Atch 31 Statement of Objectives - Demo Porject Const. Bldg 703 GCS Compound Pad.doc

DOC document 152 KB Posted

Attached to
CREECH SABER IDIQ
Solicitation number
FA4861-11-R-A400
Issued by

About this file

CREECH AFB SABER ATTACHMENT 31

View the file

Other files

File Type Posted
12 Clarification QA 25 Aug 11.pdf PDF
Creech Conformed Copy Amend 2.pdf PDF
Creech Amend 2 MOD.pdf PDF
E_LP_003.TIF TIF image
Atch 32 Diagram 1 Bldg 703.pdf PDF
Atch 39a Drawing Bldg 703.jpg JPG image
Atch 39d Drawing Bldg 703.jpg JPG image
Creech SABER Amendment 1.pdf PDF
Atch 39e Drawing Bldg 703.jpg JPG image
Atch 39f Drawing Bldg 703.pdf PDF
Atch 35 Diagram 4 Bldg 703.pdf PDF
Atch 1 Specifications for Creech SABER REV 1.pdf PDF
Atch 39i Drawing Bldg 703.jpg JPG image
Atch 38 Performance Information Form.pdf PDF
Atch 39b Drawing Bldg 703.jpg JPG image
Atch 33 Diagram 2 Bldg 703.pdf PDF
Atch 31 SOO Demo Project Const. Bldg 703 GCS Compound.Pad.pdf PDF
Creech SABER Amend 1 Conformed Copy.pdf PDF
Atch 29 SOO - Demo Project Bldg 707 Rev 1.pdf PDF
Atch 39g Drawing Bldg 703.jpg JPG image
Atch 39h Drawing Bldg 703.jpg JPG image
Atch 34 Diagram 3 Bldg 703.pdf PDF
Atch 39c Drawing Bldg 703.jpg JPG image
Creech SABER Q A Final dtd 16 Aug 11.docx DOCX document
Creech PPQ Question and Answer 1.docx DOCX document
Atch 25 Past Performance Questionnaire.pdf PDF
Atch 26 Financial Information Request.pdf PDF
Atch 27 Bonding Information Request.pdf PDF
Atch 11 AF Form 3064 Progress Schedule.pdf PDF
Atch 15 AF Form 1477 Inspection Record.pdf PDF
Atch 16 AF Form 103 Dig Outage and Location Request.pdf PDF
Atch 12 AF Form 3000 Material Approval Submittal.pdf PDF
Atch 32 thru 35 Diagram 1 thru 4 for Building 703.pdf PDF
FA4861-11-R-A400_CREECH_SABER_Atch 36 Consent Letter dtd 15 Feb 10.doc DOC document
Atch 14 Range Pass NAFB 0-74.doc DOC document
Atch 7 UFC 3-580-01.pdf PDF
Atch 13 AF Form 3065 Contract Progress Report.xls XLS spreadsheet
Atch 5 Tech Spec SCIF May 5 2011.pdf PDF
Atch 19 UFC 1-300-08.pdf PDF
Atch 29 Statement of Objectives - Demo Project Ren. Int. Op Cell Bldg 707.doc DOC document
Atch 30A As Built Drawing Bldg 707.pdf PDF
Atch 18 Sample of DD1354.pdf PDF
Atch 26 Financial Information Request CREECH.pdf PDF
Atch 22 Wage Determination NV100022 - Heavy thru Mod 07.docx DOCX document
Atch 4 Engineering Technical Letter —
Atch 30B As Built Drawing Bldg. 707.pdf PDF
Atch 8 38EIGHTB33-01 Comm Infor 1st 400 Ft.doc DOC document
Atch 11 AF Form 3064 Progress Schedule.xfdl XFDL file
Atch 15 AF Form 1477 Inspection Record.xfdl XFDL file
Atch 23 Wage Determination NV100004 - Highway thru Mod 01.docx DOCX document
Show 40 more

Latest 50 of 67 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SABER

STATEMENT OF Objectives for Construct Bldg. 703 Addition & GCS Compound/Pad, 556 TES

