B2610 - ACM-LBP Technical Specs(Use).doc
DOC document 287 KB Posted
- Attached to
- Repair Facility 2610 Federal contract opportunity
- Solicitation number
- FA4897-09-R-0015_
About this file
Asbestos/Lead Abatement Technical Specification
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 2610A-Amendment 0006 Drawing.pdf | ||
| Amendment 0006.doc | DOC document | |
| Amendment 0005.doc | DOC document | |
| Amendment 0004.doc | DOC document | |
| AMENDMENT 0003.doc | DOC document | |
| Emergency Roof Shoring B2610 - Final Report | — | |
| FAC 2610 - Furnishings List.docx | DOCX document | |
| DIGITALSENDER_20090729_084248_0150.pdf | ||
| SITE VISIT ANNOUCEMENT.docx | DOCX document | |
| Drawings Repair 2610.pdf | ||
| Amendment 0002.doc | DOC document | |
| Solicitation 15 Jul 09 Amendment .doc | DOC document | |
| 2610 MHAFB 100 Resubmittal PDF SET.pdf | ||
| Approved PPT Questionnaire.doc | DOC document | |
| Repair Fac 2610 - Addendum 1.doc | DOC document | |
| 3836 - HDR Engineering - Final Report - MHAFB Bld 2610.pdf | ||
| Notification of Complaince with Insurance.doc | DOC document | |
| DETERMINATION OF RESPONSIBILITY RFP.doc | DOC document | |
| Solicitation 15 Jul 09 .doc | DOC document | |
| Information to Offerors.doc | DOC document | |
| ID10_dvb_July 3.mht | MHT file |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MOUNTAIN HOME AIR FORCE BASE
February 2008
ASBESTOS/LEAD ABATEMENT
TECHNICAL SPECIFICATION
REPAIR FACILITY 2610
MOUNTAIN HOME AFB, IDAHO
Presented By:
Industrial Hygiene Resources 206 Murray Street Boise, ID 83714 (208) 323-8287
Harry Beaulieu, PhD, CIH, CSP
SECTION 01013 ‑ SUMMARY OF THE WORK
1.0
PROJECT/WORK IDENTIFICATION:
1.1 Dimensions, quantities and locations are approximate, included solely to provide general information to the Contractor. The Contractor is responsible for abatement of all asbestos containing materials (ACM) and lead-base paint (LBP) specified herein without regard to accuracy of quantity recorded. The Contractor will be responsible to identify all multiple layers of ACM and LBP building materials. By definition, additive or deductive change order requests will be valid only if actual quantities vary by more than twenty (20) percent of the quantity estimates provided. The Contractors shall visit the site and familiarize themselves with the work and conditions under which the work is to be performed.
Asbestos Containing Materials
· Approximately 100 L.F. of Roof Flashing around penetrations
Lead (Pb) Containing Materials (Alternate)
· Approximately 60 S.F. of white paint and red primer on interior load bearing columns (XX each)
· Approximately 60 S. F. of yellow paint on interior floor and equipment (safety yellow)
Engineering Controls for non-friable roof flashing ACM:
1. Install two (2) layers of poly lining in dumpster or waste container
2. Proper respiratory protection
3. Disposable full-body protective clothing w/hood (no street clothes)
4. Barrier tape and posting around building
5. Wet methods for removal and dust control in container
6. Water tight seal on container when removal completed
7. Label container with proper stickers
8. Complete Waste Shipment Record and collect dump receipt
Engineering Controls for Lead Demolition: Contractor shall reference to section 01526, 6.0 Non-Enclosure Requirements (Lead Demolition) pages 38 and 39 of the Technical Specifications for Manual Demolition. Workers scraping, sanding, heat gun applications, power tool cleaning, abrasive blasting, welding, cutting and torch burning on surfaces that are coated with lead (Pb) are required to follow the OSHA Construction Standard of Lead (29CFR 1926.62) 2.0
INSPECTION:
2.1 Prior to commencement of work, a representative of Mountain Home AFB, and the Contractor shall walk through the areas in which work will be performed and prepare a listing of existing damage to structures, surfaces, equipment, or of surrounding properties which could be misconstrued as damage resulting from asbestos removal. All representatives shall sign the developed list. It is the sole responsibility of the Contractor to identify damage not listed but present in the work areas. Damage identified at the completion of work will be repaired by the Contractor.
3.0
POTENTIAL ASBESTOS HAZARD:
3.1 The disturbance or dislocation of asbestos‑containing materials may cause asbestos fibers and lead (Pb) in air to be released into the building's atmosphere, thereby creating a potential health hazard to workers. Apprise all workers, supervisory personnel, subcontractors and consultants who will be at the job site of the seriousness of the hazards and of proper work procedures that must be followed.
3.2 During the performance of the work, if the project is located where workers, supervisory personnel, subcontractors, or Mountain Home AFB personnel may encounter, disturb, or otherwise function in the immediate vicinity of any identified asbestos-containing and lead (Pb) materials, take appropriate continuous measures as necessary to protect all building occupants from the potential hazard of exposure to airborne asbestos and lead (Pb). Such measures shall include the procedures and methods described in the contract documents, and compliance with regulations of applicable federal, state, and local agencies.
4.0 Reserved 5.0
ASBESTOS‑LEAD CONTAINING MATERIALS:
5.1 Asbestos and Lead (Pb) containing materials are known to be present at the work site. If any other materials are found which are suspected of containing asbestos or lead (Pb), notify the Mountain Home AFB representative immediately.
