections, and existing columns, or the complete patio-cover system, including roof framing, column bases, and foundations?

a. Scope of work includes a design build for the Beam and all load bearing element related to the beam. The design analysis will need to account for all loading on the beam and how it will be transferred through the beam, to the columns and foundation for review and approval.

b. The SOW assumes the design analysis will account and allow for the reuse for the existing metal columns. If new columns are required as a result of the design analysis, the new columns may be determined as a change in condition. For bidding purposes, inspect, refurbish, and reuse existing metal columns.

c. The concrete for the patio is in scope for a new finished surface to match exterior door thresholds at the patio and is in scope for the design analysis that will support the beam. The concrete foundation at the bottom of the column will also be load bearing.

26. Temporary shoring (Structural): Should shoring for the glulam replacement be designed by the structural engineer of record, or delegated to the contractor’s specialty engineer?

a. Means and methods, the responsibility of the Design is on the contractor, not the Government. The A-E firm hired for the project holds the responsibility for all aspects of the Design to include but not limited to temporary shoring and safety.

b. See SOW 3.2.1 Design for design requirements. The design analysis, specs and drawings will be reviewed for the determination for the temporary shoring. All code, to include but not limited to, USACE EM 385 safety requirements, all relevant UFC and IBC requirements is a requirement of the design is the responsibility of the DOR during the design phase, and the responsibility of the prime contractor throughout the entire duration of the project including Design, not the Government.

27. Roof scope (Structural): Is the structural scope limited to reviewing the new roof dead load, roof-deck condition, localized deck repairs, and wind-uplift attachment criteria, or is a complete evaluation of the existing roof framing and diaphragm required?

a. See UFC 3-110-03 which refers to additional UFC requirements for roof type.

b. If the decking or structural members are no longer sufficient beyond the 240-square-foot decking, the insufficient materials may be determined as an unforeseen condition.

28. Roof-deck repairs (Structural): Is the 240-square-foot deck replacement quantity a firm limit or an allowance? If deterioration exceeds that amount or extends into the supporting framing, will the additional design be handled as an added service or contract modification?

a. For bidding purposes, assume the 240 square-foot deck is in scope. Any additional work to address insufficient and unsuitable materials to include but not limited to roof deck (and supporting framing) beyond the quantity of 240 square-foot decking and will be understood to be a change in condition.

29. Exterior concrete (Structural): Will the Government or design-build team provide a topographic survey and geotechnical design information for the new landings, ramps, steps, and walkways?

a. No. This is a Design Build contract. If the DOR requires survey information the existing conditions are available presently and after award; field investigation and verification are means and methods.

b. The most current ABA, Architectural Barriers Act up to the 35% Design milestone is a requirement.

c. Note, pesticide contamination is suspect. See SOW para 3.2.2.1.2.4.3. Soil testing for pesticides and the MHAFB Environmental Specifications

6.4.1 Specs Intact file – “4.1_01 57 19_MHAFB Env Spec

20220614.SEC”

6.5.2 pdf file – “4.2_01 57 19_MHAFB Env Spec 20220614.pdf” (upon request)

30. Civil/structural division (Structural): Please clarify the division of responsibility for exterior grading, drainage, walkway and ramp geometry, concrete reinforcement, foundations, retaining conditions, and railing anchorage.

a. The A-E and DOR should be capable and competent for making these determinations, see also answers to question 29 above.

b. The drawings typically include walk ways and drainage in the C discipline. A Table of Contents for the specification is required at the 30% Design milestone and all is submitted for review and approval by the GOV.

c. It appears the elements listed belong to Civil but that is not a formal direction to the DOR which has the final determination to propose for GOV review and comments.

31. HVAC support (Structural): Should the structural proposal include evaluation and design of equipment supports, pads, anchorage, mezzanine or floor framing, penetrations, and localized reinforcing for the selected HVAC system?

a. Yes.