LKTC 11-1040A

CREECH AIR FORCE BASE, NEVADA

10 Jun 2011

OFFICE OF THE BASE CIVIL ENGINEER

NELLIS AIR FORCE BASE, NEVADA

STATEMENT OF OBJECTIVES

1. SCOPE: Contractor shall furnish all design, labor, equipment, material, transportation, administration, supervision and all else necessary to perform all operations in connection with successfully completing this project LKTC 11-1040A, Constrcut Building Building 703 Addition & GCS Compound/Pad, 556 TES, FORMDROPDOWN

2. The renovation of B703 will create an Open Secure Storage Area (OSSA) in the East side of the existing building & extend to an area adjacent to the building, on the North (flight line) side. Construction will include renovating the existing structure of designated rooms to meet OSSA requirements; enclosing open areas between the 2 sides of the existing bldg to create new server room and operating locations, renovating an existing room (Rm106) and constructing a secure compound for Ground Control Station (GCS) operations. Power and HVAC systems will be installed to operate and cool new servers, room additions, and operating systems within required standards. Install a back-up generator, connect all comm and electrical systems in room additions, ops floor Rm 106, GCS Compound, and UNCLASS comm room to generator via auto-transfer switch. Security systems will be installed to provide 24X7 IDS and Access Control coverage. Additional comm connectivity will be installed from another building (B707) thru this renovation area to an unclass room (Rm115) in B703. A radio antenna will be installed as a roof mount. Communications conduit, cable ladders/trays, wiring, cabinets, NEMA Enclosures, patch panels, wire management devices, and associated hardware are required to meet the OSSA standards and the OPS requirements for the 2 new office/server areas, Rm 106, & the new GCS compound.

3. Customer will provide SCI escort bodies for construction activities pending Creech SSO recommendation, pending ICD 705 review.

4. When complete, the project shall be as shown below (either in the attached sketch or work description). Include in the submittal, reference to the specifications that apply to this project and identification of material items required to be submitted to the government for approval (use AF Form 66), both will be incorporated in the construction project.

5. LOCATION: The project site is located on FORMDROPDOWN . The Main base is located approximately 55 miles north of Las Vegas on Highway US 95.

6. CODES: All design and construction must be in compliance with the International Building Code (UBC-2006) (or most recent edition), Department of Defense Unified Facilities Criteria Standards (UFC), all Public Laws, Executive Orders, Code of Federal Regulations, Department of Defense Instructions, (DODI), Department of Defense Directives, NAFB Design Compatibility Guidelines, Clark County, State of Nevada and Federal standards, codes and laws or other higher authority documents as applicable.

7. REFERENCES:

7.1 ICD 705

7.2 DoD 5200.1-R, AP7

7.3 ACC33-165

7.4 UFC 3-580-01, Telecommunications Building Cabling Systems Planning and Design, 22 June 2007

7.5 Nellis and Creech AFB Addendum, Building Telecommunications Cabling System, Section 27 10 00, May 2010

7.6 Engineering Technical Letter (ETL) 02-12: Communications and Information System Criteria for Air Force Facilities, 27 Jun, 2002

7.7 MIL-STD-188-124B, Department of Defense Interface Standard, Grounding, Bonding, and Shielding, 18 Dec 2000

7.8 AFMAN 33-214 V1, paragraph 5.3.1.1, [will become AFSSI 7701]

7.8.1 (U) INFORMATION ASSURANCE SYSTEMS COUNTERMEASURES.

7.8.2 (U) Expose RED Signal Lines.

7.8.3 (U) In controlled access areas that are not controlled 24 hours a day, 7 days a week (24/7), expose all RED signal lines to viewing. This applies to both wire and fiber optic RED signal lines. Exposing means do not hide RED signal lines above false ceilings, below raised flooring, or behind a cover attached to a wall. Conduit (electrical metallic tubing [EMT]), Panduit, or other distribution facilities may be used to protect the signal lines from damage or to achieve neatness and orderliness as long as they are exposed to viewing and begin and end within the same controlled access area. RED signal lines may be run above a false ceiling or below a raised floor provided the hidden area they traverse is alarmed or the signal lines are run in conduit with the conduit ends exposed below the false ceiling or above the raised floor. Spot-weld or epoxy all joints of the conduit. Check RED signal lines that are run above a false ceiling or below a raised floor for tampering twice a year or whenever un-cleared personnel have had access to them (housekeeping, painting, civil engineering [CE] work, etc.).

