Attachment 1 SOW XLWU 208174 revised 29JUL21.pdf
PDF 379 KB Posted
- Attached to
- Restore CEMIRT Parking Area Federal contract opportunity
- Solicitation number
- FA481921R0023
About this file
This statement of work describes a construction services contract opportunity for the Department of the Air Force at Tyndall Air Force Base in Florida. The contractor will be responsible for constructing a new secured parking facility and improving stormwater facilities at the CEMIRT facility. Specific tasks include extending the secured parking area to meet storage requirements, installing lighting and electric outlets for the new parking area, designing stormwater attenuation to improve an existing stormwater facility, and installing new fencing around the new parking facility. The contractor must follow all applicable construction codes and regulations and obtain necessary permits. The performance period is 365 calendar days after notice to proceed. The solicitation will use the lowest price technically acceptable source selection procedure. The requirement is set aside for service-disabled veteran-owned small businesses. The pre-solicitation notice provides details on monitoring the beta.SAM.gov website for solicitation release and amendments with a response deadline expected in June 2021.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
XLWU 20‐8174
Construct CEMIRT Parking Lot
Statement of Work
Department of the Air Force
325 Fighter Wing (ACC)
Tyndall Air Force Base, Florida
Page Intentionally Left Blank
Statement of Work
Repair Pavements, Multi
Tyndall AFB, Florida
Base Project Number: XLWU 20‐8174
30 March 2021
1.0 Introduction
The intent of this project is to construct a new secured parking facility and improve storm water facilities at the CERMIRT facility with in Tyndall Air Force Base (AFB). Contractor shall perform the services herein and as described in this Statement of Work (SOW).
2.0 Scope of Work
The Contractor shall be responsible for all professional services, permits, equipment, labor, tools, materials, and ancillary items necessary to complete the tasks defined by the SOW. The performed tasks shall be based on the project description, other data furnished in this SOW, and information covered during a pre‐construction/criteria review meeting to be held prior to Contractor mobilization.
2.1 Scope and Applicable Documents
This SOW sets forth the requirements for a Sustainment, Restoration & Modernization (SR&M)
Acquisition contract for a site specific construction effort for repair of select pavements located on
Tyndall AFB, Florida. The Contractor shall adhere to the following guidance during construction phase(s) of this project: Unified Facilities Criteria (UFC) 3‐250‐01, Pavement Design for Roads and
Parking Areas; UFC 3‐250‐03, Standard Practice Manual for Flexible Pavements; UFC 3‐600‐01, Fire
Protection for Facilities; United States Army Corps of Engineers; Uniform Building Code (UBC); those sections of the Southern Standard Building Codes not incorporated in the UBC/International Building
Code (IBC) for our respective area; Air Force Standards; Department of Defense (DOD) Directives;
Florida State Statutes; Florida Department of Transportation (FDOT); the Tyndall AFB Facility
Excellence Plan (Base Regulations); 325th Fighter Wing Bird Aircraft Strike Hazard (BASH) Plan 910;
National Electric Code (NEC); Occupational Safety and Health Administration (OSHA) Requirements;
Department of Environmental Protection (DEP) Regulations; Environmental Protection Agency (EPA)
Regulations; and any related Americans with Disabilities Act (ADA) Compliance Requirements. If there is a conflict between these codes, regulations and specifications the most stringent requirements shall apply at all times. Documents listed by and/or provided by the Government are for reference only and do not relieve the Contractor from adherence with applicable codes not specifically addressed.
2.2 Description of Work
The project intent is to extend the secured parking area to meet the user’s storage requirements as outlined in Appendix A and to improve existing storm water facilities. The project is a design – build effort which includes all aspects of design, permitting and construction of the secured parking area which includes lighting, electrical outlets, storm water attenuation facility, and fencing. The
Contractor shall implement means and methods that will limit disturbance to the natural vegetation, dune systems, water bodies and base activities to the greatest extent practicable throughout the project performance. Maintenance of Traffic (MOT) guidelines shall be followed. Unless noted otherwise, work is anticipated to be performed during normal working hours. The Government provided documents and existing field conditions shall be reviewed by the contractor to identify any potential discrepancies and develop necessary Requests for Information (RFI) prior to construction mobilization.
The project work is outlined in the following tasks:
2.2.1 Task 1.0 (New Parking Facility)
Extend secure parking facility to meet user’s requirements as outlined in Appendix A. Area of new impervious surface not to exceed 60,000 SF. Pavement is to be rigid (concrete) pavement and must be designed to meet load requirements. Design will ensure minimal uncontrolled cracking, and proper load transference to reduce deflection and stress at the joints.
A. Clear & Grub site B. Compact sub grade C. Install and compact base D. Install Rigid (concrete) pavement
2.2.2 Task 2.0 (Lighting & Electric)
Install lights and electric outlets for new parking area to meet requirements set forth in the SOW.