6.0
CONTRACTOR USE OF PREMISES:
6.1 General: The Contractor shall limit their use of the premises to the work indicated, so as to allow for on-going operations of the Mountain Home AFB. Unless specifically identified within this specification, the Contractor should assume that the site is fully operational 24 hours per day and that all process systems are active. It is the sole responsibility of the Contractor to ensure that business is not interrupted at any time. Further, it is the Contractor's responsibility to ensure that supervisors, workers, and subcontractors do not leave the immediate area of work.
6.2 Use of the Site: Confine operations at the site to the areas permitted under the Contract. Portions of the site beyond areas on which work is indicated are not to be disturbed. Depending upon the situation, violations of this requirement may result in immediate dismissal from the site. It is the responsibility of the Contractor to conform to all rules affecting the work while engaged in project construction as listed below:
6.2.1 Lock automotive-type vehicles, such as passenger cars and trucks and other mechanized or motorized construction equipment, when parked and unattended, to prevent unauthorized use. Do not leave such vehicles or equipment unattended with the motor running or the ignition key in place or accessible to unauthorized persons.
6.2.2 Do not unreasonably encumber the site with materials or equipment. Confine stockpiling of materials to specific areas identified by the Mountain Home AFB representative. The Owner will determine the on-site office and storage areas prior to the on set of work.
6.2.3 Keep existing driveways and entrances serving the premises clear and available to the Mountain Home AFB and its employees at all times. Contractor will use designated parking areas at all times.
6.2.4 Use designated smoking areas, if available, while working on the site.
6.2.5 The location of any locked, fully enclosed dumpsters will be coordinated with the Mountain Home AFB prior to the onset of work.
6.2.6 Mountain Home AFB controls the use of open flames, torches, or other ignition sources during any abatement operation. If such equipment is to be used, a BURNING PERMIT must be obtained from proper authorities. Smoking or open fires will not be permitted within the building enclosure on the premises.
END OF SECTION ‑ 01013
SECTION 01043 ‑ PROJECT COORDINATION ‑ ASBESTOS ABATEMENT & LEAD DEMOLITION
1.0
SUMMARY
1.1 This Section specifies administrative and supervisory requirements necessary for project coordination.
GENERAL SUPERINTENDENT:
Provide a full‑time General Superintendent who is experienced in administration and supervision of asbestos and lead (Pb) abatement projects including work practices, protective measures for building and personnel, disposal procedures, etc. This person is the Contractor's representative responsible for compliance with all applicable federal, state, and local regulations, particularly those relating to asbestos and lead (Pb) containing materials.
2.2 Certification: If necessary, the General Superintendent must hold a current State asbestos abatement and lead (Pb) demolition site supervisor certificate and "hard card" and/or as a minimum a current AHERA Contractor/Supervisor and EPA Lead Contractor/Supervisor Certificates. A copy of all certificates and cards shall be on file with the Contracting Officer prior to the initiation of the project.
2.3 Training: The General Superintendent must have completed a course at an EPA Training Course or equivalent certificate course in asbestos abatement and lead (Pb) demolition procedures, and have had a minimum to two (2) years on-the-job training in asbestos and lead abatement procedures.
Reserved 4.0
DAILY LOG:
4.1 Daily Log: The Contractor shall maintain, as part of the Decontamination Unit, a daily log documenting the dates and time of, but not limited to, the following items.
Meetings; purpose, attendees, brief discussion
Visitations; authorized and unauthorized
Personnel; by name, entering and leaving the work area
Special or unusual events; i.e. barrier breaching, equipment failures, accidents
OSHA Air monitoring tests and test results (Contractor's).
Complete documentation includes as a minimum: Locations, activity, pump calibrations and Sample ID
Documentation of Contractor's completion of the following:
· Inspection of work area preparation prior to start of removal and daily thereafter.
· Removal of any sheet plastic barriers.
· Contractor's inspections prior to spray back, lock back, encapsulation, enclosure, or any other operation that will conceal the condition of asbestos and lead (Pb) containing materials or the substrate from which such materials have been removed.
· Removal of waste materials from work area, and the amount of waste removed.
· Decontamination of equipment (list items).
· Contractor's final visual examination.
4.2 Provide one (1) copy of this log to the Mountain Home AFB representative on a daily basis.
SPECIAL REPORTS:
General: Except as otherwise indicated, submit special reports directly to the Mountain Contracting Officer within one day of occurrence requiring special report, and others affected by the occurrence.
5.2 Reporting Unusual Events: When an event of unusual and significant nature including without limitation barrier breach and failure of any seal occurs at site (examples: failure of pressure differential system, rupture of temporary enclosures), prepare and submit a special report listing chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. When such events are known or predictable in advance, advise the Mountain Home AFB representative in advance, or at least 24 hours prior to the initiation of work.
5.3 Reporting Accidents: Prepare and submit reports of significant accidents, at site and anywhere else work is in progress. Record and document data and actions; comply with industry standards. For this purpose, a significant accident is defined to include events where personal injury is sustained, property loss of substance is sustained, or where the event posed a significant threat of loss or personal injury.
5.4 Report Discovered Conditions: When an unusual condition of the building is discovered during the work (e.g., leaks, termites, corrosion) prepare and submit a special report indicating condition discovered.
CONTINGENCY PLAN:
Contingency plan: Prepare a contingency plan for emergencies including fire, accident, power failure, pressure differential system failure, supplied air system failure, or any other event that may require modification or abridgment of decontamination or work area isolation procedures. Include in the plan specific procedures for decontamination or work area isolation. Note that nothing in this specification should impede safe exiting or provision of adequate medical attention in the event of an emergency.