7.8.4 AFSSI 7702 EMSEC Countermeasures Reviews

7.9 38EIG Handbook 3301, Communications and Information First Four Hundred Feet, 1 May 2005

8. DRAWING STANDARDS: All drawings submitted shall be prepared in accordance with the applicable provisions of the Architectural/Engineering/Construction (A/E/C) Computer-Aided Design and Drafting (CADD) standard. All drawings shall comply with the specifications in Attachment #1 for Simplified Acquisition of Base Engineering Requirements (SABER) dated 26 June 2011. Contractor shall maintain one set of drawings on site and record all changes and any hidden or subsurface data discovered during construction. Construction drawings shall be submitted to government with Red Line Marks.

9. ENVIRONMENTAL PROTECTION: All work and contractor operations shall comply with the requirements imposed by all applicable Federal, State, local and NAFB laws, regulations, codes and permits (including NAFB Management Plan12) concerning environmental protection. Test for Asbestos Containing Material (ACM) and Lead Base Paint (LBP) in the area of construction. Provide test report of findings to government.

10. DESCRIPTION OF WORK: The work to be accomplished includes but is not limited to the following description.

11. Occupant count for new server/office areas

11.1 Ops floor Bldg 703, Rm106 & Server room addition: Total of 9 Users

11.2 South Office Addition (Bldg 703): Total of 6 Users

12. Construction requirements:

12.1 Ops Floor Room #106;

12.1.1 Construct Ops Floor Rm 106 to OSSA standards as per DoD 5200.1-R, AP7. Shared wall with new west server room will be to ICD 705 standards.

12.1.2 Install one (1) STC 45 door and frame in hallway entry to room 106 See drawing diagram 2 for approximate location. Install X09 locks.

12.1.3 Install a raised floor system, with movable tiles to provide access to cables below, approximately 20’-10” by 26’-11” to support five (5) operator consoles, personnel, and equipment. See drawing diagram 2 for approximate location.

12.1.4 Remove existing suspended ceiling system and all fixtures; re-install existing projector mounts & screens, raise ceiling approximately 16” higher to accommodate raised floor system.

12.1.5 Install an insulator, to all conduits, pipes, and HVAC system penetration, in accordance with ICD 705 & DoD 5200.1-R, AP7. Adapt construction standards as per walls shared between secure areas.

12.1.6 Reconfigure existing light circuits and install dimmer balances in light fixture to operate with two 3-way dimmer switches in Ops floor. The 2 variable switches, will control front lighting and rear lighting.

12.1.7 Contractor will install blue light on the ops floor, locate control switch at Server room double door entry and at Rm 106 hallway entry point. Switches will control all blue lights (additional light will be installed in server room).

12.1.8 Install Access Control badge station conduits for comm lines, locate at hallway entry of ops floor; station will be controlled separately from server room Access Control.

12.1.9 Install separate A/C unit for Ops Rm #106, moisture control, and ambient control system.

12.1.10 See diagram 2 for Ops floor power requirements

12.1.11 .

12.2 New West Server Room Addition: Room addition West of Rm 106 built in accordance with ICD 705.

12.2.1 Install one (1) STC 50 door and frame, 3’-0” x 7’-0”, into new server room from room 106 and install STC 50 or better rated double doors at entry/exit to GCS compound. Install X09 locks on both doors.

12.2.2 Construct new server room, approximately 11’-2” x 40’-0”, west of room 106, Diagrams # 1 & 2.

12.2.3 Redesign roof; existing roof line to cover new server room area in accordance with ICD 705

12.2.4 Install raised floor system; tiles are to remain removable for access to cabling below.

12.2.5 Install primary and secondary HVAC system, (HVAC system to support 8 cabinets producing 45,000 BTU per cabinet)

12.2.6 Install room light controls on 1 variable switch, located at door to Rm 106.

12.2.7 Install Access Control badge station at server room entry from Rm 106 and server room entry from GCS compound, (these are controlled separately from Access Control Station at hallway Ops Floor entry).