Gulf Coast Electric Cooperative (GCEC) is the private utility contractor on Tyndall Air Force base and as such will maintain ownership and maintenance of all lighting and electric components. GCEC will be responsible for all construction and installation efforts involved in the electric and lighting component of this project. The prime contractor will be responsible for coordinating with GCEC to include cost for this effort.
A. Design and install lighting for new parking area. Lights to be user controlled with electrical control switches at entrance to parking area.
B. Install 2 20 amp receptacles every 20 ft around perimeter of new parking facility.
Receptacles are to be install above ground in water-proof electrical boxes. Every set of receptacles are to be on a dedicated 20 amp circuit. Electric panel to be clearly marked to indicate breaker to outlet circuit.
2.2.3 Task 3.0 (Storm water facilities)
Design storm water attenuation to improve the existing stormwater facility and meet the needs of the new parking. Florida Department of Environmental Protection storm water permit will be required. Permit submittal must be reviewed and approved by CES prior to submitting to FDEP.
A. Remove berm #1 B. Remove berm #2 and install overflow barrier C. Install attenuation (rock) at downspouts for buildings # 1141 & 1142 D. Re-slope and regrade erosion site #1 E. Install attenuation (rock) at erosion site #1 F. Re-slope, regrade and re-sod existing retention and conveyance swells.
G. Install new storm water facility for new parking area.
2.2.4 Task 4.0 (Fencing)
Install new fencing around new parking facility to maintain secure environment for storage area.
A. Remove existing fencing in area connecting existing parking area to new parking area.
B. Install new 8 foot chain link fencing with privacy slats extending existing fencing to secure new parking area.
C. Install 6 in concrete filled steel pipe safety bollards as necessary to protect perimeter fencing.
2.3 Security Requirements
MIL‐HDBK‐1013: DOD Military Handbook Design Guidelines for Physical Security of Facilities.
AFI 31‐101: Air Force Instruction 31‐101: The Air Force Installation Security Program
DOD 5200.1.R: DOD 5200.1.R: Information Security Program Construction Standards
UFC 4‐010‐01: Unified Facilities Criteria Antiterrorism Standards for New and Existing Facilities
2.4 Permits (Where Applicable)
The Contractor shall develop, coordinate, and be responsible for labor and other costs associated with acquiring any and all required state, local, and other applicable permits; base access (including off‐base easements and leases), agreements, licenses, and certificates required to perform and complete the project. Before the start of work, the Contractor shall process an Air Force Form 103, Work Clearance Request, through the local Base Civil Engineer (BCE) office. The Contractor shall maintain a library of the documents on site as well as at the corporate facility handling each project.
The Contractor shall comply with applicable permit conditions, environmental protection policies and appended guidelines.
2.5 Design:
The Contractor shall acquire Florida licensed professional design services to develop complete construction documents to meet the requirements of the contract documents.
2.6 Construction:
Upon approval by the Contracting Officer (CO) and receipt of all required permits (if applicable) and phasing plans, the Contractor may commence on‐site construction activities. The Contractor shall conform to all specifically referenced requirements and other applicable requirements during performance of the work as described in the SOW:
1. Mobilization: Mobilize equipment, labor, tools, materials, and ancillary items necessary to complete the work defined in the SOW.
2. Demolition/Construction: Perform awarded tasks as defined in Section 2.2, Description of
Work.
A. Protect work area with barricades, warning tape, signs and/or other appropriate methods for the work being completed to ensure the safety of pedestrians, contractor personnel, vehicles, and property;
B. Remove and dispose of all demolition and general construction debris from the site (off‐ base);
C. Perform ancillary efforts required to complete the work necessary to provide a clean, complete, and functional facility;
D. Limit disturbance to the natural vegetation, persons, and property to the greatest extent practicable.
2.7 Government Furnished Equipment:
None
3.0 General Requirements
Applicable provisions of the Contract Clauses in the contract will govern work under each section of the specifications.
3.1 Pricing Schedule:
The Contractor shall complete a Pricing Schedule and include the completed schedule with the submitted bid documents.
3.2 Kick‐Off Meeting:
A kick‐off meeting shall be accomplished with the Contractor, CO, the Civil Engineer Squadron (CES), and user in accordance with the Table of Deliverables (Section 8.10 of the SOW). The meeting objective is to review project details, determine the start date, security procedures for the site, dumpster locations, and any applicable requirements during construction. The Contractor shall visit the job site to verify location, conditions, and dimensions prior to starting work.
3.3 Facility Occupancy:
The road and parking facilities covered by this contract are currently open to the public and experiences low to moderate pedestrian and vehicle traffic. During performance of this contract, non‐work areas will remain functional to normal activities unless noted otherwise. Refer to the Task
Descriptions for task specific occupancy conditions. Base personnel will relocate military vehicles/equipment from the work areas. The Contractor is responsible for all maintenance of traffic
(MOT) in the work areas for the duration of the performance period.
