This document is a Statement of Work (SOW) dated 29 March 2024 for a project to repair the metal roof section at Facility 2371, the Base Gymnasium, at Mountain Home Air Force Base. The 30-day project requires the contractor to procure the proper metal roof seamer, ensure the correct rollers are installed to produce the correct folded standing seam, and re-seam approximately 1,000 square feet or 630 linear feet of standing seam roofing panels. The contractor must also remove and replace the existing 90 feet of mesh soffit, matching the eave end soffit. The work must be performed in accordance with manufacturer's instructions, environmental specifications, and OSHA regulations, while protecting the occupied building from water intrusion and damages. The related federal contract opportunity, Solicitation Number FA489724R0003, seeks proposals for this Roof Repair - Metal Roof Panels project, with a site visit scheduled for 7 March 2024 and proposals due by 21 March 2024.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
29 March 2024 Project: WT# 13585616 Title: Repair Metal Roof Section J, Facility 2371 Project Manager: Charles Shoemaker Facility: Base Gymnasium 2371 Period of Performance: 30 days Liquidated Damages: Does not apply to this project Submittals: Colors & Soffit Material Government Furnished Material: None
Work requirements:
Contractor shall procure the proper metal roof seamer. Contractor shall ensure that the correct rollers for the seamer are installed to produce the correct folded standing seam on Gymnasium 2371 to match the existing panels as shown on attached drawing. Approximately 1,000 square feet or 630 linear feet of standing seam need re-worked. (approximate area of work highlighted). The Standing Seam Metal Roof Panels are approximately 16” wide X 90’ long. No asbestos or lead based materials are expected to be encountered during construction.
Repair the roof at Gymnasium 2371 re-seaming 7 roof panels standing seams. The edge panel may have exposed fasteners (Screws with watertight washers) securely installed to purlins. Metal roofing materials removed may be disposed of at base recycle center. Re-install all trim metal if removed.
Gasketed fasteners matching the trim colors may be utilized to ensure security on the leading edge to prevent further wind damage.
Remove the existing 90 feet of mesh soffit and install soffit material that matches the eave end soffit.
See attached photos.
The following requirements are part of this project:
1. All materials shall be installed in accordance with manufacturer’s recommendations and installations instructions.
2. Environmental: All work shall be in accordance with latest Mountain Home AFB Environmental Specifications.
3. Safety: All work shall be in accordance with OSHA regulations.
4. During construction the building will remain occupied. Contractor shall provide protection for building occupants entering or leaving the building as necessary. Contractor shall also protect and ensure water does not enter the building and shall be responsible for any damages caused by construction.
5. Clean up project area after repair work complete.