32. Fire-suppression system (Structural): Will sprinkler supports and seismic bracing be delegated to the fire-suppression contractor, with structural review of attachments, or is the structural engineer expected to design and verify supports throughout the building?

a. The responsibility for the loading of all elements for the work falls upon the A- E firm and the DOR, see also all UFC and IBC requirements will be reviewed in the design analysis and should be determined by the Designer of record (DOR) means and methods.

b. Structural design falls upon the DOR.

c. Sprinkler coverage and all fire suppression elements must be included in the final design prior to the construction phase and must be endorsed by a professional engineer for fire protection (FPE).

33. Field investigation (Structural): Will limited destructive investigation and access to concealed framing be permitted, and will hazardous-material clearance be completed before structural investigation?

a. In terms of “clearance” Hazardous materials identification, testing, and handling is to be performed by authorized personnel only that are employed with a firm that specializes in the areas of all suspected hazardous materials.

b. Pre-bid destructive testing will be allowed if the specialty firm as described above (33.a.) must be hired by the prime contractor. The damage(s) to finishes caused by the destructive sampling must be patched and matched to include corner to corner finishes.

34. Deliverables and construction services (Structural): Please confirm the required structural design milestones, whether separate structural drawings and calculations are required, and the anticipated number of structural site visits and construction-phase reviews to include in the proposal.

a. Government review for each of the 30-60-90 percent Design package submittals, for each design submittal milestone, will include all disciplines required to complete the project in its entirety.

b. There are no limits to onsite visits.

c. The recommended schedule for all design submittals for all disciplines of the project is scheduled on page 24 para 5 of the SOW.

d. Design Deliverables

A. 30% Design

a) Drawings – (2) 11 x 17 hardcopy, (1) 22 x 34 hardcopy, (1) AutoCad “.dwg” and (1)“.pdf” files.

b) Specification – (1) 8-1/2 x 11 hardcopy, and (1) “.pdf” file of complete specifications TOC.

c) Design analysis – (1) 8-1/2 x 11 hardcopy, and (1) “.pdf” file.

e. B. 60%-90%-Final Design

a) Drawings – (2) 11 x 17 hardcopy, (1) 22 x 34 hardcopy, (1) AutoCad “.dwg” and (1) “.pdf” files.

b) Specification – (1) 8-1/2 x 11 hardcopy, (1) and (1) “.pdf” file of complete specifications.

c) Design analysis – (1) 8-1/2 x 11 hardcopy, and (1) “.pdf” file of complete specifications.

35. Wooded Handrail and Stairs (Architectural): During the site visit, the existing guardrail and wooden stairs serving the mechanical loft were observed to appear noncompliant with current code requirements. The Scope of work currently identifies replacement of guardrails and handrails at the chapel pulpit and exterior locations; however, no work is identified for the mechanical loft stair or guardrail.

Please clarify whether this condition is to remain unchanged or if the Government intends to include modifications as part of this project.

a. If the work area such as the mechanical room (see also in non compliant, the work area must be made compliant.

b. All aspects for UFC, IBC, apply.

c. The noncompliance “for the mechanical loft stair or guardrail” are a requirement of the contract, as the entire mechanical room is in scope.

36. | Electrical | Sec. 9 | Does the Government require an arc flash hazard study and equipment labeling for the new 400A MP1/MP2 panelboards and 300 kVA transformer, given this is not explicitly scoped in the SOW?

The USG will require the following studies in EasyPower Modeling Software after switchgear is identified and prior to procuring switchgear equipment.

a) Power Flow

b) Short Circuit

c) Arc Flash

d) Coordination

e) Reliability

37. | Electrical | 3.2.2.13.1 | Please confirm existing branch circuit wiring throughout the facility may be reused except where a task element specifically calls for demolition (panels, transformer, fixtures).

a. Branch circuits may be reused; however, USG will not allow any splices for any circuits—if wiring / cables are too short, then wiring / cables need to be replaced

38. | Electrical / Fire Alarm | Sec. 10 | Please confirm firestopping responsibility (electrical subcontractor vs. general trades) for all trade penetrations through fire-rated assemblies.

a. This contract will not address any new firestopping through existing penetrations

b. New penetrations will need to incorporate firestopping.