3.4 Identification of Employees
The contractor shall be responsible for obtaining security clearances and badges for each employee, and for requiring each employee engaged in the work to display identification as approved and directed by the CO and Security Forces. The contractor shall submit personnel background check applications for badging within fourteen (14) days after award. Badge processing typically requires fourteen (14) days to complete and badges are issued to the applicant in‐person at the Tyndall AFB
Visitor’s Center. During performance of the contract, prescribed identification shall immediately be delivered to the CO for cancellation upon the release of any employee. When required, the
Contractor shall obtain and provide fingerprints of persons employed on the project. All Contractor and sub‐contractor personnel shall wear identifying markings clearly defining the company for whom the employee works.
3.5 Employee Parking:
Contractor employees shall park privately owned vehicles in an area designated by CES and approved by the CO.
3.6 Job Site Tools and Equipment:
All hand tools and equipment shall be maintained in good working condition and properly stored when not in use. Construction attire shall be in accordance with applicable OSHA regulations.
3.7 Notification Requirements:
The Contractor shall notify the Government a minimum of ten (10) days in advance of mobilization.
The Contractor is required to notify the CO and Government Project Manager of critical issues that may affect the contract performance and/or human health and the environment. For critical issues pertaining to human health and the environment, the Contractor shall immediately notify the CO and stop work. Work shall only resume at the direction of the CO following resolution of the issue.
3.8 Environmental Protection:
Activities shall be planned and implemented in a manner that protects existing site utilities, structures, surface features, service operations, critical wildlife, and the general site environment.
This includes the protection of the trees, shrubs, and other vegetation not in the affected zone from dust damage, soil compaction, and physical contact with machines and equipment. If appropriate, the Contractor shall conserve uncontaminated topsoil by removal, storage, or redistribution. All reasonable measures shall be taken to minimize and suppress fugitive emissions of dust, vapors, and other site materials during site work. All fill materials shall be non‐contaminated. The Contractor shall conduct operations and activities with the intent of reducing the amount of pollution generated.
Specific areas to be focused on are generation of solid waste, use of hazardous materials, use of ozone depleting chemicals, generation of hazardous waste, and use of energy and water. The
Contractor shall plan, construct, operate, maintain, optimize, and commission systems necessary to control any storm water run‐on and runoff. At a minimum, the Contractor shall employ best management practices consistent with the Florida Development Manual, Chapter 6, Storm‐water and
Erosion and Sediment Control Best Management Practices for Developing Areas.
3.9 Hazardous Waste Management:
CO will notify 325 CES/CEA if any hazardous waste is encountered or generated by the Contractor.
The Contractor shall stop all work in the event 325 CES/CEA identifies noncompliance with federal and state regulations and shall correct any discrepancies immediately within 2 hours of notification by 325 CES/CEA. All hazardous waste shall be labeled and an inventory management system will be initiated to insure timely removal and proper disposal. No on‐base disposal will be allowed. All drums will be labeled with a hazardous waste label. The label shall include the proper Department of
Transportation (DOT) shipping name, United Nations (UN) or North American (NA), EPA waste number, generator information, and accumulation start date. The label shall be placed on the side of the drum. All drums used to store hazardous waste shall be non‐leaking and safe to handle.
Contractor shall be responsible for over packing drums that are rusted, dented, or leaking. Drums and/or over packs shall be provided by the Contractor. All drums shall be “new” DOT approved containers. The storage location for the hazardous drums shall be approved by the 325 CES/CEA prior to the generation of hazardous waste. The Contractor shall document inspection of drums for leaks on a daily basis or if not working in the area daily, then document the inspection of drums for leaks on a weekly basis. A copy of the inspection checklist shall be coordinated through 325 CES/EA. The
Contractor shall be responsible for transportation and disposal shall be coordinated through 325
CES/CEA every Friday. Hazardous waste transportation and disposal of all hazardous waste at an EPA approved treatment, storage, disposal facility (TSDF). The transportation and disposal facilities shall be approved by 325 CES/CEA prior to their use. Manifests shall be signed only by 325 CES/CEA. Drums shall be disposed of within 90 days of placing the first drop in the container.
3.10 On‐Site Field Oversight:
The Contractor shall provide the manpower, equipment, material, services, and transportation necessary to ensure oversight services throughout accomplishment of the construction period for the
Invitation for Bid (IFB). It is the responsibility of the Contractor to establish and maintain open communications between salient authorities associated with accomplishment of this contract.
3.11 Federal Holidays:
Tyndall AFB observes the following Federal Legal Holidays:
New Year’s Day 1 January
Martin Luther King’s Birthday Third Monday in January
Presidents’ Day/Washington’s Birthday Third Monday in February
Memorial Day Last Monday in May
Independence Day 4 July
Labor Day First Monday in September
Columbus Day Second Monday in October
Veterans Day Second Monday in November
Thanksgiving Day Fourth Thursday in November
Christmas Day 25 December
3.12 Working Hours:
The normal duty hours are from 7:00 AM to 5:00 PM, Monday thru Friday excluding Federal Holidays.
