FA4861-08-R-A028-01.doc
DOC document 77 KB Posted
- Attached to
- Construct Hand Grenade Range
- Solicitation number
- FA4861-08-R-A028
About this file
Attached is an amendment that makes updates to the SOW based upon the 26 August 2008 site visit.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site Visit Q A | — | |
| Site Visit Q A.doc | DOC document | |
| Site Visit Minutes | — | |
| NV080022_Heavy_Rev07.dot | DOT file | |
| Solicitation 08-R-A028.doc | DOC document | |
| TC 25-8 Ranges 2004.pdf | ||
| LayoutHandGrenadeTrainingRange.pdf | ||
| FM3-23.30 Hand Grenade.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been added by full text:
STATEMENT OF WORK (5 SEP 08)
RKXF 08-8010
CONSTRUCT RANGE 6/6A HAND GRENADE TRAINING RANGE, R63C
(5 September 2008)
GENERAL REQUIREMENTS
SCOPE OF SERVICES:
The design-build contract will consist of two separate segments by the Contractor. The first is the Design Segment and the second is the Construction Segment. The specific requirements for this project are detailed in the description of work. These requirements will govern the Contractor’s Design and Construction Segments of the contract. The Scope of Services will include the following.
DESCRIPTION OF WORK:
The Contractor shall furnish all labor, supervision, materials, tools, equipment, incidental work, and professional design as necessary to design and construct a Hand Grenade Training Range at the Nellis Air Force Range (R63C) near Creech Air Force Base Nevada for the 99th Ground Combat Training Squadron. The training range consists of 6 earthen berms, 5 throwing pits, 1 observation pit and 1 ready wall. A proposed layout of the training range is provided for reference. Additional guidance is also available in US Army Field Manual No. 3-23.30, dated June 2005 and Training Circular No. 25-8, dated April 2004. The contractor will be required to submit a 35%, 95% and 100% final design package to the Government for review and approval. Offeror shall be responsible for obtaining any documents not attached as part of the RFP but referenced as criteria for the project. The project shall include, but is not limited to the following major items of work:
a. Earthen Berms (6 Total). Each earthen berm shall be 6 feet high. The cross section shall be trapezoidal, measuring approximately 6 feet wide at the top and 42 feet wide at the base. The longitudinal section shall be trapezoidal, measuring approximately 128 feet at the top and 164 feet at the base. The slope on all four sides shall be a rise of 1 foot per 3 feet of run. No borrow pit is available on site; therefore, all soil necessary to construct the earthen berms will be provided by the contractor. For berm soil description; construction spoil (recycle) without any petroleum products, also concrete materials not to exceed approximately 6” in size. is permissible. Outside layer after construction spoil shall be Type II rock and shall be 2’ thick and compacted to a minimum of 85%. The overall outside layer after Type II rock shall be 3’ thick Type II clean fill soil for added protection to prevent erosion. Provide necessary clearing and grubbing along with the demolition of existing structures. Berms shall be constructed parallel to each other and with a separation distance of 164 feet center-to-center. See proposed layout in ATTACHMENT #1 for reference. All Joshua trees and yuccas within the designated area are state protected and must be transplanted into a nursery area away from the impacted area. These trees need to be maintained in the nursery by watering 1 or 2 times per month with a water truck. Suggest that contractor trench rows for transplanting that are far enough apart to drive a water truck between the rows for easy watering.
b. Throwing Pits (5 Total). Each throwing pit shall be constructed with reinforced concrete walls and footing. Three sides of the structure measure 9’ wide x 6’ high x 0.5’ thick and the fourth side (knee wall) measures 9’ wide x 2’ high x 0.5’ thick. The top of the knee wall shall be sloped inward to allow any grenade dropped on the wall to roll into the throwing pit. Install drain pipes (no more than 2 inches in diameter) in the knee wall to allow throwing pit drainage. Slope the floor of the pits in the direction of the drainage pipes. The structure shall a dirt floor and no roof. The first 12 inches in depth of the pit floor shall be excavated and backfilled with sand. Additionally, a sand pit is also required outside of the throwing pit past the knee wall. Excavate an area 9 feet wide x 9 feet long x 12 inches deep and backfill the area with sand. See proposed layout in ATTACHMENT #1 for reference.
c. Observation Pit. This 3-sided structure shall be constructed with reinforced concrete walls, footings, and floor slab with no roof. The main wall of the structure shall measure 12’ wide x 8 feet high x 0.5’ thick. The other two wing walls shall each measure 9’ wide x 8’ wide x 0.5’ thick. Construct the wing walls at a 135( angle from the main wall. Provide a total of four (4) windows, each measuring 30” wide x 24” high. Install 2 windows equidistant across the main wall and 1 window centered on each of the wing walls. All the windows shall be installed approximately 46” from the finished floor elevation to the bottom of the windows. The window panes shall be 35 mm (about 1-3/8 inches) thick and constructed in accordance with paragraph C-4, page C-2, Appendix C of US Army Field Manual No. 3-23.30. The finished floor elevation shall be approximately 12” above grade. Provide concrete steps across the back side (the side without a wall) for easy access to the reinforced concrete observation deck floor. See proposed layout in ATTACHMENT #1 for reference.
d. Ready Wall. The ready wall consists of two detached reinforced concrete walls with a 6 foot separation. The total requirement is 48 LF of wall x 8’ high x 0.5’ thick along with adequate footings. The ready wall shall have a dirt floor and no roof. See proposed layout in ATTACHMENT #1 for reference.