12.2.8 Wire new server room with new 225 Amp load center which must be tied to back up power.

12.3 Additional (South) Office: Office space shall be constructed to ICD 705

12.3.1 Install additional office space added to Bldg 703 (see diagrams 1 & 3).

12.3.2 Install one (1) STC 50 door and frame, 3’-0” x 7’-0”, in south office from hallway. Install X09 locks on door.

12.3.3 Construct new server room, approximately 11’-2” x 40’-0”, south of new west server room, Diagrams # 1 & 2.

12.3.4 Redesign roof; existing roof line to cover new server room area in accordance with ICD 705

12.3.5 Install raised floor system; tiles are to remain removable for access to cabling below.

12.3.6 Install primary and secondary HVAC system. (HVAC system to support 3 cabinets producing 45,000 BTU per cabinet)

12.3.7 Install room light controls on 1 variable switch, located at entry door to hallway.

12.3.8 Install /blue light as noted in Diagram 3; control switch located at doorway.

12.3.9 Install Access Control badge station at server room entry from hallway, (These are controlled separately from Access Control Station at West Server room and hallway Ops Floor entry).

12.3.10 See Diagram 3 for Power requirements.

12.4 GCS Compound:

12.4.1 Install concrete pad 60ftx160ft (psi 45, type).

12.4.2 Install concrete (psi 25, type) walkway to server room entry.

12.4.3 Install auto-sensor exterior lighting above server room double doors.

12.4.4 Install, 11ft width awning above server room double doors to extend out 10ft.

12.4.5 Install compound TYPE A fencing. Install vertical outriggers (to accommodate 6 strands of tensioned barbed wire) in order to provide a proper fence sensor platform. The fence also has to be 7 feet tall, needs a tensioning wire and bracing rails, 9-guage wire mesh, etc.

12.4.6 Install that Access Control at turn style. Install comm conduit to support.

12.4.7 Install Grounding in compliance with ACC33-165.

12.4.8 Install street lighting for GCS pad area (at each corner)

12.4.9 Install Power Distribution System/ Load center, junction box for (1) 100amp MilSpec and (2) 60amp MilSpec.

12.4.10 Contractor shall connect new GCS unit to new power source

12.4.11 Install Generator to support four GCS’s, Ops floor and server room.

12.4.12 Ensure each PDS junction box is lockable and alarmed.

13. Earthwork:

13.1 Remove and dispose of existing trees and shrubs. Grade area to natural slope.

13.2 Remove existing drainage rocks

13.3 Re-grade, cut and fill an approximate area of 200’ by 75’. Bring grade elevation up to match the existing fence line retaining wall and slope towards existing concrete pad elevations.

13.4 Design and install drainage to divert the water flow away from the existing and new concrete pads. ARCP and RCP with end section are to be used and installed per Clark County Unified Standards for reinforced piping.

13.5 Contractor shall provide 35% construction drawings of earthwork and hydraulics calculations for the size of RCP to be used for approval before work is to commence.

14. Communication requirements for Ops Cell/Server room/Secure Compound; Installation of all comm will be in accordance with the references listed in Para 6. Although this facility and adjacent GCS compound will be alarmed (under this contract) at entrances and exits, they DO NOT meet the requirements to be considered a 24/7 operation, therefore, ALL red signal lines, whether fiber or copper must be either alarmed, if traversing hidden space, or exposed to viewing, beginning and ending in the same physical space. Specific details of how this must be accomplished is found in AFMAN 33-214 V1, paragraph 5.3.1.1 will become AFSSI 7701.