The Contractor may submit a request to the CO for approval to perform work outside of normal duty hours, on weekends, and on holidays. This request shall be submitted no less than three (3) workdays prior to the time requested.
3.13 Availability and Use of Utility Services:
The Government will make all reasonably required utilities available to the Contractor from existing outlets and supplies, as specified in the contract.
3.14 Sanitation:
The Contractor shall provide and maintain with in the construction area minimum field‐type sanitary facilities approved by the CO. Government toilet facilities will not be available to the Contractor’s personnel.
3.15 Clean Up:
At the end of each working day, the Contractor shall clean up the work site by the removal of all construction debris, waste materials, packing material and the like. If the previously mentioned items could become airborne they shall be placed in refuse containers immediately. Clean up of the work site shall include the construction area(s), construction office area(s), material storage area(s), parking and eating area(s), and any other area(s) affected by the construction process. Any dirt or mud which is tracked on to any Base street, parking area, sidewalk, patio, or driveway shall be cleaned away daily. Materials resulting from demolition activities which are salvageable shall be stored within the work area or a supplemental storage area. Stored material not in trailers, whether new or salvaged, shall be neatly stacked when stored in an approved location.
3.16 Contractor’s Management and Use of Electromagnetic Emission Devices on Base:
Electromagnetic emission devices include: Radio/Radar Transmitters; Navigational
Aids/Instrumentations; Signaling, Intrusion Detecting, and Identification Devices; Mobile and Fixed
Business Radio Communications Equipment; and Military Affiliate Radio System (MARS), Citizen Band radios (CBs), and Amateur Radio Stations. The Contractor shall comply with the Air Force Military
Training Center (AFMTC) Regulation 700‐14, July 1989.
3.17 Preparation of Progress Schedules and Reports:
The reports contemplated by Clause 52.236‐15, Schedules for Construction Contracts, shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, Contract Progress
Schedule and AF Form 3065, Contract Progress Report. Contract Schedules and Reports shall run from
Monday through Sunday and be submitted to the CO per Table of Deliverables (Section 8.10 of the
SOW).
4.0 General Safety Requirements
4.1 Workplace:
Provide a safe workplace for employees and the general public while performing the contract work.
4.2 Personal Protective Equipment:
Supply each employee with personal protective equipment. This equipment includes (but is not limited to) protection for the eyes, face head, ears, and extremities. Use the proper protective equipment for the work performed.
4.3 Roads:
Obey the posted base speed limits. Wear seat belts on base in accordance with AFI 91‐207, The US
Air Force Traffic Safety Program.
4.4 Accidents:
Report Contractor accidents involving injury to Air Force personnel or damage to Government property to the Base Law Enforcement Desk and the CO.
4.5 Safety Regulations:
Familiarize yourself and comply with the general safety requirements in accordance with Department of Labor (DOL) regulations, OSHA 29 CFP Part 1926, as well as applicable Air Force Office or Safety and Health (AFOSH) standards and Air Force Regulations (AFR). These standards and AFRs are available in the Wing Ground Safety Office, Building 662.
4.6 Required:
Standard Section Subject
OSHA 1910, Occupations Safety and Health Standards
.133/.134/.135/.136/.138 Personal Protective Equipment
OSHA 1910 .215 Explosives
AFM 91‐201, Explosives Safety Standards
Explosives Safety Standards
OSHA 1926, Safety and Health Regulations for Construction
Subpart H Material Handling
OSHA 1926 Subpart O Mechanized Equipment
OSHA 1926 Subpart Q Concrete Forms
OSHA 1926 Subpart T Demolition
AFOSH 161‐4, Exposure to Asbestos Asbestos and PPE
OSHA 1910 .1001 Asbestos
AFOSH 91‐5, Welding and Cutting (Hot Work)
Welding, Cutting, Brazing
National Electric Code (NEC) Electrical Work
OSHA 1926 Subpart P Trenching
OSHA 1926 Subpart G Barricades
AFOSH 91‐25, Confined Spaces Confined Space Entry
OSHA 1926 Subpart L Scaffolding
4.7 OSHA Inspections:
The Contractor shall be subject to no‐notice inspections under OSHA program by inspectors of the
DOL.
4.8 Protection and Maintenance of Traffic:
During construction the Contractor shall provide and maintain MOT equipment and personnel in accordance with FDOT standards to ensure the safety of pedestrians and vehicles. The Contractor shall maintain and protect traffic on all affected roads/pedestrian paths during the construction period except as otherwise specifically directed by the CO. Measures for the protection and diversion of traffic, including the provision of watchmen and flagmen, erection of barriers, placing of lights around and in front of equipment and the work, and the erection and maintenance of adequate warning, danger, and direction signs, shall be required by the State and local authorities having jurisdiction. The traveling public shall be protected from damage to person and property. The
Contractor’s traffic on roads selected for hauling material to and from the site shall interfere as little as possible with public traffic. The Contractor shall investigate the adequacy of existing roads and the allowable load limit on these roads. The Contractor shall be responsible for the repair of any damage caused by their operations.