Emergency Numbers: Post in the clean room of personnel decontamination unit telephone numbers and locations of emergency services including but not limited to hospital, police department, fire department, and poison control center.
7.0
NOTIFICATIONS:
7.1 Notify other entities at the job site of the nature of the asbestos abatement activities, location of asbestos-containing materials, requirements relative to asbestos set forth in these specifications, and applicable regulations.
7.2 The Contractor is required to notify, in writing, emergency response service providers of the type and duration of work to be completed. This notification shall be made prior to the initiation of work.
7.3 Notifications of Emergency: Any individual at the job site may notify emergency service agencies if necessary.
7.4 Multi-employer Work Sites: The contractor must inform other employers on site of the asbestos and lead (Pb) work that will be conducted and take measures to ensure that the employees are not exposed to asbestos or lead (Pb).
7.5 A copy of the demolition/renovation notice shall be submitted as required by 40 CFR 61 Subparts M, National Emission Standard for Asbestos. Send the notice to the following agencies.
· The applicable State entities
· 366 CONS
· 366 CES
· 366 CEAN
The notification forms shall be completed and submitted by the Contractor for abatement projects that are not covered under 40 CFR 61 Subparts A and M. All other agencies, regional or local, having jurisdiction over this project must be notified.
7.6 Documentation that arrangements for the transport and disposal of asbestos and lead (Pb) containing or contaminated materials and supplies have been made must be submitted. The name and location of the disposal site, a copy of handling procedures and a list of protective equipment utilized for asbestos disposal at the landfill, prepared and signed by the landfill Owner, shall be obtained and submitted.
8.0
TECHNICAL SUPPORT
8.1 Air monitoring required by OSHA is the work of the Contractor. Identify an Industrial Hygienist, staff, and/or consultant used for technical support and guidance. Provide copies of their training and qualifications; meeting the following:
8.2 Experience: Have at least 2 years of asbestos and lead (Pb) related experiences
8.3 Accreditation: Have a current EPA-AHERA Contractor/Supervisor certificate
END OF SECTION ‑ 01043
SECTION 01091 ‑ DEFINITIONS AND STANDARDS ‑ ASBESTOS ABATEMENT AND LEAD DEMOLITION
SUMMARY
General Explanation: A substantial amount of specification language constitutes definitions for terms found in other contract documents, including the drawings (drawings must be recognized as diagrammatic in nature and not completely descriptive of the requirements indicated). Certain terms used in Contract Documents are defined in this article.
DEFINITIONS:
Asbestos Abatement: means procedures to control fiber release from asbestos-containing materials. This includes removal, encapsulation, enclosure, entombment and repair.
Lead Abatement/Demolition: The process to reduce lead exposure from lead-containing building materials either by total removal or encapsulation, enclosure, entombment and repair.
Aerosol: A system consisting of particles, solid or liquid, suspended in air.
Aggressive Sampling: A method of sampling in which the person collecting the air sample creates activity during the sampling period to stir up settled dust and stimulate the activity of that area of the building.
Air Cell: Insulation normally used on pipes and ductwork that is comprised of corrugated cardboard which is frequently comprised of asbestos combined with cellulose or refractory binders.
Air Sampling “Asbestos”: The process of measuring the fiber content of a known volume of air collected during a specific period of time. The procedure utilized for asbestos follows the NIOSH Method 7400A (Revision #3, 5/15/89). In addition, transmission electron microscopy methods may be utilized for lower delectability and specific fiber identification.
Air Sampling “Lead”: The process of measuring the lead content of a specific volume of air in a stated period of time.
Airlock: A system for permitting entrance and exit with minimum air movement between a contaminated area and an uncontaminated area, consisting of two curtained doorways separate by a distance of at least three feet such that one passes through one doorway into the airlock, allowing the doorway sheeting to overlap preventing flow-through contamination.
Amended Water: Water to which a surfactant has been added to decrease the surface tension to 35 or less dynes.
Area Air Sampling: Any form of air sampling or monitoring where the sampling device is placed at some stationary location. Area air sampling is conducted each day during an asbestos or lead abatement project. Sampling locations include inside the work area, outside the work area, at the exhaust side on an air filtration machine, and outside the building.
Asbestos: The asbestiform varieties of serpentine (chrysotile), riebeckite (crocidolite), cummingtonite‑grunerite, anthophyllite, and actinolite‑tremolite. For purposes of determining respiratory and worker protection both the asbestiform and non‑asbestiform varieties of the above minerals and any of these materials that have been chemically treated and/or altered shall be considered as asbestos.
Asbestos‑Containing Material (ACM): Any material containing more than one percent by volume of asbestos of any type or mixture of types.
Asbestos-Containing Building Material (ACBM): Surfacing ACM, thermal system insulation ACM, or miscellaneous ACM that is found in or on interior structural members or other parts of a building.
Asbestos‑Containing Waste Material: Any material that is or is suspected of being or any material contaminated with an asbestos‑containing material that is to be removed from a work area for disposal.
Asbestos Debris: Pieces of ACBM that can be identified by color, texture, or composition, or dust, if the dust is determined by an accredited inspector to be ACM.
Asbestos Worker: An individual who cleans, removes, encapsulates, hauls or disposes of friable asbestos material, and is licensed by the state.
Authorized Visitor: The Owner, the Mountain Home AFB representative, testing lab personnel, the Architect/Engineer, emergency personnel, or a representative of any federal, state and local regulatory or other agency having authority over the project.
Background Level Monitoring: A method used to determine airborne asbestos fiber concentrations inside and outside a building prior to starting an asbestos abatement project.