39. | HVAC | 3.2.2.13.6 | Does the Government have a system preference (hydronic boiler/AHU vs. package units) for the Mechanical Room 111 replacement, or is the contractor’s recommended approach acceptable as proposed at 30% design?

a. Scope of Work is to deliver hydronic boiler/AHU system.

b. Alternate systems at 30% are welcomed; if the alternate system after the

30% review is determined to be a benefit to the government, the system may be approved, or not.

c. Recommend the design of the alternate system include initial cost, expected life cycle, replacement cost, operations and maintenance cost, salvage cost (if applicable) for review and determination at the 30% design milestone.

40. | HVAC | 3.2.2.13.7.1 | If R-32 refrigerant is unavailable for the contractor’s proposed equipment line, what alternate refrigerant and documentation will the Government accept?

a. The government has a strong preference for R-32 related to ongoing maintenance costs. R454 is the next alternate refrigerant that is acceptable.

41. | HVAC / Plumbing | 3.2.2.16.19.2 | Please confirm whether the Room 119 hot water heater relocation is HVAC subcontractor scope or plumbing subcontractor scope.

a. Relocation of the hot water heater in Room 119 is the responsibility of the general contractor to whom the project is awarded.

42. | HVAC | 3.2.2.13.7.3 | Does the WebCTRL/Automated Logic BAS expansion at the Building 1300 front-end server require a factory-authorized dealer, and if so, can the Government identify the current vendor of record?

a. The authorized Automated Logic vendor for the area is Clime-Tech Corporation in Boise, ID.

43. | Roofing | 3.2.2.6 / 7 | Please confirm the exact roof area square footage for both the TPO (approx. 26 squares) and metal (approx. 126 squares) roof systems referenced in the SOW.

a. Exact area is not provided by the GOV, contractor must field verify.

b. Roof access is available upon notification but the contractor must provide their own means to access the roof such as a ladder.

44. | Roofing / Structural | 3.2.2.4 | Please confirm the GLB replacement at the patio cover near Door 102 is intended as structural/carpentry scope rather than roofing scope.

a. Means and methods, ultimately DOR is responsible, however it is recommend the beam be included in the structural discipline.

45. | Fire Suppression | 3.2.2.12.6.1 | Please confirm whether full concealment of fire suppression piping is achievable in Room 104, or whether an exposed-pipe alternate should be priced.

a. Full concealment is preferred. Bid for full concealment and offer cost for exposed for credit back to the government.

46. | Fire Suppression | 2.7.6 (DA ref) | Please confirm the age, condition, and compatibility of the existing sprinkler system in Room 121 (Kitchen/Mechanical Room) intended for incorporation into the new facility-wide system.

a. Fire suppression was completed in 2018. System is in good condition. All current codes by the 30% Design milestone will apply to incorporate the exiting fire suppression system into the new fire suppression system.

b. For bidding purposes, the existing fire suppression system will only require minor modifications to initiate in tandem with the new design.

47. | Concrete | 3.2.2.3.5.4.1 | Please confirm whether soil testing and remediation for the pesticide-affected area near Door 104 is Concrete subcontractor scope or a separate environmental scope.

a. Pesticide testing notification, and handling is in SOW para3.2.2.1.

b. Contract requires the design specifications include the MHAFB specs SOW para 4.3 which requires an environmental protection plan preconstruction submittal that will address all environmental requirements including testing planning, reporting and disposal.

48. | Concrete / Structural | 3.2.2.2 | Please confirm which trade is responsible for demolishing the masonry wall and exterior planter at Door 102/125, since the SOW does not explicitly assign it to a specific trade.

a. The A-E and DOR should be capable and competent for making these determinations, see also answers to question 26.a. above.

b. It appears this work falls under Division 02 but the design is the responsibility of the DOR, means and methods not the government.

49. | Plumbing / Finish Carpentry | 3.2.2.16.9-10 | Please confirm whether ABA grab bars and restroom dispensers are Government-furnished or contractor-furnished, and if contractor-furnished, under which trade.

a. All ABA, IBC, and UFC requirements must be included, see SOW para

3.2.2.16 and para 4.

b. See also 29.b. above

c. The A-E and DOR should be capable and competent for making these determinations, see also answers to question 26.a. above.