4.9 Barricades:
The Contractor shall erect and maintain temporary barricades to limit public access to hazardous areas as required by OSHA, Florida Department of Transportation, and related Agencies. Such barricades shall be required whenever safe public access to paved areas such as roads, parking areas, sidewalks, or other work areas are prevented by construction activities or as otherwise necessary to ensure the safety of both pedestrian and vehicular traffic. The minimum required number of barricades shall be securely placed in a neat and orderly fashion, clearly visible with adequate illumination to provide sufficient visual warning of the hazard during both day and night. Barricades shall be maintained in an orderly fashion during the duration of their placement.
4.10 Severe Weather:
Upon the receipt of the CO of a severe weather warning with anticipated winds of 35 knots or higher, the following sequence of actions shall be carried out:
4.10.1 Notification:
The CO or the Contracting Officer’s Representative (COR) will notify the Contractor of the severe weather warning.
4.10.2 Notification to Secure Property:
The CO or COR will instruct the Contractor to secure all materials and equipment.
4.10.3 Secure Property:
The Contractor shall take immediate action to tie down, remove, protect, and/or secure construction materials, equipment, and refuse to the satisfaction of the Air Force Inspector in order to reasonably assure that Government property will not be damaged. If the Contractor fails or refuses to secure materials and equipment to the satisfaction of the Air Force Inspector, the work will be accomplished by Air Force personnel and the cost thereof charged to the Contractor.
4.11 Fire Regulations and Preventative Practices:
The Contractor shall comply with fire prevention practices as set forth by the National Fire Protection
Association (NFPA), other recognized fire prevention agencies, and base regulations.
4.12 Explosive Operated Hand Tools:
The Contractor shall comply with OSHA Standard 1910.215 when utilizing explosive operated hand tools. Storage of explosive cartridges on the installation shall be in metal containers and limited to one days’ supply. The Contractor shall provide adequate controls to prevent loss/theft of cartridges used and stored on the installation.
4.13 Welding:
Welding shall not be performed without first obtaining a welding permit issued by the Base Fire
Department.
5.0 Generated Refuse
5.1 Refuse:
The Contractor shall take positive action to prevent work‐generated refuse from entering the sewer system and water bodies. All Contractor generated refuse and waste shall be hauled from the construction site daily to a disposal area located outside the physical boundaries of the installation.
This refuse and waste material shall be hauled in with tight‐fitting beds and covers to prevent spillage on roadways and waterways. The construction site shall be kept neat, orderly, and safe for workmen at all times.
5.1.1 General Waste Material
All waste materials other than uncontaminated recyclable metals generated by any work under this contract shall become the property of the Contractor and shall be handled, transported, stored and disposed of off‐base by the Contractor at the end of each work day. Such material shall be hauled off‐ base to a Contractor selected disposal area and disposed of in accordance with applicable Florida
Administrative Code 62‐701, Solid Waste Management; federal, state, and local laws; ordinances;
regulations; court orders; or other types of rules or rulings having the effect of law. The Contractor shall provide the CO with the waste manifest tickets for all disposal runs associated with the project.
5.1.2 Salvageable Goods
Salvageable, goods shall be turned in to the appropriate base agency. Precious scrap and waste metals (e.g. steel, iron, etc.) shall be recycled and/or disposed in accordance with base policies.
6.0 Utility Outages
6.1 Definition:
Utility outages shall be defined as a stoppage in electric, gas, potable water, sewer, chilled or hot water, steam, telephone, Energy Monitoring and Control System (EMCS), or any other similar utility whether serving all or a part of a single facility or of several facilities.
6.2 Outage Coordination:
All utility outages shall be coordinated with the Using Agency through the CO or the COR. Notice of the necessity for an outage shall be provided by the Contractor to the CO in writing, not less than seven (7) working days prior to the time of the required outage and written approval for the outage will be issued by the CO. All work shall be coordinated and arranged to ensure that the outage will be of minimal duration.
6.3 Utility Restoration:
Once a utility outage is arranged and work begin, work shall continue until all utilities are restored to the affected facility or facilities.
6.4 Cancellation:
In the event a scheduled utility outage is cancelled by the Government, notification will be given to the Contractor at least 24 hours in advance of the time for the outage to start. Rescheduling of a cancelled outage must be coordinated with written notification as described above.
7.0 Existing Utilities
7.1 Reference Drawings:
Record drawings showing existing underground utilities are located in Building 36270, Tyndall AFB.
The Contractor shall avail himself/herself of the drawings. Any utility line shown on the record drawings (or made known to the Contractor) and damaged during construction work shall be repaired immediately by the Contractor at no cost the Government.