Breathing Zone: A hemisphere forward of the shoulders with a radius of approximately 6 to 9 inches from the nose and mouth.
Building Owner: The person who has legal title to the premises. In all instances where referred in this document, Mountain Home AFB, is the Building Owner.
Ceiling Concentration: The concentration of an airborne substance that shall not be exceeded.
Certified Industrial Hygienist (CIH): An industrial hygienist certified in Comprehensive Practice by the American Board of Industrial Hygiene.
Class I Work Activity: Activities involving the removal of asbestos-containing material or presumed asbestos containing material that is thermal insulation and surfacing material.
Class II Work Activity: Activities involving removal of other types of asbestos-containing material such as resilient flooring and roofing.
Class III Work Activity: Activities involving repair and maintenance where asbestos-containing material or presumed asbestos-containing material is disturbed.
Class IV Work Activity: Activities involving maintenance and custodial construction work during which employees contact but do not disturb ACM or PACM and activities to clean up dust, waste, and debris resulting from Class I, II, and III activities.
Clean Room: An uncontaminated area or room which is a part of the worker decontamination enclosure with provisions for storage of worker's street clothes and protective equipment.
Clearance Air Monitoring: The employment of aggressive sampling techniques with a volume of air collected to determine the airborne concentration of residual fibers upon conclusion of an asbestos abatement project.
Contracting Entity: This is the party with whom the Contractor will enter into agreement with to perform the Work.
Contractor: State Licensed Asbestos Abatement Contractor
Corrective Action: Removal, encapsulation, or enclosure, and where no significant health hazard exists, repair or maintenance or friable asbestos material.
Critical Barrier: Barriers constructed to separate and isolate air and electrical passageways from the abatement area.
Decontamination Enclosure System: A series of connected rooms, separated from the work area and from each other by air locks, for the decontamination of workers, materials, and equipment.
Demolition: The wrecking or taking out of any building component, system, finish, or assembly of a facility together with any related handling operations.
Disposal Bag: A properly labeled 6-mil thick leak‑tight plastic bags used for transporting asbestos waste from work and to disposal site.
Encapsulant: A material that surrounds or embeds asbestos fibers in an adhesive matrix to prevent release of fibers.
Bridging encapsulant: an encapsulant that forms a discrete layer on the surface of an in situ asbestos matrix.
Penetrating encapsulant: an encapsulant that is absorbed by the in situ asbestos matrix without leaving a discrete surface layer.
Removal encapsulant: a penetrating encapsulant specifically designed to minimize fiber release during removal of asbestos‑containing materials rather that for in situ encapsulation.
Encapsulation: Treatment of asbestos‑containing materials, with an encapsulant.
Enclosure: The construction of an air‑tight, impermeable, permanent barrier around asbestos‑containing material to control the release of asbestos fibers into the air.
Equipment Decontamination Enclosure: That portion of a decontamination enclosure system designed for the controlled transfer of materials and equipment, consisting of a washroom and a holding area.
Equipment Room: A contaminated area or room that is part of the worker decontamination enclosure system with provisions for the storage of contaminated clothing and equipment.
Filter: A media component used in respirators to remove solid or liquid particles from the inspired air.
Fixed Object: A unit of equipment or furniture in the work area that cannot be removed from the work area.
Friable Asbestos Material: Material that contains more than one percent asbestos by weight and that can be crumbled, pulverized, or reduced to powder by hand pressure when dry.
Friable Material Containment: The encapsulation or enclosure of any friable asbestos material in a facility.
General Superintendent: This is the Contractor's Representative at the work site. This person will generally be the Competent Person required by OSHA in 29 CFR 1926 and licensed by the State of Idaho as a certified site supervisor.
Glove Bag: A sack (typically constructed of 6-mil transparent polyethylene or polyvinylchloride plastic) with inward-projecting long sleeve gloves, which are designed to enclose an object from which an asbestos‑containing material is to be removed.
HEPA Filter: A High Efficiency Particulate Air (HEPA) filter capable of trapping and retaining 99.97 percent of asbestos fibers greater than 0.3 microns in diameter.
HEPA Filter Vacuum Collection Equipment (or vacuum cleaner): High efficiency particulate air filtered vacuum collection equipment with a filter system capable of collecting and retaining asbestos fibers. Filters should be of 99.97 percent efficiency for retaining fibers of 0.3 microns or larger.
High-Efficiency Particulate Air Filter: (HEPA) refers to a filtering system capable of trapping and retaining 99.97 percent of all monodispersed particles 0.3 um in diameter or larger.
Holding Area: A chamber in the equipment decontamination enclosure located between the washroom and an uncontaminated area.
Homogeneous Work Area: A site within the abatement work area that contains one type of asbestos-containing material and where one type of abatement is used.
Lead Control Area: An area where lead removal operations are performed which is sealed or isolated by physical barriers to prevent the spread of lead-contaminated dust.
Movable Object: A unit of equipment or furniture in the work area that can be removed from the work area.
Negative Exposure Assessment: Objective data obtained from individual employees that demonstrate that employee exposures will be below the PEL. Respiratory protection cannot be used to lower potential employee exposures.
Negative Pressure Respirator: A respirator in which the air pressure inside the respiratory‑inlet covering is positive during exhalation in relation to the air pressure of the outside atmosphere and negative during inhalation in relation to the air pressure of the outside atmosphere.
Negative Pressure Ventilation System: A pressure differential and ventilation system.
Outside Air: The air outside buildings and structures.
PCM: Phase Contrast Microscopy. The analytical technique used for the counting of fibers no smaller than 5.0 micrometers in length and 0.15 micrometers in width.