14.1 ALL fiber will be OFNP

14.2 ALL CAT6 will be screened shielded (S/STP), plenum rated, color jacketed as noted in Tables 1-4

14.3 ALL cable entrances/exits to the raised floor, entrance/exits to the above ceiling space, and conduit stub-ups to and from the GCS pad will be alarmed to monitor tampering

15. General Comm requirements for Bldg 703 Server Room addition/Room 106 renovation/South Office room addition/GCS Compound. Contractor will EFI&T all communications wiring, outlet boxes, cable trays, NEMA boxes, data racks, patch panels, Panduit, and associated parts to complete the communications req associated with this project renovation. Refer to Diagrams 1-3 for graphic of each area

15.1 Contractor will EFI&T comm wiring from data racks in new server room to designated consoles and wall outlets as specified in room diagrams and wiring matrix, Tables 1-4 & Diagrams 1-3. Routing will be via grounded cable trays, conduit, or surface mount Panduit in accordance with security standards. Wall penetrations will be thru lockable NEMA cabinets of sufficient depth to allow visual inspection of cabling from one room thru wall space into opposing room. UNCLASSIFIED and CLASSIFIED wiring will remain 2” apart along the entire route from data patch panel locations and outlet boxes, thru cable trays, and all other floor/ceiling penetrations. CLASSIFIED and UNCLASSIFIED wiring will enter/exit thru separate NEMA boxes as depicted in Diagram 1

15.2 Both room additions will have a TMGB ground plate installed, connected to facility ground and meet less than 10 ohms resistance

15.3 All contractor installed cabinets will be secured to the flooring in accordance with earthquake safety standards. Each data cabinet will have 2 dedicated L5-30 125VAC and 2 dedicated L6-30 250VAC, mounted under raised floor. Patch panels for Fiber and CAT6 S/STP will be installed to meet connectivity requirements and wire (S/STP) grounding; patch panels and premise wiring will be installed in a common data/voice configuration

15.4 Do not install cabinets in a corner; provide 36” maintenance space on all sides unless one side can be against a wall, allowing maintenance access to front, back and one side

15.5 Coordinate with customer & 99 CS/OL-A PM for rack elevation drawings.

15.6 All outlet boxes must be metal with multiple 1” knockouts and must be of sufficient depth to provide bend radius space for the CAT6 S/STP and FO wiring.

15.7 Separate 1” conduits will be used for CAT6 and FO. This applies to wall and under raised floor outlet box installations.

15.8 Outlet boxes will be of sufficient width to accommodate all ports Installed for each outlet location as per diagrams. Outlet face plates will be white, Quick Port style.

15.9 All CLASSIFIED outlet boxes, above raised floor or below ceiling tiles, must be surface mounted. Wiring to all CLASSIFIED outlet boxes will be installed in surface mounted Panduit, wire runs will have covers that are easily removed for visual inspection.

15.10 Outlet boxes installed under raised floor space, and associated wiring, will not require Panduit, since the space traversed by the classified wiring will be alarmed. Wiring under the raised floor (alarmed space) will require cable trays to traverse the area. All comm wiring under raised floor space will be easily inspected

16. Comm requirements for Bldg 703 Server Room addition and Room 106 renovation, Diagram 2.

16.1 Contractor will install, & Test 7 GFE lockable, free-standing data cabinets, side panels, including wire management, in new server room addition. Contractor will install 5 HP Rack Coupling Kits.

16.2 Contractor will EFI&T all communications wiring, outlet boxes, cable trays, NEMA boxes, data racks, patch panels, Panduit, and associated parts to complete the communications req associated with this project renovation. See Tables 1 & 2 for wiring matrix

16.3 Contractor will install 24 strands SM FO from B703 North East UNCLASSIFIED comm room and terminate in Rack 1, new server room, via NEMA Enclosure 4

16.4 Contractor will install 50 Pair Copper from B703 North East UNCLASSIFIED comm room and terminate in Rack 1, new server room, via NEMA Enclosure 4 Wiring Matrix--Server Room Addition and Rm 106; Outlet boxes 6’ above raised floor R∆=Classified G∆=Unclassified

Rack1
Rack2
Rack3
Rack4
Rack5
Rack6
Rack7

R∆ (2) Cat6

X

R∆ (2) RG6

X

R∆ 4 str MM ST

X

G∆ (2) Cat6

X

G∆ (2) RG6
X

G∆ 4 str MM ST

X

Table 1

Wiring Matrix--Server Room Addition and Rm 106; Outlet boxes below raised floor R□=CLASSIFIED G□=UNCLASSFIED