8.0 Deliverables/Submittals
8.1 Construction Phasing Plan:
The Contractor shall submit a Phasing Plan a minimum of ten (10) days in advance of mobilization.
The plan should define in detail work phasing intent of the Contractor with dates and duration for each phase of work. Note that the Government anticipates that the work will be primarily continuous after mobilization and that portions of the work may be in progress simultaneously. This plan will be used as the basis for base populous notification and planning.
8.2 Contract Progress Schedule (AF 3064):
The Contractor shall submit a signed AF 3064 (or approved equivalent), Contract Progress Schedule, depicting an overall contract progress schedule for the main elements of work for the period of performance as described in the Table of Deliverables (Section 8.10 of the SOW). The Contractor shall provide a line graph depicting actual construction progress (solid line) versus scheduled construction progress (dotted line) throughout the period of performance. The progress schedule shall be signed by either the COR or the Government contract inspector recommending approval and approved by the CO. If the Contractor requires reimbursement of a high dollar value item, the item shell be identified on the AF 3065, an appropriate percentage applied, and the item must be received and stored on the site.
8.3 Contract Progress Report (AF 3065):
The Contractor shall submit AF 3065 as described in the Table of Deliverables (Section 8.10 of the
SOW). This report shall be signed by the Contractor’s on‐site representative in the Remarks section of the AF 3065. The work elements and percentages on the AF 3064. The Contractor shall obtain either the COR or the Government contract inspector’s acceptance by signature of the actual reported progress prior to submission to the CO. Additionally, the Contractor shall submit the updated AF3064 as an attachment to the AF3065.
8.4 Work Clearance Request / Digging Permit:
Obtain a blank AF Form 103, Base Civil Engineer Work Clearance Request (often called a digging permit) from 325 CES Customer Service, (850) 283‐4949. Contractors shall request a digging permit at least ten (10) working days in advance.
8.5 Hazardous Material and Hazardous Waste:
The Contractor will submit Tyndall AFB (TAFB) Form 81 (Contractor Questionnaire) and TAFB Form 82
(Chemical Inventory) in ten (10) days upon issuance of the notice to proceed and prior commencement of work on site. The Contractor should note that Tyndall AFB is required to report chemicals such as (but not limited to) compressed gases, adhesives, aerosol, cans, sealants, paints, lubricants, solvents, oils, cleaners, degreasers, and pesticides. Copies of manufacturer‐specific
Material Safety Data Sheets (MSDS) must be attached to TAFB Form 82. After submission, CEA will notify the Project Manager and/or CONS of the reportable chemicals and of any special instructions.
The Contractor is required to submit TAFB Form 83 (Reporting Entry Form) at the end of the project or as indicated by CEA. CEA must be notified if anything changes from the original submittal (i.e. new chemical is added, size of container or unit of issue changes or if the manufacturer changes).
8.6 Construction Documents:
Design drawings, calculations and specifications for each awarded task shall be well prepared, complete, and accomplished in accordance with the best professional practice to show clearly and concisely the type and extent of work to be performed. The drawings shall be drawn to appropriate scales and dimensioned completely and accurately. Extensive explanatory notes on the drawings should be held to a minimum or placed in the specifications. Dimensions shall be shown in Standard English units. Standard building material indications and symbols for architectural items and for mechanical and electrical equipment shall be used to the greatest extent possible.
8.6.1 Drawing Standards:
Drawings shall be prepared on AutoCAD release 2008 or compatible format. All drawings will utilize the Tri‐Service Spatial Data Standards (TSSDS) Version 1.8, for compliance with the installation standards. Digital copies of all drawings for project files and CES review shall be provided to the Contracting Officer for project at each of the design submission phases. Approved, For Construction plan set shall be provided digitally and in hard copy with the designer of record’s signature and seal.
When the 100% design drawings are accepted, the contractor may then begin construction. As‐Builts shall be submitted to the government upon completion of construction and shall be reviewed for accuracy. Upon approval, the contractor shall provide electronic versions of the As‐Built drawings in both AutoCAD 2008 or later, and as .PDF to the government on CD. The drawings shall be drawn to appropriate scales and dimensioned completely and accurately. Extensive explanatory notes on the drawings should be held to a minimum. Dimensions shall be shown in Standard English units.
Standard building material indications and symbols for architectural items and for mechanical and electrical equipment shall be used to the greatest extent possible.
8.6.2 Government Review:
The Contracting Officer or the authorized representative may furnish the contractor review comments on the data submitted at each of the design submission phases. The Government's review is intended to be limited to functional aspects, with limited technical review of a Page 9 of 13 general cursory nature only. Any review by the Government of technical items shall not be construed to relieve the contractor of responsibility for technically correct and complete documents in compliance with applicable codes, industry standards, and the intent of this SOW. Review comments for compliance with Federal Acquisition Regulations (FAR) will also be provided by the Contracting Officer. Government design review comments will be issued to the contractor in accordance with the Table of Deliverables. If any review comment requires clarification and/or amplification to assure compliance, the contractor shall notify the Contracting Officer or the authorized representative in writing. After each review, the contractor will be furnished the comments to be annotated and returned to the Government. Comments annotated by the contractor with a "D" ‐ do not concur, "E" ‐ exception, or "X" ‐ delete, shall have an explanatory note added to justify the noncompliance with the comment. The contractor shall furnish these annotated comments to the Government within the time period specified in the Table of Deliverables. The contractor shall comply with the review comments in the development of data for the next submittal.