Personal Decontamination Unit: means that portion of a decontamination enclosure system designed for controlled passage of workers and other personnel and authorized visitors, consisting of a clean room, a shower room and an equipment room separated from each other and from the work area by airlocks and curtained doorways.
Personnel Monitoring: Sampling of the asbestos fiber or lead concentrations within the breathing zone of an employee. The Contractor shall be responsible for collection, analysis, and reporting of his OSHA compliance monitoring. Weekly reports of personal monitoring shall be submitted to the Owner's Representative on a weekly basis.
PLM: Polarized Light Microscopy. See 40 CFR 763, Appendix A to Subpart F for further details.
Pressure Differential and Ventilation System: A local exhaust system, using HEPA filtration capable of maintaining a pressure differential with the inside of the Work Area at a lower pressure than any adjacent area, and which cleans recirculated air or generates a constant air flow from adjacent areas into the Work Area.
Primary Barrier: Barriers constructed adjacent to the critical barrier to enclose the abatement area from the rest of the building and the outdoors.
Project Manager: Project Monitor will serve as the Project Manager for this project, unless delegated by the Mountain Home AFB. The Project Manager will represent the Owner during construction and until final payment is due. The Project Manager will serve as the Contractor's primary contact throughout the project.
Protection Factor: The ratio of the ambient concentration of an airborne substance to the concentration of the substance inside the respirator at the breathing zone of the wearer. The protection factor is a measure of the degree of protection provided by a respirator to the wearer.
RCRA: Resource Conservation and Recovery Act
Removal “Asbestos”: The stripping of any asbestos-containing materials from surfaces or components of a facility or taking out structure components in accordance with 40 CFR 61 Subparts A and M.
Removal “Lead”: The act of removing and transporting lead-based painted building materials from the work site to a suitable disposal site.
Repair: Returning damaged ACBM to an undamaged condition or to an intact state so as to prevent fiber release.
Respirator: A device designed to protect the wearer from the inhalation of harmful atmospheres.
Shower Room: A room between the clean room and the equipment room in the worker decontamination enclosure with hot and cold running water controllable at the tap and arranged for complete showering during decontamination.
Staging Area: The area near the waste transfer airlock where containerized asbestos waste has been placed prior to removal from the work area.
Strip: Remove friable asbestos materials from any part of the facility.
Structural Member: Any load-supporting member of a facility, such as beams and load-supporting walls, or any non-load-supporting member, such as ceilings and non-load-supporting walls.
Supervisor: The Contractor or person designated to be Contractor's representative and responsible for the on-site supervision of the removal, encapsulation, or enclosure of friable asbestos-containing material in an educational facility.
Surfactant: A chemical wetting agent added to water to improve penetration, thus reducing the quantity of water required for a given operation or area.
TEM: Transmission Electron Microscopy. The analytical technique used for the counting of fibers for clearance monitoring and identifying types of fibers collected on the filer.
Testing Laboratories: A "testing laboratory" is an independent entity engaged to perform specific inspections or tests, either at the project site or elsewhere, and to report on, and, if required, to interpret, results of those inspections or tests.
Time Weighted Average (TWA): The average concentration of a contaminant in air during a specific time period.
Visible Emissions: Any emissions containing particulate asbestos material that are visually detectable without the aid of instruments. This does not include condensed uncombined water vapor.
Washroom: A room between the work area and the holding area in the equipment decontamination enclosure system where equipment and waste containers are wet cleaned or HEPA vacuumed prior to disposal.
Waste Generator “Lead”: Any Owner or operator of a source covered by RCRA regulations whose act or process produces lead-containing waste.
Wet Cleaning: The process of eliminating asbestos contamination from building surfaces and objects by using cloths, mops, or other cleaning utensils which have been dampened with amended water or diluted removal encapsulant and afterwards thoroughly decontaminated or disposed of as asbestos-contaminated waste.
Work Area “Asbestos”: The area where asbestos-related work or removal operations are performed which is defined and/or isolated to prevent the spread of asbestos dust, fibers or debris, and entry by unauthorized personnel. The work area is a Regulated Area as defined by 29 CFR 1926. A "Work Area" is considered contaminated during the work, and must be isolated from the balance of the building, and decontaminated at the completion of the asbestos‑control work.
Work Area “Lead”: The area protected by polyethylene sheeting where lead removal operations are performed with a Lead Control Area.
INDUSTRY STANDARDS
Applicability of Standards: Except where Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into Contract Documents. Such standards are made a part of the Contract Documents by reference. Individual sections indicate which codes and standards the Contractor must keep available at the project site for reference.
Referenced industry standards take precedence over standards that are not referenced but recognized in the construction industry as applicable.
3.3 Non-referenced industry standards are not directly applicable to the work, except as a general requirement of whether the work complies with recognized construction industry standards.
3.4 Conflicting Requirements: Where compliance with two or more standards is specified, and they establish different or conflicting requirements for minimum quantities or quality levels, the most stringent requirement will be enforced, unless the Contract Documents indicate otherwise. Refer requirements that are different, but apparently equal, and uncertainties as to which quality level is more stringent to the Owner's Representative for a decision before proceeding.
3.5 Minimum Quantities or Quality Levels: In every instance the quantity or quality level shown or specified shall be the minimum to be provided or performed. The actual installation may comply exactly, within specified tolerances, with the minimum quantity or quality specified, or it may exceed that minimum within reasonable limits. In complying with these requirements, indicated numeric values are minimum or maximum values, as noted, or appropriate for the context of the requirements. Refer instances of uncertainty to the Project Manager for decision before proceeding.