Outlet box
Rack1
Rack2
Rack3
Rack4
Rack5
Rack6
Rack7

R□(4) Cat6

X

R□(6) RG6

X

R□12str MM ST

X

G□ (4) Cat6

X

G□(6) RG6
X

G□ 12str MM ST

X

Table 2

17. Comm Requirements for PRC-117 radio antenna roof-top infrastructure installation, West Server Room Addition: Contractor will EFI&T 2” conduit installation in southwest corner of new server room addition. Conduit will exit room via lockable NEMA enclosure and exit roof top via lockable, weather-proof NEMA enclosure. Contractor will install pull-strings in conduit. (Diagram 2)

18. Comm requirements for Bldg 703 South Office Addition; Contractor will EFI&T all communications wiring, outlet boxes, cable trays, NEMA enclosures, data racks, patch panels, Panduit, and associated parts to complete the communication req associated with this project renovation. See Table 3 for wiring matrix.

18.1 Contractor will EFI&T, 3 Great Lakes Case & Cabinet Co., Enhanced Series 24"x42"x86" Server Cabinets, 44U, GL840ES-2442MSFS. Include side panels, front, rear doors, and wire management panels.

18.2 Contractor will EFI&T 12 str FO SM from Bldg 703 North Server Room rack 1 to South Office Addition, terminate on Rack 1. Route thru NEMA Box 1, NEMA Box 5 and cable trays.

18.3 Contractor will EFI&T 12 pair copper from Bldg 703 North Server Room rack 1 to South Office Addition terminates on Rack 1. Route thru NEMA Box 1, NEMA Box 5 and cable trays.

18.4 Contractor will EFI&T cable trays under raised floor, route cable from racks 1-3 to outlet box locations 1-7 as detailed in Table 3.

B703 South Office Addition Wiring Matrix
Outlet box below raised floor
Outlet box 6 ft above raised floor
Data Cabinet Termination point
Outlet box
Positions 1-6
Position 7
Rack 1
Rack 2
Rack 3
12 str RED ST MM
X

X

4 str YELLOW SC MM
X

X

6 str GREEN ST MM
X

X

3 CAT6
X

X

2 str RED ST MM

X

X

2 str YELLOW SC MM

X

X

2 str GREEN ST MM;

X
X

Table 3

19. GCS Compound: Contractor will EFI&T 3, 4” HDPE conduits underground from Bldg 703 north server room addition to contractor-installed NEMA Enclosures in Ground Control Station compound. Contractor will install 4, 1” inner ducts in each 4” conduit; empty inner ducts will have pull string.

19.1 Contractor will EFI&T weather-proof, lockable NEMA Enclosures at each GCS location. Each enclosure will be free-standing and accommodate 3 entrance conduits and 1 exit conduit for comm connectivity. Conduit entrance/exits will be at bottom of enclosure. NEMA enclosures will be alarmed

19.2 Contractor will EFI&T, FO and Cat6 S/STP via Comm Hand Hole, to route & distribute CLASSIFIED fiber and UNCLASSIFIED copper wiring from B703, new server room, to each of 4 NEMA telecomm enclosures, via separate conduits (1 for FO and 1 for Copper). Alarm the Comm Hand Hole.

19.3 GCS Compound NEMA Enclosure Connectivity requirements, Table 4.

NEMA Enclosures on GCS Compound to Data cabinets in new server room

Each NEMA Enclosure
Rack1
Rack2
Rack3
Rack4
Rack5
Rack5
Rack6

48 st MM FO (SC)

X

24 str SM FO (ST)

X

48 st MM FO (SC)
X
24 str SM FO (ST)
X
6 ea, CAT6 S/STP
X

Table 4

19.4 Contractor will EFI&T 1” conduit, wiring, exterior phone and enclosure, outside GCS pad perimeter fencing, left side of turn style. Coordinate with 99CS/OL-A for Govt service point termination.

19.5 Contractor will EFI&T 1” conduit, wiring, exterior phone and enclosure, NE side, left side of double fencing, GCS pad perimeter. Coordinate with 99CS/OL-A for Govt service point termination.

19.6 Contractor will EFI&T 1” conduit, wiring, to each IDS alarm location. Coordinate with 99CS/OL-A for Govt service point termination.

