Official Questions Form updated .pdf
PDF 140 KB Posted
- Attached to
- 38th Technical Rescue FMP Course Training
- Solicitation number
- FA483026Q0001
About this file
This document is a Questions and Answers (Q&A) document for Solicitation FA483026Q0001 for a 38 RQS Technical Rescue FMP Course. The Q&A covers four key points: (1) and (2) the government is agreeing to extend equipment delivery dates by 90 days to accommodate potential supply chain or stock level challenges, with the contractor making best efforts to deliver items as soon as possible; (3) the Ranger Handbook specifications are confirmed as "Rite in the rain" paper in standard army handbook size; and (4) the event timeline indicates the 8th will be a travel and preparation day, while the 13th will be a training day with return travel.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Updated 38 RQS FMP PWS.docx | DOCX document | |
| DAF Approved Vendors List_16 JAN 26.pdf | ||
| Combo-Synopsis.pdf | ||
| UPDATED 38th RQS FMP PWS .docx | DOCX document | |
| Combo-Synopsis.pdf | ||
| Combo-Synopsis.pdf | ||
| 2026 FMP- Statement of Work .docx | DOCX document | |
| Combo-Synopsis.pdf | ||
| Pricing Schedule.pdf | ||
| 2026 FMP- Statement of Work .docx | DOCX document | |
| afman10-3511.pdf | ||
| Joint Travel Regulations 2026 PER DIEM Rate.pdf | ||
| Wage Determinations.pdf | ||
| Combo-Synopsis.pdf | ||
| 38th RQS FMP Regulations.docx | DOCX document | |
| ACC Element Leader QTP (Sep09).pdf | ||
| afman10-3507.pdf | ||
| 1T2X1 CFETP TCS CAO 12 July 18.docx | DOCX document | |
| Official Questions Form.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA483026Q0001- 38 RQS Technical
Rescue FMP Course Q&A’s
Question Answer
1. The contractor understands that a portion of the items marked as, “provided by contractor for reuse in course” would be needed at the time of the training event (Section 6, item a, subitem vii and item d., subitems xi, xii, and xiii). However, considering a portion of the other items are currently backordered or have an extended lead time per the manufacturer, would the Government consider extending the delivery date an additional 90 days for the medical items listed within this section other than the items noted for use in course, with the understanding that the contractor will make every effort to deliver these items as soon as possible?
Yes, we are fine with extending out the date 90 days for equipment
2. In accordance with SOW Section 16, the contractor must supply the equipment listed by Day One of the exercise (8th February 2026). Would the Government consider extending the delivery date by an additional 90 days to ensure the Contractor’s ability to receive, consolidate, and ship the items, based on the inability to check stock levels for some of the medical items due to pending sizing determinations?
2. Same as #1
3. Could the Government please provide specifications (e.g., type of paper, size, version) for the printed Ranger Handbook?
3. Rite in the rain paper, standard ranger handbook size as published by the army.
4. Will the 8th and 13th be travel days?
4.8 th will be travel and prep day, 13th will be training day and travel back
File details come from the government source that posted it. Updated .