8.6.3
The Contractor shall provide 35% design for review and comment. This package shall contain sufficient detail for general compliance verification for location, materials, and overall concept. The Government will perform a design submittal review and provide the Contractor with review comments as defined in Section 8.6.2. Government acceptance will be issued to acknowledge receipt of the design submittal. Government comments shall be addressed in the following design review submission. Refer to the Table of Deliverables for submittal, review period, and conference details.
Design Submittal Requirements
a. AF Form 3000 documenting the submittal contents.
b. Table of Contents.
c. Design analysis summarizing design approach.
d. Initial plans and details.
8.6.4
The Contractor shall provide 95% design for review and comment. This package shall be in a substantially complete design state. The Government will perform a design submittal review and provide the Contractor with review comments as defined in Section 8.6.2. Contractor shall schedule and attend a final review conference meeting at Tyndall AFB, FL. Formal acceptance of the submittal will be issued when the government comments have been addressed in the construction documents.
Refer to the Table of Deliverables for submittal, review period, and conference details.
Design Submittal Requirements
a. AF Form 3000 documenting the submittal contents.
b. Table of Contents.
c. Design analysis summarizing design with completed engineering calculations.
d. Essentially complete construction documents.
e. Fully populated AF Form 66; Schedule of Material Submittals.
8.6.5
The Contractor shall provide 100% Final Design package. All previous Government comments shall be addressed in this design package. No review conference is required for this design submittal. The submittal will be formally approved upon verification that the package is complete and all previously provided review comments have been addressed. Refer to the Table of Deliverables for submittal details.
Design Submittal Requirements
a. AF Form 3000 documenting the submittal contents.
b. Review comments and Contractor responses from 95%.
c. Minutes and sign‐in sheet of 95% review meeting.
d. Final design analysis.
e. Final construction documents.
f. Final AF Form 66; Schedule of Material Submittals
8.7 Transfer and Acceptance of Military Real Property (If Applicable):
The Contractor shall prepare and submit a DD Form 1354, Transfer and Acceptance of Military Real
Property document. The draft and final copies shall be submitted in accordance with the Table of
Deliverables (Section 8.10 of the SOW).
8.8 Pre‐Final Inspection:
The Contractor shall conduct a pre‐final walk through inspection with Base personnel and publish the pre‐final inspection findings in a pre‐final inspection (punch list) report. The Contractor shall include a draft DD Form 1354, Transfer and Acceptance of Real Property to the COR for review.
8.9 Final Inspection:
The Contractor shall conduct a final inspection with base personnel and publish the findings in a final inspection report. The inspection shall concentrate on the items identified and recorded in the pre‐ final inspection (punch list) report. A final inspection shall not be performed until the pre‐final inspection (punch list) report has been resolved. A the final inspection, the Contractor shall present a completed DD Form 1354, Transfer and Acceptance of Real Property to the Base Civil Engineer (BCE) or other appropriate organization for signature and acceptance, if required.
8.10 Delivery/Warranty:
The Contractor shall complete all inspection and commissioning requirements prior to final inspection. Following final inspection, the Contractor shall deliver to the Government the warrant documentation. The warranty shall be issued in accordance with FAR 52.246‐21, Warranty of
Construct.
8.11 Table of Deliverables:
Project shall be as shown in the following table.