DESIGN SEGMENT
1.
Contractor is responsible for field verifying all information given. The Design Segment shall consist of the following stages.
a. Contractor’s Proposal & Site Visit: A site visit will be scheduled after Contractor’s receipt of this RFP. Contractor shall provide a cost proposal only within 30 days after the site visit.
b. Notice to Proceed (NTP) with Design: After award and receipt of bonding, an NTP shall be provided to the Contractor to proceed with the Design Segment of the Contract. The contractor shall take the design to 35%, 95% and 100% design as specified below. The design segment shall be 91 calendar days, including government review as outlined below.
(1) 35% Design: The Contractor shall provide the government with the 35% design submittal to the Contracting Officer within 28 calendar days of receipt of the Notice to Proceed (NTP). The Government will then have 14 CALENDAR DAYS after receipt to review and provide comments back to the contractor.
(2) 95% Pre-Final Design: The Contractor shall provide the government with the 95% design submittal to the Contracting Officer within 21 calendar days of receipt of the Notice to Proceed (NTP) which will include the Government’s 35% design comments. This submittal shall consist of the proposed final Schedule of Materials, Equipment and Finishes and four sets of the drawings and specifications for review. The Government will then have 14 CALENDAR DAYS after receipt to review and provide comments back to the contractor.
(3) 100% Final Design: The Contractor shall provide the government with the 100% Design Submittal within 7 calendar days of approval of the 90% design submittal. After the specified review period, the Contractor shall incorporate all review comments received during the Final Design review. The Contractor shall submit one check set to allow the government to insure complete incorporation of the review comments. Upon approval of the check set, the Contractor shall then provide the Contracting Officer four bound sets of the final Schedule of Materials, Equipment and Finishes, and design analysis. The Contractor shall provide four sets of the specifications and full size hard copy drawings and the digitized drawings on CD media. The Government will then have 7 CALENDAR DAYS after receipt to review and provide comments back to the contractor. After final review and acceptance of the completed, 100% design, NTP will be issued to start the Construction Segment.
2.
Elements of submission are clarified below:
a.
Submittals:
(1) Specifications shall be provided using the Construction Specifications Institute (CSI) MasterFormat 2004 Edition (49 Divisions). If available, draft copies of these specifications can be provided to the contractor upon request. The contractor shall edit the specification sections that correspond with the work required in the project. All approved 100% specifications shall be submitted on Compact Discs in a file format that is compatible with Microsoft Word 2003 for Windows.
(2) Identify all the necessary submittals during design on AF Form 66, Schedule of Material Submittals. Provide AF Form 66 with the 95% design submittal.
(3) Provide twelve (12) copies (4-full size and 8-half size sets) for each interim design submittal to the Contracting Officer for review and approval.
(4) Materials submittals shall be prepared and submitted in four (4) copies on an AF Form 3000, Material Submittal, for government review and approval. The contractor shall identify and submit for review any long-lead material items. Once approved, the contractor may request these long-lead items be placed on order.
(5) All drawings and documents provided during each design phase will be clearly annotated with the current percentage of design complete.
b.
Stamped Drawings: The government requires that all drawings be wet stamped and signed by a professional engineer or architect on those pages pertaining to their disciplines. Provide wet stamped engineering design drawings and calculations for the civil, structural, and others as required.
c.
Hardcopy and Electronic Output: All documents presented by the Contractor during the submittal process shall be presented in hardcopy and both hardcopy and digitized for the final design submittal. The digitized drawings will have digitized manufacturer’s data (maintenance data, spare parts data, etc, with catalog cuts) available through hyperlinks on the appropriate AutoCAD drawings. Drawings created must be saved and provided in PDF and AutoCAD 2005. Any specifications, reports, or studies will be provided in Microsoft Word 2003 version. Electronic data will be provided on compact disks (CD) media.
d.
List of required design analysis: Civil and structural analysis, as applicable.
e.
Licenses: List all permits and licenses required to be obtained prior to start of construction work. The Contractor shall obtain all necessary underground utilities clearances, permits, and authorizations prior to beginning construction.
f.
Testing: Not applicable g.
Training: Not applicable h.
Abatement Plan: Not applicable i.
List of expected warranties and guarantees: One year from the date of final acceptance.
j.