3.6 Copies of Standards: Each entity engaged in construction on the Project is required to be familiar with industry standards applicable to that entities' construction activity. Copies of applicable standards are not bound with the Contract Documents.
Where copies of standards are needed for performance of a required construction activity, the Contractor shall obtain copies directly from the publication source.
Although copies of standards needed for enforcement of requirements may be part of required submittals, the Project Administrator and Project Manager reserve the right to require the Contractor to submit additional copies as necessary for enforcement of requirements.
END OF SECTION ‑ 01091
SECTION 01092 ‑ CODES, REGULATIONS, AND STANDARDS ‑ ASBESTOS ABATEMENT AND LEAD DEMOLITION
SUMMARY:
This section sets forth governmental regulations and industry standards that are included and incorporated herein by reference and made a part of the specification. This section also sets forth those notices and permits that are known to the Owner and that either must be applied for and received, or which must be given to governmental agencies before start of work.
Requirements include adherence to work practices and procedures set forth in applicable codes, regulations and standards.
Requirements include obtaining permits, licenses, inspections, releases and similar documentation, as well as payments, statements and similar requirements associated with codes, regulations, and standards.
CODES AND REGULATIONS
General Applicability of Codes and Regulations, and Standards: Except to the extent that more explicit or more stringent requirements are written directly into the contract documents, all applicable codes, regulations, and standards have the same force and effect (and are made a part of the contract documents by reference) as if copied directly into the contract documents, or as if published copies are bound herewith.
Contractor Responsibility: The Contractor shall assume full responsibility and liability for the compliance with all applicable federal, state, and local regulations pertaining to work practices, hauling, disposal, and protection of workers, visitors to the site, and persons occupying areas adjacent to the site. The Contractor is responsible for providing medical examinations and maintaining medical records of personnel as required by the applicable federal, state, and local regulations. The Contractor shall hold the Owner, and Project Manager, and any employees or agents, harmless and shall defend the same against any and all claims, actions, or proceedings, including attorney's fees in connection therewith, arising out of or connected with the failure of Contractor, its subcontractors, and agents or employees of either, to fully comply with any applicable work, hauling, disposal, safety, health, or other law, regulation, or standard.
Federal Requirements: Federal requirements which govern asbestos abatement work or hauling and disposal of asbestos waste materials include but are not limited to the following.
2.3.1 OSHA: US Department of Labor, Occupational Safety and Health Administration, (OSHA), including but not limited to the following regulations.
Occupational Exposure to Asbestos, Tremolite, Anthophyllite, and Actinolite; Final Rules Title 29, Part 1910, Section 1001 and
Part 1926, Section 1101 of the Code of Federal Regulations
(as amended August 10, 1994)
Occupational Exposure to Lead, Handling Materials, and Equipment
OSHA Standard 29CFR 1926.62, Code of Federal Regulations
Respiratory Protection
Title 29, Part 1910, Section 134 of the
Code of Federal Regulations
Construction Industry
Title 29, Part 1926, of the
(as amended August 10, 1994)
Access to Employee Exposure and Medical Records
Title 29, Part 1910, Section 20 of the
Hazard Communication
Title 29, Part 1910, Section 1200 of the
Specifications for Accident Prevention Signs and Tags
Title 29, Part 1910, Section 145 of the
2.3.2 DOT: U. S. Department of Transportation, including but not limited to the following.
Hazardous Substances
Title 29, Part 171 and 172 of the
2.3.3 EPA: U. S. Environmental Protection Agency (EPA), including but not limited to the following.
Asbestos Abatement Projects; Worker Protection Rule
Title 40 Part 763, Sub-part G of the
National Emission Standard for Hazardous Air Pollutants (NESHAPS)
National Emission Standard for Asbestos
Title 40, Part 61, Sub‑part A, and Sub-part M (Revised Sub‑part B) of the
Revised November 20, 1990
2.3.4 State Requirements: Contractors must abide by the applicable state regulations that govern asbestos abatement and lead demolition work or hauling and disposal of asbestos and lead waste materials
2.3.5 Local Requirements: Abide by all local requirements that govern asbestos abatement and lead (Pb) demolition work or hauling and disposal of asbestos and lead waste materials.
STANDARDS:
General Applicability of Standards: Except to the extent that more explicit or more stringent requirements are written directly into the Contract Documents, all applicable standards have the same force and effect (and are made a part of the Contract Documents by reference) as if copied directly into the Contract Documents, or as if published copies are bound herewith.
Contractor Responsibility: The Contractor shall assume full responsibility and liability for the compliance with all standards and patents pertaining to work practices, hauling, disposal, and protection of workers, visitors to the site, and persons occupying areas adjacent to the site. The Contractor shall hold the Owner and Owner's Representative, and any employees or agents thereof, harmless and shall defend the same against any and all claims, actions, or proceedings, including attorneys' fees in connection therewith, arising out of or connected with the failure of Contractor, its subcontractors, and agents or employees of either, to fully comply with any applicable work, hauling, disposal, safety, health, or other law, regulation, or standard.
Standards: Standards which apply to asbestos abatement work or hauling and disposal of asbestos waste materials include but are not limited to the following.