50. | Finish Carpentry | 3.2.2.9.2 / 9.3 | Please confirm the floor vent systems serving Rooms 104 and 117 are non-functional and may be safely abandoned in place.

a. If the Design proposes to cap and abandoned, the contractor is responsible to field verify that the system is no longer in use, and that the proposed cap and abandon in place is included in the design for review. The proposed design may then be authorized upon the approval of the CO.

51. | Fire Alarm | 6.2 refs | Please confirm no material substitutions are anticipated to the completed Silent Knight 6820EVS-based fire alarm/mass notification design.

a. No substitutions shall be in lieu of Silent Knight EVS

52. | HAZTOX | 3.2.2.1 | Please confirm whether the 2018 hazardous materials survey of the Kitchen and Fellowship Hall #1 may be relied upon for those specific areas, or whether a full re-survey of those areas is required under this contract.

a. The existing surveys may be used but all suspect materials within the project limits are in scope.

b. The determination to test will require an EPP and a testing plan preconstruction submittal, see also SOW para 4.3.

53. | General / All Trades | 4.1 | Please confirm whether a formal, independent commissioning (Cx) process is required for this project, or whether system-specific testing (TAB, NETA ATS, NFPA 72/13 testing) by each installing subcontractor satisfies the Government’s requirements.

a. The system-specific testing (TAB, NETA ATS, NFPA 72/13 testing) by each installing subcontractor will satisfy the Government’s requirements.

54. | Structural / Finish Carpentry | 3.2.2.16.6.4 | Please confirm whether a hard-lid ceiling is acceptable in the reconfigured restroom area, or whether a suspended ceiling matching the rest of the facility is required.

a. Hard lid is up to the A-E and DOR.

b. Privacy will be a determining factor for the review of the design.

c. Each room should have a uniform ceiling type, throughout the entire space.

55. | Finish Carpentry / Plumbing | 3.2.2.15 / 16.19.1 | Please confirm the Government’s intended final configuration for Room 119 (lactation room vs. retained space for the relocated hot water heater), given the competing ABA space requirements between Rooms 116 and 118.

a. See SOW para 3.2.2.16.1 for minimal preferences. SOW is open for the Design team to propose floor plans for the possible configurations for the restrooms and lactation rooms.

b. The design will be considered and reviewed at the 30% review and commented on at 35% milestone for final configuration.

c. Hot water relocation is means and methods.

56. | Electrical | 3.2.2.13.2 | Reference replacement of the 300 kVA, 12470/120/208V main transformer. Please clarify: (a) is the new transformer contractor-furnished and installed, or Government-furnished; (b) the demarcation between base-performed and contractor work on the 12,470V primary side, including who de-energizes, switches, and reconnects the primary, and who furnishes and terminates the primary conductors to the transformer; (c) transformer configuration (pad-mount, unit substation, or vault) and whether the existing pad or housing is reused;

(d) the number and duration of permitted primary outages and whether 366 CES performs the cutover; (e) whether 300 kVA is fixed or the design minimum, and who bears the cost if the design load calculation requires a larger unit; and (f) whether the existing transformer is known or suspected to contain PCBs and whether its testing and disposal are within the contractor HAZTOX scope.

a. New transformer “T-2606” will be contractor furnished and installed with the following requirements:

1) Transformer Specs

a) 12,470-Volts / 7200-Volts Wye primary

b) 120-Volts / 208 Volts Wye secondary

2) Three (3) off/on switches (one for primary side A, one for primary side B, and one for transformer secondary side.

3) The four-position rotary switch mechanism shall not be selected for use.

4) Feed-Through with Lighting arrestors on the B Primary side while the A side is feeding the transformer.

5) Recommend oil-submersed bayonet fusing, gauges, pressure relief valve, drain valve, etc.

6) Recommend Cooper or Hitachi. USG does not recommend Howard or any other reconditioned transformer.

b. Demarcation point will be the SecTER box “JB-080” feeding the Chapel.