List of Government Furnished Materials (GFM): None k.
Heating, Ventilation and Air Conditioning (HVAC) requirements: Not applicable l.
Energy Management Control System (EMCS) requirements: Not applicable m.
Fire suppression system, fire detection, alarm, and notification system requirements: Not applicable n.
Communications Requirements: Not applicable o.
Force Protection Requirements: Not applicable p.
American Disabilities Act (ADA) requirements: Compliance with ADA is not required.
q.
Exterior finish requirements: Not applicable r.
Roofing requirements: Not applicable s.
Doors and windows requirements: No doors are required on this project. See US Army FM 3-23.30 paragraph C-4, page C-2 for composition of laminated window panes.
t.
Interior finish requirements: Not applicable u.
Landscaping requirements: None.
v.
Site Improvement/Development requirements: The layout of the Hand Grenade Training Range shall be in accordance with the US Army Field Manual No. 3-23.30, dated June 2005 and Training Circular No. 25-8, dated April 2004.
w.
Utility Connection requirements: Not applicable x.
Licenses and Permits: Contractor is responsible for acquiring all necessary permits and fees for the legal operation of any installed equipment, to include dust permit, etc.
CONSTRUCTION SEGMENT
1.
NTP for Construction: After approval of the Final 100% Design Submittal, the Contracting Officer will issue a NTP for the Construction Segment of the contract. Construction shall be completed and ready for final inspection within 120 calendar days after receipt of the NTP.
2.
Pre-Construction Requirements: Upon acceptance of the 100% Final Submittal, the Contracting Officer will schedule a Pre-Construction Conference. It is anticipated that the NTP for construction shall be issued. As a minimum, the Contractor’s project manager and any appropriate subcontractor representatives shall attend a preconstruction conference at Nellis AFB. Upon receipt of the NTP for construction, the Contractor shall initiate all required digging permits.
3.
Pre-Final Inspection Requirements: When construction has progressed to the stage that the Contractor desires a Pre-Final Inspection, the Contractor can request one in writing to the Contracting Officer. The Contractor is responsible to continually maintain red-lined drawings during construction to reflect all changes to the project since Final Design approval. In addition to the red-lined copy of the drawings, the contractor shall provide a digitized set of the as-built drawings in AutoCAD.
4.
Contract Closeout Requirements: The contract will not be considered final or closed out until all requirements have been completed. This includes but is not limited to the correction of the inspection punch list items to the satisfaction of the Project Engineer / Architect and the Contracting Officer, the As-Built drawings in Auto CAD 2005 format have been received and accepted.
The following have been deleted:
STATEMENT OF WORK
SECTION E - INSPECTION AND ACCEPTANCE
The Acceptance/Inspection Schedule for CLIN 0001 has been changed from:
| INSPECT AT |
| INSPECT BY |
| ACCEPT AT |
| ACCEPT BY |
| Destination |
| N/A |
| Destination |
| Government |
To:
| INSPECT AT |
| INSPECT BY |
| ACCEPT AT |
| ACCEPT BY |
| Destination |
| Government |
| Destination |
| Government |
SECTION G - CONTRACT ADMINISTRATION DATA
The following have been modified:
G-403
SUBMIT INVOICES ELECTRONICALLY
(a) To expedite payment, reduce lost documents, and increase visibility into the status of payments, the Department of Defense (DoD) has implemented electronic invoicing. In conformance with Defense Federal Acquisition Regulation Supplement (DFARS) Clause 252.232-7003, Electronic Submission of Payment Requests, which is incorporated herein by reference, contractors shall submit invoices ELECTRONICALLY through the Defense Finance and Accounting System (DFAS) Web Invoicing System [Wide Area Workflow – Receipt and Acceptance (WAWF-RA)] at https://wawf.eb.mil/. Additionally, contractors can also concurrently create electronic receiving reports when they create their invoices (select CONSTRUCTION Invoice); with one keystroke they can ensure prompt presentation of the required data to the payment office.
(b) Applicable codes necessary for submission of invoices against this contract are as shown below.
(1)
ADMINISTERED BY:
FA4861
(2)
ISSUED BY:
(3)
CONTRACTING OFFICE:
(4)
PAYMENT OFFICIAL:
FORMDROPDOWN
(5)
INSPECT BY:
F3GHFA
(6)
LPO:
Leave BLANK
(c) Paper invoices may be rejected and returned by the DFAS Payment office and the contractor advised to invoice electronically.
(d) For assistance regarding specific electronic invoicing issues, please contact the WAWF Customer Service at 866‑618‑5988 or DFAS Electronic Commerce Division at 614‑693‑7674 . Web-based training is available at the WAWF site (http://www.wawftraining.com/).
(End of clause)
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
The following have been modified:
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| 13.9% |
| 9.6% |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is
Clark County, Nevada.
(End of provision) (End of Summary of Changes)