FA4861-11-R-A400
Attachment #29
SABER
STATEMENT OF OBJECTIVES
FOR
Renovate Interior for Operations Cell Bldg. 707
LKTC 11-1040B
CREECH AIR FORCE BASE, NEVADA
17 August 2011
OFFICE OF THE BASE CIVIL ENGINEER
NELLIS AIR FORCE BASE, NEVADA
STATEMENT OF OBJECTIVES
1. SCOPE: Contractor shall furnish all design, labor, equipment, material, transportation, administration, supervision and all else necessary to perform all operations in connection with successfully completing this project LKTC11-1040B, Renovate Interior for Operations Cell
Bldg.707 atCreech AFB, Indian Springs, Nevada. When complete, the project shall be as shown below (either in the attached sketch or work description). Include in the submittal, reference to the specifications that apply to this project and identification of material items required to be submitted to the government for approval (use AF Form 66), both will be incorporated in the construction project.
2. LOCATION: The project site is located atCreech AFB, Nevada. The Main base is located approximately 55 miles north of Las Vegas on Highway US 95 (Las Vegas
Blvd.).
3. CODES: All design and construction must be in compliance with the International Building
Code (UBC-2006) (or most recent edition), Department of Defense Unified Facilities Criteria
Standards (UFC), all Public Laws, Executive Orders, Code of Federal Regulations, Department of Defense Instructions, (DODI), Department of Defense Directives, NAFB Design
Compatibility Guidelines, Clark County, State of Nevada and Federal standards, codes and laws or other higher authority documents as applicable.
4. DRAWING STANDARDS: All drawings submitted shall be prepared in accordance with the applicable provisions of the Architectural/Engineering/Construction (A/E/C) Computer-Aided
Design and Drafting (CADD) standard. All drawings shall comply with the specifications in
Attachment #1 for Simplified Acquisition of Base Engineering Requirements (SABER) dated 26
June 2011. Contractor shall maintain one set of drawings on site and record all changes and any hidden or subsurface data discovered during construction. Construction drawings shall be submitted to government with Red Line Marks.
5. ENVIRONMENTAL PROTECTION: All work and contractor operations shall comply with the requirements imposed by all applicable Federal, State, local and NAFB laws, regulations, codes and permits (including NAFB Management Plan12) concerning environmental protection.
6. DESCRIPTION OF WORK: The work to be accomplished includes but is not limited to the following description:
DEMO/Construction:
7. Remove approximately 8 feet of ceiling grid and tiles off all walls in GCS training rooms.
8. Remove two (2) existing main entrance wooden doors in both GCS training rooms.
9. Demo only one (1) GCS training room at a time. User will identify which room to start first at site visit.
10. Demo all locks off main entrance doors and return to government.
11. Remove all face plates, receptacles and all wall mount devices, in both GCS rooms. All materials will be saved for re-installation.
12. Construct pony wall on existing walls, extending wall to the bottom of roof deck and seal edge of wall and roof meets, in accordance with Open Storage to security level requirement.
13. Install all walls box extension in accordance with current National Electrical Code, (NEC).
14. Re-install all devices and receptacles that were removed to add the additional layer of 527 quiet sheetrock.
15. Install 5/8” quiet sheetrock from true floor to true ceiling and seal the edge of roof line and new wall, in accordance with Open Storage to security level requirement.
16. Mud, tape and finish all walls to match existing wall finishes and texture, color to be selected by the Government.
17. Prime all walls with one coat of prime and two coats of paint. Paint color to be selected by the government.
18. Install two (2) STC-50 doors and frame with threshold and magnetic seals around door jamb for the two GCS training rooms. Door measurement will measured by the contractor at site visit. Door must be tall and wide, as existing opening, enough to allow the removal and re-installation of similar sized existing equipment.
19. Install two (2) card access / card swipe with pin access system on each GCS trainer rooms. This system will be tied into the same system being installed in Bldg 703 and the new GCS pad area. Contractor shall submit all plans and materials to the Government prior to purchase and installation for approval of type of unit and placement of the system.
20. Install Magnetic locks on both doors on the inside of the room. Magnetic will work with the card access system for the users to gain access and exit the rooms. (no electric latches).
21. Install 180 degree motion sensors above the doors to act as release device for magnetic lock for exiting the GCS rooms.
22. Install two (2) LKM 7000 or equal combination locks without key override for each of the GCS training rooms in Bldg 707. See Tech Spec for ICD 705.
23. All existing penetrations made in the two (2) rooms will be sealed and insulated in accordance with IC Tech Spec for ICD 705.
24. All walls below the raised floor will be sealed in accordance to open storage security level.
25. Constructor shall refer to ICD 705 and 5200 1-R appendix G, Physical Security
Standards, Para 2 Secure room.
26. Only one of the GCS trainers may be renovated at a time; work will need to be planned/performed in phases.
End of Statement of Objectives