Solicitation Amendment FA480324R00400006 SF 30.pdf
PDF 1 MB Posted
- Solicitation number
- FA480324R0040
About this file
This is Standard Form 30 (Amendment of Solicitation/Modification of Contract) that modifies the solicitation for Shaw AFB Multi Building Demolition and Abatement project. The amendment makes several key changes: adds B202 Locomotive Barn and B115 Maintenance Hangar attachments, includes Version 2 of Questions and Answers, adds a revised Statement of Work dated December 11, 2024, adds updated B1724 sketch, and includes Version 2 of the site visit sign-in sheet and base map.
The amendment modifies the period of performance for all CLINs to February 6, 2025 through September 4, 2025 (previously September 16, 2024 through April 14, 2025). The evaluation factors remain technical capability, price, and past performance (CPARS), with technical and past performance combined being more important than price. Technical proposals are limited to 10 pages and must include a narrative describing the approach to demolition and site services for 11 specified facilities, along with assumptions, risks, constraints, and a Gantt chart showing the work sequence. Proposals will receive an acceptable/unacceptable rating based on this technical submission.
View the file
Other files
Show 40 more
Latest 50 of 55 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The purpose of this amendment is to:Block 14 (Description of Amendment/Modification):
1. Add B202 Locomotive Barn and B115 Maintenance Hangar attachment.
2. Add Version 2 of Questions and Answers.
3. Add revised SOW dated 2024-12-11.
4. Add B1724 updated sketch.
5. Add Version 2 Site visit sign in sheet and the base map.
Note: All other terms and conditions remain unchanged.
Deliveries or Performance
The delivery information for the following CLIN(s) / SLIN(s) / ELIN(s) were added:
INFORMATION VALUE
Period of Performance 06 Feb 2025 to 04 Sep 2025
INFORMATION VALUE
Period of Performance 06 Feb 2025 to 04 Sep 2025
INFORMATION VALUE
Period of Performance 06 Feb 2025 to 04 Sep 2025
INFORMATION VALUE
Period of Performance 06 Feb 2025 to 04 Sep 2025
INFORMATION VALUE
Period of Performance 06 Feb 2025 to 04 Sep 2025
The delivery information for the following CLIN(s) / SLIN(s) / ELIN(s) were modified:
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
FA480324R00400006
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
INFORMATION FROM TO
Period of Performance 16 Sep 2024 to 14 Apr 2025 06 Feb 2025 to 04 Sep 2025
List of Attachments
The following attachments were added:
01 SOW VLSB 23-0010 Demo Theater and Others 2024-12-11 B1724 2024-12-11 Base Map Version 2 - Site Visit sign in - Project Multi-Building Demo Version 2 -Questions and Answers
The following attachments were modified:
Version 1 - Questions and Answers - 26 Aug 24
INFORMATION FROM TO
AttachmentURL 62759771 63034032
The following attachments were deleted:
01 SOW VLSB 23-0010 Demo Theater and Others 2024-11-05 B1724
Miscellaneous text in this section has been modified to:
1. Statement of Work (11 December 2024)
2. Wage Determinations
3. As-builts (FOR BUILDING LAYOUT ONLY)
4. Asbestos Survey
5. Q&A
Evaluation Factors for Award
Miscellaneous text in this section has been modified to:
52.212-2 FAR Provision Evaluation-- and (Nov 2021)Commercial Products Commercial Services
(a) The Government will award a contract resulting from this to the responsible whose conforming to the will be most solicitation offeror offer solicitation advantageous to the Government, price and other factors considered. The following factors be used to evaluate : shall offers
(i) technical capability;
(ii) price;
(iii) past performance (CPARS).
Technical and , when combined, are past performance considered to be more important when compared to price.
(b) Options. The Government will evaluate for award (Contractors please note: Options are not applicable for this acquisition) offers purposes by adding the total price for all to the total price for the basic requirement. The Government determine that an is unacceptable if the options may offer prices are significantly unbalanced. Evaluation of not obligate the Government to exercise the (s).option options shall option
(c) A written notice of award or acceptance of an , mailed or otherwise furnished to the successful within the time for acceptance specified in the , offer offeror offer result in a binding contract without further action by either party. Before the 's specified expiration time, the Government accept an (or part of anshall offer may offer
), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.offer
(End of provision)
(52.212-2 ADDENDUM) Evaluation Process:
Step 1: Evaluate all proposals for responsiveness.
Step 2: Sort all timely proposals from lowest to highest based upon offeror's Total Evaluated Price (TEP).
Step 3: Evaluate all proposals based on CPARS.
Step 4: The technical capability of each offeror will be evaluated based on the submittal of a technical narrative, and offeror's ability to meet technical requirements within the specified timeline. Each offeror's technical narrative ( ) will receive a rating ( ) based on the submission no more than 10 pages acceptable/unacceptable of a written, technical proposal describing the offeror's approach to meeting the technical requirements of the demolition and site services IAW SOW dated 11
December 2024, for the following facilities:
B1413 Base Theater
B1047 Aerospace Physiology
B115 Maintenance Hangar
B5004 Palmetto Heights Gate House
B202 Locomotive Barn
B1102 Picnic Shelter
B5237 Slab and Sign
B1724 Mobile Storage Bldg and Compressor Cover
B396 Auditorium
B1908 Hazardous Waste Cover
B212 Pavilion
The narrative must include assumptions, risks, and constraints. The narrative must also provide sufficient information to adequately support a submittal of a Gantt Chart, including market conditions (i.e. supply chain delays, labor shortages, if applicable). The chart will not count towards the narrative maximum and must outline all 10-page major work elements showing a logical sequence of events, complete services IAW the SOW and be realistic to the offeror's TEP. Narratives that include executive summaries, and/or vague or general statements about company capabilities will receive a rating of unacceptable.
Step 5: The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government.
| SUMMARY OF CHANGES |
| Deliveries or Performance |
| List of Attachments |
| Evaluation Factors for Award |
| IDCode: J |
| Page: 1 |
| Pages: 5 |
| AmendNo: 0006 |
| EffDate: 11 Dec 2024 |
| ReqNo: |
| ProjNo: |
| IssCode: FA4803 |
| AdmCode: |
| IssuedBy: FA4803 20 CONS LGCA |
321 CULLEN ST BLDG 216, CP 803 895 5403
SHAW AFB, SC 29152-5125
UNITED STATES
Jeesenia Nauta Criollo, Email: jeesenia.nauta_criollo@us.af.mil Telephone: 965-5623 AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: FA480324R0040 |
| SolDate: 07 Aug 2024 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: See Section G - Contract Administration Data |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: See Schedule |
| ContNameTitle: |
| CoNameTitle: Cesar Tapia-Caballero, CO, USAF |
| ContDate: |
| CODate: 11 Dec 2024 |
File details come from the government source that posted it. Updated .