USG Electrical Shop will manipulate switches / elbows at JB-080. USG and Contractor will Lockout/Tagout JB-080. Contractor will own cables from JB- 080 to Transformer T-2606. Contractor shall provide all commissioning documents of the new Transformer T-2606 to USG before commissioning.

c. Pad mounted transformer is required. Existing pad may be re-used if appropriately sized.

d. No restriction other than 2-weeks notice so that USG can route outage request to affected customers

e. The electrical sizing of the transformer is the Contractor’s responsibility, along with appropriate studies (defined in (a) above).

f. Existing transformer does not contain PCB; however, the Contractor is responsible to verify absence of PCB by testing.

57. | Electrical | 3.2.2.11 / 3.2.2.14.1 | The facility-wide LED lighting replacement is a Design-Build element with no fixture schedule provided, and AutoCAD as-builts are furnished only after award per SOW 4.10. To allow consistent pricing across offerors, will the Government provide an existing lighting fixture inventory or a room-by-room area schedule for Building 2606? If not, please confirm offerors should price the relight on a Design-Build basis using field-verified existing fixture counts and UFC 3-530-01 illuminance criteria, replacing in kind with LED 4x4, 2x4, and recessed can fixtures, and confirm the expected extent of facility-wide emergency and egress lighting.

a. It is the Contractor’s responsibility to estimate number of lighting for their proposal. The site visit provided an opportunity to identify number of existing fixtures. the design-build portion will determine number as per luminance study and determine what type of LED to incorporate. Facility-wide emergency lighting and egress lighting should be determined by design-build with appropriate studies/calculations.

58. | Fire Suppression | 3.2.2.12 | The new Design-Build fire suppression system covers the entire facility, but no hydrant flow test or existing fire service size is provided.

Please provide the most recent hydrant flow test data serving Building 2606 and the existing fire service line size, so offerors can determine whether the water supply is adequate or a fire pump and new fire service tap must be carried.

a. It is the contractor’s responsibility to conduct a hydrant water flow test.

59. | Fire Alarm | 2.7.5 (DA) / 6.2 | The FA/MNS is sole-sourced as Silent Knight EVS and must report to the MHAFB AES IntelliNet 2.0 base-wide monitoring system via a compatible radio transmitter and VHF. Please confirm whether the AES IntelliNet radio transmitter is Government-furnished or contractor-furnished, and identify who coordinates and schedules the base monitoring cutover and acceptance testing with 366 CES.

a. AES IntelliNet radio transmitter is Contractor-furnished.

b. Contractor shall ensure commissioning and testing satisfies the USG requirements, then Contractor shall schedule USG to witness final acceptance testing of new FA system.

60. | HAZTOX | 3.2.2.1 / DA App. D | The hazardous materials survey and abatement are contractor scope with quantities unknown at bid, while the Fire Alarm Design Analysis includes an asbestos and lead inspection report at Appendix D. Please confirm whether Appendix D covers the full renovation footprint or only the fire alarm work areas, and whether facility-wide abatement should be priced against a Government allowance or unit prices rather than lump sum, given quantities cannot be verified before award.

a. The Fire Alarm Design is limited to only the Fire Alarm Design.

b. HAZTOX survey is required an all other emelments to achieve the scope of work beyond the Fire Alarm Design.

61. | General / Phasing | 2.2 / 4.9 | The facility remains occupied across two 180-day phases, with work restricted on Sundays, holy days, and the listed holidays, and fire alarm and fire suppression work will require system outages. Please confirm whether after-hours or weekend work is anticipated or required, and whether a fire watch is required during any fire alarm or sprinkler impairment, so offerors can price premium time and standby coverage accordingly.

a. After hours is allowed.

b. Disturbances during occupied hours is strongly encouraged to be performed after hours.

c. Access to the construction site must protect the general public from accidental access and must be clearly marked to allow authorized personnel only.

d. The authorized area may be occupied by the contractor at the hours as determined in the design specification 01 14 00 Work Restrictions as proposed by the DOR and upon the authorization of the CO.

62. | Contracts (Section M) | Sec. M | Under the Quality and Past Performance factors, will the Government evaluate prior experience and past performance based only on projects the offeror performed as the prime contractor, or will experience performed as a subcontractor, teaming partner, or joint venture member also be considered? If subcontractor experience is considered, how will the offeror’s specific role and scope be verified?