American National Standards Institute (ANSI)
1430 Broadway
New York, New York 10018
(212) 354‑3300
Fundamentals Governing the Design and Operation of Local Exhaust Systems Publication Z9.2‑79
Practices for Respiratory Protection Publication Z88.2‑80
American Society for Testing and Materials (ASTM)
1916 Race Street
Philadelphia, PA 19103
(215) 299‑5400
Safety and Health Requirements Relating to Occupational Exposure to Asbestos E 849‑82
EPA GUIDANCE DOCUMENTS:
EPA Guidance Documents: discuss asbestos abatement work or hauling and disposal of asbestos waste materials listed below for the Contractor's information only. These documents do not describe the work and are not a part of the work of this contract. EPA maintains an information number (800) 334‑8571, publications can be ordered from (800) 424‑9065 (554‑1404 in Washington, DC):
EPA C00090 (out of print).
Guidance for Controlling Asbestos Containing Materials in Buildings (Purple Book) EPA 560/5‑85‑024.
Asbestos in Buildings: National Survey of Asbestos‑Containing Friable Materials. EPA 560/5‑84‑006.
Asbestos in Buildings: Guidance for Service and Maintenance Personnel. EPA 560/5‑85‑018.
Asbestos Waste Management Guidance. EPA 530‑SW‑85‑007.
Asbestos Fact Book. EPA Office of Public Affairs.
Asbestos in Buildings. Simplified Sampling Scheme for Friable Surfacing Materials.
Commercial Laboratories with Polarized Light Microscopy Capabilities for bulk asbestos identification.
A Guide to Respiratory Protection for the Asbestos Abatement Industry. EPA‑560‑OPTS‑86‑001
END OF SECTION - 01092
SECTION 01340 ‑ SUBMITTALS
SUMMARY:
This section specifies administrative and procedural requirements for submittals required for performance of the Work, including:
Submittal Procedures
Certifications
Citations and Violations
Abatement Contractor’s Project schedule
Plan of Action
Product Data
Rental Equipment
Bid Submittal Checklist
Post Notification Submittal Checklist
Daily Submittal Checklist
Close-out Submittal Checklist
SUBMITTAL PROCEDURES:
Submittal Preparation: Use AF Form 3000 for Submittals:
Indicate the section and sub-section(s) for which the submittal applies;
Indicate the name of the submittal; and
Include the date.
Submittal Transmittal: Package each submittal appropriately for transmittal and handling. Transmit each submittal from Contractor to the Project Monitor using a transmittal form.
On the transmittal, record relevant information and requests for data. On the form, or separate sheet, record deviations from Contract Document requirements, including minor variations and limitations. Include Contractor's certification that information complies with Contract Document requirements.
CERTIFICATIONS
A copy of the Project Permit shall be submitted (if applicable).
Evidence that the Asbestos Abatement Contractor holds a current Idaho state Abatement Contractor License.
A copy of the Asbestos Abatement Contractor’s Work Plan that meets, state/local requirements and the Master Specification.
A copy of the statement provided by the state regarding bonding and liability insurance.
3.5 A list of all workers and supervisors that will be present at the site along with current state certificates to conduct asbestos-related work.
A copy of the Certificate of Worker Acknowledgment and Release for each worker who is to be at the job site or enter the work area.
3.7 Documentation from a physician that all employees or agents who may be exposed to airborne asbestos or lead in excess of background levels have been provided with an opportunity to be medically monitored to determine if physically capable of working while wearing the required respiratory equipment without suffering adverse health effects. In addition, documentation that personnel have received medical monitoring as required in OSHA 29 CFR 1926.1101 and 1926.62 shall be submitted. Submit current physicals for all employees directly involved with this project. The records shall include blood tests for lead exposure. Blood tests shall be conducted for each individual before they will be allowed onsite. The Contractor shall provide information to the examining physician about conditions in the work place environment (e.g. high temperatures, humidity, chemical contaminants).
3.8 Documentation that all of the Contractor's employees and agents who must enter the work area have passed respirator fit tests and have been assigned respirators that fit. This fit testing shall be in accordance with qualitative procedures as detailed in the OSHA Respiratory Standard 29 CFR 1910.134 Qualitative Fit Test Protocol (1998).
3.9 Personnel: The Contractor shall notify the Mountain Home AFB representative of any personnel changes and submit all certification information for any employee hired and scheduled to work at the site.
4.0 RESERVED
5.0 RESERVED
PLAN OF ACTION
Plan of Action: The Contractor will be required to submit a detailed plan of the procedures proposed for use in complying with the requirements of this specification. Include in the plan the location and layout of decontamination areas, the sequencing of asbestos and lead work, the interface of trades involved in the performance of work, methods to be used to assure the safety of building occupants and visitors to the site, disposal plan including location of approved disposal site, and a detailed description of the methods to be employed to control asbestos and lead emissions. Describe the method of removal to prohibit visible emissions in work area and packaging of removed asbestos and lead debris. The Contracting Officer must approve the plan prior to commencement of work. All material required for the submittal package will be included with the Plan of Action.
PRODUCT DATA
The Contractor shall submit evidence that they are a holder of a valid license under US Patent Number 4,604,111 if they propose to use ventilation units governed by this patent.
The contractor shall submit manufacturer's certification that HEPA vacuums, negative air pressure equipment and other local exhaust ventilation equipment conform to ANSI Z 9.2-79 and the state asbestos abatement rules.
The contractor shall submit logs documenting filter changes on respirators, HEPA vacuums, negative pressure ventilation systems, and other engineering controls.
The contractor shall submit a list of NIOSH approvals for all respiratory protective devices used on site. In addition, manufacturer certification of HEPA filtration capabilities for all cartridges and filters shall be submitted.