20. B707 to B703 Fiber connectivity requirements

20.1 Contractor will EFI&T, 48 strand SC MM fiber from Bldg 707 server room rack 1, thru B703 UNCLASS Comm Room and terminate in bldg 703, Route thru NEMA Box 1 to server room addition, rack 2. Coordinate with 99CS/OL-A POC for routing thru available base infrastructure.

20.2 Contractor will EFI&T, 48 strand ST SM fiber from Bldg 707 server room rack 1, thru B703 UNCLASS Comm Room and terminate in bldg 703 , Route thru NEMA Box 1 to server room addition, rack 2. Coordinate with 99CS/OL-A POC for routing thru available base infrastructure.

20.3 Contractor will EFI&T, 48 strand SC MM fiber from Bldg 703 server room rack 1, terminate in bldg 703 room 115 wall rack, with 3m maintenance loop. Route FO thru NEMA 1 box, thru cable trays to Rm 115 location.

20.4 Contractor will EFI&T, 24 str ST SM fiber from Bldg 703 server room rack 1, terminate in bldg 703 room 115 wall rack, with 3m maintenance loops. Route FO thru NEMA 1 box, thru cable trays to Rm 115 location.

20.5 Contractor will EFI&T, 24 str ST MM fiber from Bldg 703 South office addition to new North server room rack 1, terminate in bldg 703 North server room addition rack 1. Route FO thru internal NEMA 5 box, thru cable trays to internal NEMA 1 box.

21. Ops Floor Room #106

21.1 Install one (1) STC 50 doors and frames, 3’-0” x 7’-0”, into new server room from room 106 and one (1) STC 45 door and frame from the hallway to room 106 in bldg 703 built to open storage at the secret level, in accordance to ICD 705. See drawing diagram #2 & 4 for approximate location

21.2 Install a raised floor system in room 106, approximately 20’-10” by 26’-11” to support five (5) operator console s, personnel and equipment. See drawing diagram # 2 & 4 for approximate location

21.3 Remove existing suspend ceiling system and all fixture and raised ceiling approximately 16” higher to accommodated raised floor system

21.4 Construct all walls true floor to ceiling in accordance to ICD 705. Install an insulator, to all conduits, pipes, and HVAC system penetration, in accordance to ICD 705

21.5 Reconfigure existing light circuits and install dimmer balances in light fixture to operate with two 3-way dimmer switches in Ops floor is on 2 variable switches, front ops floor and rear ops floor

21.6 Contractor shall keep existing projector mounts/screens are left in place, see diagram #2 & 4 for cable relocation.

21.7 Contractor shall install HDMI cable from classified floor gang to wall gang, desk 1-3

21.8 Contractor shall install HDMI cable from unclassified floor gang to wall gang, desk 1-3

21.9 Contractor shall install blue light in the new server room and ops floor, switch located at ops floor entry way and server room double door entry.

21.10 Request that Ops floor entry door is rated at STC-45 or better

21.11 Request that swipe badge is located at entry of ops floor; entry controlled separately than server room

21.12 Request to have Cadillac style raise floor, tiles NOT screwed down

21.13 Re-wire Ops room and console to back generator with auto-transfer switch

21.14 Contractor shall install separate A/C unit for Ops Rm #106, moisture control, and ambient control system

22. Server Room:

22.1 Construct new server room, approximately 11’-2” x 40’-0”, next to room 106

22.2 Redesign roof existing roof line to cover over new server room area in accordance with ICD 705

22.3 Request for bldg 703, room 106 addition built to SCI standard ICD 705

22.4 Contractor shall install server room addition have Cadillac style raised floor, tiles NOT screwed down.

22.5 Contractor shall install all server rack receptacles are on 6ft SO cord beneath raise floor (per cabinet)

22.6 Contractor shall install primary and secondary HVAC system; minimum 36,000 BTU units see diagrams #2 & 4. 4200 BTU per cabinet.

22.7 Request that server room lighting is on 1 variable switch

22.8 Request that server room exit to GCS compound is rated at STC 50 or better

22.9 Request that swipe badge is located at server room entry and server room entry from GCS compound, these are controlled separately than Ops Floor entry

22.10 Wire new server room with new 225 Amp load center which must be tied to back up power.

22.11 Install 1 STC(50) Doors from Room 106 to Server Room

23. GCS Compound:

23.1 Construct pad approximately 60 ft x 160 ft x6 in thick pad (psi 4500, type) Needs to be complete by NLT 01 Mar 12, see Diagram #1.

23.2 Construct concrete (psi 2500, type) walkway to server room entry. See Diagram #1.

23.3 Install out lighting for Lighting above server room double doors

23.4 Construct for awning, 11ft width above server room double doors to extend out 10ft.

23.5 Construct compound is fenced (type A) accordingly to meet secure compound requirements (guidance ICD 705).

23.6 Install card access system, compatible to base card system, swipe badge system is to be installed at the new turn style to go into the new area for the GCS area.

23.7 Install Grounding is compliant with ACC33-165

23.8 Install 4 street lighting for GCS pad area (at each corner of the new fenced in area).

23.9 Install Power Distribution System/ Load center, junction box for (1) 100amp Hubble style or approved equal and (2) 60amp Hubbles or approved equal style exterior light fixture

23.10 Contractor shall connect new GCS unit to new power source

23.11 Install back Generator with Automatic Transfer Switch (ATS) to support four GCS’s, Ops floor and new server room and new HVAC system for all new construction area/rooms.

23.12 Install PDS junction box is lockable and alarmed.

23.13 Install a 225 amps server panel per each GCS units. Each panel must support two HVAC systems per GCS.

24. Earthwork:

24.1 Remove and dispose of existing trees and shrubs. Grade area to natural slope

24.2 Remove existing drainage rocks

24.3 Re-grade, cut and fill an approximate area of 200’ by 75’. Bring grade elevation up to match the existing fence line retaining wall and slope towards existing concrete pad elevations

24.4 Design and install drainage to divert the water flow away from the existing and new concrete pads. ARCP and RCP with end section are to be used and installed per Clark County Unified Standards for reinforced piping

24.5 Contractor shall provide 35% construction drawings of earthwork and hydraulics calculations for the size of RCP to be used for approval before work is to commence.

25. Additional Office:

25.1 Request additional office space added to Bldg 703 (see diagram #3 )

25.2 Office space shall be constructed to ICD 705 (note: customer will provide SCI bodies pending Creech SSO recommendation)

26. Electrical sever in Ops room and new sever room:

26.1 Install all required receptacles per the current IBC and NEC and use drawing to show other type of power requirements. See drawing provided.

26.2 Provide power for UPS model HP R5500 Va 3U (L630P). APC Smart-UPS XL 3000Va RM 3U (L530O)

26.3 Install four floor receptacle 115/120VAC. See drawing for location.

26.4 Install four wall receptacle 115/120VAC. See drawing for location

26.5 Install four above ground receptacle 115/120VAC. See drawing for location.

26.6 Install 4 CAT6e Plenum rated. See drawing for location.

26.7 Install 6 RG6 BNC. See drawing for location.

26.8 Install 6 ST MM. See drawing for location.

26.9 Install 6ft above ground: See drawing for location

26.9.1 Install 2 CAT 6e Plenum rated

26.9.2 Install 2 RG6 BNC.

26.9.3 Install 2 ST MM

26.10 Install 4 CAT 6e plenum rated. See drawing for location.

26.10.1 Install 6 RG6 BNC

26.10.2 Install 6 ST MM

26.11 Install 6ft above ground: See drawing for location

26.11.1 Install 2 CAT 6e plenum rated.

26.11.2 Install 2 RG6 BNC

26.11.3 Install 2 ST MM.

26.12 Install Analog and Digital phone lines. See drawing for location.

26.13 Install two HVAC for each system for the new server room admin room and existing Ops room. Unit must tie-in to new ATS system. Approximate two 3-1/2 TON unit with separate thermostat per area.

27. Fire Suppression/ Alarms:

27.1 Update bldg’s fire alarm systems to new standards re-use all wiring and conduits and update.

27.2 Install horns and strobes in accordance with current NFPA

27.3 Install mass notification system in mechanical

End of Statement of Objectives