TABLE OF DELIVERABLES
Document Title
E le ct ro ni c
H ar d C op y
Delivery Date
Pricing Schedule 1 1 With bid documents
Kick-Off Meeting Within 7 calendar days after award
Meeting Minutes 1 0 2 calendar days after each meeting
Progress Schedule (AF 3064 or approved equivalent)
1 0 At the Kick-Off Meeting. Updated form shall be submitted with each
AF 3064
Contractor Badge Application (if required) 1 0 Within 14 days after award
Work Clearance Request (AF Form 103A) 1 0 10 days prior to start of work
HAZMAT Forms 81 and 82 1 0 10 days prior to start of work
Regulatory Agency Permit or Exemption Documentation
1 0 10 days prior to start of work
Progress Report (AF 3065 or approved equivalent)
1 0 Once a week
35% Design Submittal per Section 8.6.3 1 0 30 calendar days after NTP
Government Review Period GOV review comments provided within 10 calendar days after 35% design submittal
Contractor Response to Review Comments 1 0 5 calendar days after GOV review comment receipt
95% Design Submittal per Section 8.6.4 1 0 65 calendar days after NTP
Government Review Period GOV review comments provided within 10 calendar days after 95% design submittal
Contractor Response to Review Comments 1 0 5 calendar days after GOV review comment receipt
95% Design Review Meeting Within 5 calendar days after contractor response to review comments
100% Design Submittal per Section 8.6.5 1 0 90 days after NTP
Material Approval (AF Form 3000) 1 0 Minimum 7 days prior to Order Date
Production or Delivery Problem Report 1 0 Same day of crisis
Construction Material Testing Reports 1 0 As available
Welding/Burn Permit 1 0 Prior to commencing work
Draft DD1354 1 0 30 days after NTP
Pre-Final Inspection Report 1 0 3 days after Pre-Final Inspection
HAZMAT Form 83 1 0 Prior to Final Inspection
Final DD1354 1 0 Final Inspection
Final Inspection Report 1 0 5 days after Final Inspection
As-Built Construction Documents 1 1 7 days after Final Inspection
9.0 Contractor’s Quality Control
9.1 Quality Control:
The Contractor is responsible for quality control and shall establish and maintain an effective quality control system in compliance with FAR Clause 52.246‐12, Inspection of Construction. The quality control system shall consist of plans, procedures, and organization necessary to manage all delivery orders to produce end products which comply with the contract requirements. The system shall cover all construction operations, both on‐site and off‐site, and shall be keyed to the proposed construction sequence. The Government will hold the project manager responsible for the quality of work on the job and is subject to removal by the CO for non‐compliance with quality requirements specified in the contract.
9.2 Field Measurements:
The Contractor shall be required to make his own field investigations to verify dimensions and other information shown on Government furnished reference drawings and final contract documents.
10.0 Inspection and Acceptance
10.1 Provisions:
Government inspections and final acceptance shall be scheduled by the Contractor as the work is completed with the following additional provisions;
a. The Contactor shall give the Government a minimum of three (3) working days’ notice for all requested inspections.
b. The Contractor shall make sure that the work is ready for all inspections. The presence of an unreasonable number of deficiencies, as determined by the COR, may cause the inspection to be rescheduled.
c. The Contractor will be given certificate of acceptance by the COR for each successfully completed step of the work. The certificate will be signed by the COR and shall be initialed and dated by the Contractor’s approved representative. One copy of the certificate will be given to the Contractor.
d. Contractor shall complete a 325 CES approved Contractor Daily Report form and submit to COR by 1000 hours the next day after work is performed and inspected by the Construction Quality
Control (CQC) Representative.
11.0 Deteriorated Construction and Finish
11.1 Authority:
The COR will be the governing authority in determining if existing construction and finishes are deteriorated and require repair and/or replacement.
12.0 Water Conservation
12.1 Water Conservation:
Conserve water to the greatest extent possible.
12.2 Restrictions:
If Tyndall AFB implements water usage restrictions, the Contractor is required to comply with these restrictions, at no additional cost to the Government. In the event the Contractor cannot comply with water usage restrictions and still meets other contract requirements (particularly when installing sod or hydro‐mulching), then he can request permission from the CO for relief from the restrictions.
12.3 Waivers:
Submit request for waivers to water conservation restrictions in writing. The CO will consider such cases on an individual basis and grant waivers only in extreme cases. Submit detailed requests with appropriate manufacturer’s/supplier’s data to show unavoidable noncompliance with the water usage restrictions. In the event a restriction is conditionally waived, use only the minimum amount of water necessary to comply with contract requirements.
13.0 Contractor Storage/Staging Area
13.1 Operations and Storage Approval:
Notwithstanding Contract Clause, FAR 52.236‐10, Operations and Storage Areas, subject to approval by the CO and in turn, availability and need, a storage/staging area shall be provided at the subject project site.
13.2 Storage Area Clean Up:
At work completion, clean the storage area. This area must be free of any materials, trash or debris before receipt of final payment. Existing fencing shall remain Government property.
14.0 Contract Administration/Points of Contact
14.1 Contracting Officer Authority:
CO, the term used herein, does not include any representative not acting within the scope of his/her authority. Notwithstanding any of the provisions of this contract, the CO shall be the only individual authorized to in any way amend or modify the terms of the contract.
14.2 Contracting Officer:
The CO will be assigned before contract award.
325 CONS/LGCC
540 Mississippi Ave
Bldg. 36270
Tyndall AFB, FL 32403
325CONS.construction@us.af.mil
14.3 Contracting Officer’s Representative (COR):
Primary: TBD, Alternative: Macario Garcia
14.4 Technical Representative:
325 CES/CEPMS is designated as the technical representative to ensure progression, workmanship, and inspection of materials for work being performed under this contract. This clause in no way authorizes anyone other than the CO to commit the Government to changes in the terms and conditions of the contract.
14.5 Field Changes:
The Contractor and the Government may agree to perform a no cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated items. All field changes must be approved by the CO prior to execution.