Material Safety Data Sheets:
7.5.1 Material Safety Data Sheets shall be provided for any chemical agents that are to be used in conjunction with this project. These include, but are not limited to the following:
Encapsulants, Adhesives, Solvents, Stripping Agents, and
Spray Poly
7.5.2 Material Safety Data Sheets shall be included in the Bid Submittal.
RENTAL EQUIPMENT:
For any rental equipment to be used in conjunction with the project, the Contractor shall submit a letter from the respective rental company stating that the rental company understands that the equipment will be used in conjunction with an asbestos removal project. A copy of this correspondence must be included with the project submittals.
9.0
BID SUBMITTAL CHECKLIST
The submittals required from the contractor include, but are not limited to the following:
SUBMITTALS CHECKLIST
Required within 10 working days before start of work
01043 Project Coordination - Asbestos Abatement and Lead Demolition
Contingency Plans (Medical Evacuation, Breach of Barrier, Fire Plan)
Telephone Numbers
Resume: Of anticipated general superintendent and workers
AHERA Accreditation: accreditation of general superintendent and workers
Staff Names
Technical Support Documentation
01092 Codes, Regulations, and Standards - Asbestos Abatement and Lead Demolition
State License (if required)
State Permits (if required)
01340 Submittals
Plan of Action
Citations and Violations Statement
01513 Temporary Pressure Differential & Air Circulation System
Pressure Differential System Design
01526 Temporary Enclosures
Spray Cement: MSDS
Signs
01560 Worker Protection
Certificate of Worker Acknowledgment for anticipated General
Superintendent and workers
State Licenses for anticipated General Superintendent and workers
Current training records and AHERA certifications for anticipated workers
Current medical releases and fit test records for anticipated General
Superintendent and workers
01562 Respiratory Protection
NIOSH AND MSHA Certifications for personal filters and cartridges
Type “C” System Diagram
Type “C” Operating Instruction
Historical Airborne Fiber Data
01563 Decontamination Units
Signs
02081 Removal of Asbestos and Lead Containing Materials
Material Safety Data Sheet: for each surfactant and encapsulant
02084 Disposal of Asbestos and Lead Containing Waste Material
Waste Hauler Local License
Chain of Custody Form
Waste Manifest Form
Landfill Handling Procedures
01043 Project Coordination
Notifications sent to EPA and applicable state entities
AHERA Accreditation: Accreditation of workers
OSHA Air monitoring results
01092 Codes, Regulations, and Standards - Asbestos Abatement & Lead Demolition
Copy of NESHAP 40 CFR 61 Subpart M
Copy of OSHA 29 CFR 1926.1101, and 1910.1001
Copy of AHERA 40 CFR 763, Subpart E
Copy of applicable State and Local Regulations
Copy of signed Bid Proposal
01503 Temporary Facilities - Asbestos Abatement & Lead Demolition
Scaffolding and PE Certification
Hot Water Heater
Decontamination Unit Sub-panel
Ground Fault Circuit Interrupters (GFCI)
Lamps and Light Fixtures
First Aid Supplies
Fire Extinguishers: Product data, location and schedule
01513 Temporary Pressure Differential & Air Circulation System
HEPA Filtered Fan Units: Product Data
Monitoring Equipment: Product Data
Auxiliary Generator: Product Data
01526 Temporary Enclosures
Sheet Plastic: Test Reports on NFPA 701 test
01563 Decontamination Units
Personnel Decontamination Unit: product data
Equipment Decontamination Unit: product data
Shower Pan: shop drawing
Shower Walls: product data
Shower Head and Controls: product data
Filters: product data
Filters: shop drawing
Wash Station Shower Stall: product data
Wash Station Shower Stall: shop drawing
Sump Pump: product data
02081 Removal of Asbestos and Lead Containing Materials
Surfactant: product data
Removal Encapsulant: product data
10.0 RESERVED
11.0
REQUIRED DAILY SUBMITTAL CHECKLIST
Provide daily work logs to the Mountain Home AFB representative at end of daily workshift
01013 Summary of Work - Asbestos Abatement & Lead Demolition
Daily Notification(s) to other Entities at the project site
01043 Project Coordination - Asbestos Abatement & Lead Demolition
Contractors Daily Logs
Containment Sign-In Sheets
Previous work day contractor OSHA air monitoring results
Visitor Sign-In Sheets
Special Reports:
Event Reports
Accident Reports
Discovered Condition Reports
01092 Codes, Regulations, and Standards - Asbestos Abatement & Lead Demolition
Amended Notifications (if applicable)
01340 Submittals
Record (as-built) Documents
01560 Worker Protection
Certificate of Worker Acknowledgment for General Superintendent and workers
State licenses for General Superintendent and workers
Current training records and certifications for General Superintendent
Current medical records and certifications for General Superintendent
02084 Disposal of Asbestos and Lead Containing Waste Material
Copies of waste manifests and disposal site receipts
12.0
CLOSE-OUT SUBMITTAL CHECKLIST
Submit copies of disposal manifest
END OF SECTION 01340
SECTION 01410 ‑ AIR MONITORING ‑ TEST LABORATORY SERVICES
(ENVIRONMENTAL AIR MONITORING IS NON-MANDATORY)
(OSHA AIR MONITORING IS MANDATORY)
DESCRIPTION OF THE WORK:
Not in Contract Sum: This section describes work being performed by the owner. This work is not in the Contract Sum.
1.2 This section describes air monitoring carried out by the Building Owner to verify that the building beyond the work area and the outside environment remains uncontaminated. This section also sets forth airborne fiber and lead (Pb) dust levels both inside and outside the work area as action levels, and describes the action required by the Contractor if an action level is met or exceeded.
1.3 Air monitoring required by OSHA is the work of the Contractor and is not included in this section.
AIR MONITORING:
Work Area Isolation: The purpose of the Mountain Home…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .