Further Clarification for Responses to Q&A’s posted 19 August 2011:
Question #12: Will the 35% Design elements, for the Demonstration Project as well as the Job Orders, require a Nevada licensed PE or RA?
Answer: Yes, the Project Engineer wet stamp will be required when submitting approval prior to installation. See specification UFC 3-600.
Further Clarification: The design elements for all future design and task orders will require a wet stamp of a licensed Fire Engineer, per UFC 3-600 dated 26 September 2006, Change 1 dated 14 July 2009. However, for submission of the demonstration project the wet stamp does NOT required
“Nevada” licensed Fire Engineer; it may be any state.
File details come from the government source that posted it. Updated .