- Performance as a subcontractor, teaming partner, or joint venture member will be considered. Performance as a subcontractor can be verified in any manner that can reasonably be verified for accuracy/truthfulness, such as past performance questionnaires (PPQs).

63. | Contracts | 52.228-1 / 52.228-15 | This acquisition incorporates both 52.228-1 Bid Guarantee and 52.228-15 Performance and Payment Bonds. Please confirm whether a bid guarantee (bid bond) must accompany the offer at the August 24 due date, and in what form and amount, given this is a commercial products and services acquisition under 52.212-1.

- Bid guarantees and Performance & Payment Bonds are required IAW RFO Part

28. A bid guarantee in the form of a bid bond is required for construction contracts, in the amount of 20% of the bid price, or $1,0000,000, whichever is lower.

64. | General / Schedule | Sec. 5 / 4.9 | Reference SOW Section 5 and paragraph 4.9. If Government design review or backcheck exceeds the durations shown in the recommended schedule, will the contractor receive a day-for-day extension to the 550-day period of performance, with liquidated damages tolled for that period?

Please also confirm whether the milestone durations shown in Section 5 are mandatory or recommended.

- A day-for-day extension and the tolling of Liquidated Damages (LDs) are not automatic. Any actual or perceived Government-caused delay will be evaluated on a case-by-case basis. The Contractor must demonstrate that the Government’s delay directly impacted the critical path of the approved master project schedule in accordance with standard delay analysis procedures.

- Milestone durations in section 5 are recommended only for baseline scheduling purposes and do not constitute a firm, day-for-day contractual guarantee.

65. | Contracts | 52.212-4(i)(1) | Reference the Commercial Construction Progress

Payments provision and Clause 52.212-4(i)(1). Are the design milestones (30, 60, 90, and 100 percent) payable as progress against the schedule of values, or is payment tied only to construction percentage complete? Please also state the retainage percentage the Government will withhold.

- Design milestones are payable as progress against the schedule of values (SOV) provided they are properly incorporated into the SOV. Design milestones should be incorporated into the contractor’s proposed SOV for the government review.

Once approved, the contractor may invoice for those values as the project progresses.

- Assuming satisfactory progress, performance, and payments to subcontractors and employees, no retainage is assumed.

66. | General / Contracts | 3.2.1 / 52.236-2 | Reference SOW paragraph 3.2.1 and FAR 52.236-2 Differing Site Conditions. Please confirm that latent or concealed conditions discovered after the design-phase site investigation remain eligible for equitable adjustment under Differing Site Conditions, and that performing the required site investigation does not waive the contractor’s rights under that clause.

- Confirmed. Performance of the design-phase site investigation required by SOW paragraph 3.2.1 does not waive the Contractor’s rights under FAR 52.236-2 (Differing Site Conditions). Latent or concealed physical conditions encountered at the site that differ materially from those indicated in the contract, or unknown physical conditions of an unusual nature differing materially from those ordinarily encountered, remain eligible for evaluation for an equitable adjustment. Any such conditions will be evaluated strictly in accordance with FAR 52.236-2 and FAR 52.236-3 (Site Investigation and Conditions Affecting the Work). The Contractor remains responsible for any conditions that a reasonable, professional site investigation consistent with the SOW requirements should have revealed.

67. | Architecture / Interiors | Room 103 | Can the Government confirm the need for the new wall at 103 Storage to be 1 hour rated?

a. Design A-E should be able to determine by code requirements. Government will review at design package deliverables and determine approval or disapproval per code if not expressly written into the SOW.

b. Bid what is in the SOW.

68. | Architecture / Interiors | Windows | (a) Please confirm whether the new windows are required to match the existing windows. (b) If the new windows are required to match existing, can the Government provide the information on the existing windows (manufacturer, series, frame material, glazing, thermal performance, and finish)?

a. New casement, sills, and stools must match existing.

b. Glazing appearance must be privacy…

This is the start of the file's text. The full file is on GovTribe.