SABER_10_May_Attachment_2_Demonstration_Project_SOW.doc
DOC document 4 MB Posted
- Attached to
- Simplified Acquisition Base Engineering Requirement (SABER) Federal contract opportunity
- Solicitation number
- FA4801-12-R-0005
About this file
Demo Project SOW
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
Base Project Number:
KWRD 13-0050
REPAIR F-16 ELEC/HYDRAULIC FAC, BLDG 883
AETC F-16 Beddown Holloman AFB 10 May 2013 PART 1 – project data:
TITLE: RPR F-16 ELECTRIC, CONSTRUCT HYDRO FACILITY, B883
LOCATION: Building 883, HAFB
PROJECT #KWRD 13-0050
PART 2 – Description of Work
The Contractor shall provide all labor, material, supervision, supplies, and equipment necessary to design, renovate, and repair building 830 in order to convert it from sheet metal facility into an Electro-Environmental (E&E), Hydraulics (Hydro) and Liquid Oxygen (LOX) cart maintenance & testing sections. All work on this contract shall be completed 180 calendar days from NTP.
Electrical Requirements
2.1 Disconnect existing 208/120V electrical service entrance to building from transformer bank.
2.2 Upgrade overhead primary electrical feeders and associate electrical connections to underground lines. Contractor shall furnish all labor, materials, supplies and supervision required, but not limited to replace overhead electrical feeder lines with underground primary and secondary electrical lines as indicated on location site image (see Figure 1), including replacing the overhead electrical transformers with a 750kVA, 480/277V pad mounted transformer and installing a pad mounted junction box in the location of the demolished last pole. Refer to Figure 1.
2.3 Install a dry-type, floor mounted, 3-phase, 480V Primary, 120/208V Secondary transformer and connect to existing 120/208V Panelboard. Determine appropriate size of transformer for existing panelboard.
2.4 Install a 600A MCB 480/277V Panelboard and associated Circuit Breakers, feeders, and outlets necessary to feed new shop equipment. See Addendum 1.
2.5 Connect dry-type transformer to new 480V Panelboard and determine size of associated conductors, conduit, and circuit breakers.
2.6 Install additional light fixtures to match existing fixtures in Hydraulics Shop to obtain adequate lighting levels as outlined in UFC 3-530-01 Interior & Exterior Lighting.
2.7 Install Class 1/Div 1 Explosion Proof items in the new Liquid Oxygen (LOX) shop and connect to nearest available and appropriate panelboard:
2.7.1 8 EA new fluorescent light fixtures.
2.7.2 7 EA Heavy Duty 120V 20A Electrical Outlets.
2.7.3 1 EA Heavy Duty 240V Electrical Outlet.
2.7.4 2 EA Light Switches.
2.7.5 1 EA HVAC electronic control.
2.7.6 1 EA Heat Detector and connect to existing Fire Alarm system.
2.7.7 1 EA Grounding Bar.
2.8 Install 4 EA 240V Electrical Outlets and connect to nearest available and appropriate panelboard in the Battery Shop.
2.9 Install 4 Grounding Points in the Building Exterior. (Location TBD) Structural/Plumbing Requirements
Hydro Shop
2.10 Construct approximately 40’ by 22’ high wall bisecting the main sheetmetal shop area. This wall will include a 6’x 7’ double door. Wall will be framed, covered & in a fashion to complement existing walls.
2.10 Install drainage line to capture and route cooling water from test equipment. Drainage line shall be embedded within the concrete floor. Specific location will be determined the end-user.
2.11 Install water supply line for testing equipment. Again, exact location will be determined by the end-user.
Exterior Hydro Shop
2.12
Install 4’ by 6’- 4” fiber reinforced concrete; includes 4” excavation, 4” base course compacted to
95%, subgrade prep, forwork, placement, tooled joints, finishing, texturing, curing and testing.
2.13 Install 8’x6’x7’ H awning directly over concrete pad.
Interior LOX Shop 2.14 Strip (aprox 550 sft) of epoxy from the floor.
2.15 Install 6’x7’ double door. (Refer to drawings for exact location) Battery Shop
2.16 Plumb and install emergency eyewash station.
Exterior LOX Shop
2.17 Install 8” thick; 37’ long by 14’ wide Portland cement concrete pavement 650 psi flexural strength includes; formwork, placement, finishing, texturing, curing and testing. (Refer to drawing for exact location) 2.17 Cover new concrete pad with 30’long by 20’ wide awning. (Refer to drawings for exact location)
2.18 Install 6’ wide by 37’ long fiber reinforced concrete drive with driveway approach/slab on grade
4000 psi Compressive strength includes;4” excavation, 4” Base Course compacted to 95%, formwork, subgrade prep, tooled joints, placement, finishing, texturing, curing and testing.
2.19 Install (aprox) 56 linear feet of fencing, 8’ high with a 7’ gate. Place fence along the perimeter of new LOX cart yard with the gate located at the newly place concrete driveway.
General Notes: Contractor shall be responsible to conduct site visit(s) in order to become familiar with the existing conditions, analyze the electrical distribution system, its components, take the necessary equipment readings, and run any necessary sizing calculations. Contractor shall follow all applicable building, plumbing, and electrical codes, federal and state regulations. Note: All work shall be performed IAW HAFB Design Compatibility Standards, applicable Unified Facility Criteria (UFC), federal, state, and local regulations and standards governing this type of work. In the event of conflicts between standards, UFCs will take precedence over any other code or standard. Contractor shall record where the “as needed” work was performed and immediately furnish this information to the government Contracting Officer Representative (COR) and/or Project Engineer.
· All new underground electrical lines shall be copper.
· Removed pole mounted transformers shall be turned in to the 49 CES Electric Shop.
· New pad mounted transformers shall have copper windings.
· Meet any other requirements in UFC 3-550-01 (Exterior Electrical Power Distribution), UFC 3-530-01 Interior & Exterior Lighting, UFC 3-520-01 (Interior Electrical Systems) not specified in this SOW. A copy of each UFC can be found on line using the following link: http://www.wbdg.org/ccb/browse_cat.php?o=29&c=4
PART 3: APPLICABLE DOCUMENTS
The Contractor shall identify and comply with all applicable federal, state, and local statutes; Air Force/Military, manuals, handbooks, regulations, guidance, and policy letters; Status of Forces Agreements (SOFA); Executive Orders (Eos); HAFB Design Compatibility Standards, Air Combat Command Architectural and Interior Design Standards; American Petroleum Institute (API) Codes; National Association of Corrosions Engineers (NACE); National Fire Protection (NFPA); Steel Structures and Painting Counsel (SSPC); National Electrical Code (NEC); Unified Facilities Criteria (UFC); American Society of Heating, Refrigerating, and Air-Conditioning Engineers, ASHRAE, Federal Standard 795; International Energy Conservation Code (IECC); and International Building Code (IBC), including changes and amendments in effect on the date of issuance of this TO. Mass Notification system and devices shall be installed according to UFC 3-600-1, NFPA 72, National Fire Alarm Code & NFPA 70, National Electric Code and Life Safety Code 101.It is the Contractor’s responsibility to identify and comply with applicable requirements. In the event of conflicting criteria, the contractor shall notify the contracting officer for guidance. Additional customer specific documents may be specified above.
3.0
DESIGN REQUIREMENTS
This is a task order to SABER contract and as such the Contractor shall be responsible for 35% design.
Figure 1. Location site with overhead electrical lines shown.
ADDENDUM 1
Section of Overhead line to be replaced with Underground electrical lines.
Section of Overhead line to be replaced with Underground electrical lines.
Statement of Work/KWRD 13-0050
RPR F-16 Elec/Hydro Fac, Bldg 883
File details come from the government source that posted it. Updated .