Attached are the SABER Questions Answers Round 2 - Post-Site Visit.

View the file

Other files for this federal contract opportunity

Other files attached to Simplified Acquisition Base Engineering Requirement (SABER), newest first.
File Type Posted
FA4801-12-R-0005_Amendment.pdf PDF
7._AF_IMT_3064_Contract_Progress_Schedule.pdf PDF
2._Drawing_Sheets_ANSI_D_Cover.pdf PDF
5._Utilities_883_Area.pdf PDF
6._AF_Form_3052_template_for_SABER.xlsx XLSX spreadsheet
4._HAFB_Building_883-As-Builts.pdf PDF
3._BLDG_883_ANSI_D_Sheet.pdf PDF
4._Task_Orders_ _Amounts.xlsx XLSX spreadsheet
1._Solicitation_Amendment_FA4801-12-R-0005-0001.doc DOC document
3._Financial_Information_Request.docx DOCX document
2._SABER_Q A_Round_1_-_Pre-Site_Visit.xlsx XLSX spreadsheet
HAFB_010.docx DOCX document
ATTCH_4_Heavy_General_Decision___NM130008.doc DOC document
SABER_2_May_-_Attachment_1_SOW.doc DOC document
SABER_10_May_Attachment_2_Demonstration_Project_SOW.doc DOC document
Consent_Ltr.doc DOC document
ATTCH_6_Residential_General_Decision_NM_130005.doc DOC document
Client_Authorization_Ltr.doc DOC document
ATTCH_7_Base_Access.pdf PDF
ATTCH_5_Highway_General_Decision_NM_130050.doc DOC document
AF66.xlsx XLSX spreadsheet
ATTCH_8_HAFB_VAR-1.doc DOC document
Solicitation_FA4801-12-R-0005_-_Holloman_SABER.doc DOC document
ATTCH_9_HAFB_Design_Compatibility_Standards.doc DOC document
ATTCH_3_Building_General_Decision___NM130032.doc DOC document
Past_Performance_Information_Sheet_PPIS.docx DOCX document
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question&Answer2

CategoryQuestionAnswer
Demonstration Project - ConcretePer SOW, 2.18 “Install 6’ wide by 37’ long fiber reinforced concrete driveway approach/slab”. What is the minimum depth of concrete required for this driveway?4000 psi portland cement concrete, 20-30% fly ash, type 5 portland, steel reinforced, 6" minimum depth.
Demonstration Project - ConcreteFor the new concrete driveway access from the existing road, does it require to demo the existing sidewalk/curb & gutter and install new ADA accessible sidewalk ramp?Yes.
Demonstration Project - ConcreteIs all existing sidewalk around the perimeter of Bldg 883 to remain?Yes.
Demonstration Project - LOXAre all of the items in paragraph 2.8 installed in the new Liquid Oxygen (LOX) shop?Yes.
Demonstration Project - GFEWhere is the equipment listed on pages 7, 8, and 9 to be installed in the facility. Will this be Government Furnished and Contractor Installed or installed by the Government after the project is complete?This will be government furnished, contractor installed. Exact location of equipment will be determined by end-users.
Demonstration Project - LOXReference paragraph 2.7 for the Class 1/Div 1 explosion proof items are required in the new LOX shop. Is there any existing HVAC equipment which will need to be modified/replaced to meet this requirement (in addition to the HVAC electronic control mentioned in 2.8.5)?No.
Demonstration Project - LOXReference paragraph 2.8.5 for the HVAC electronic control is called for in the new LOX shop. Can you provide the make/model of the existing HVAC electronic control and information on what it is controlling.Contractor to verify.
Demonstration Project - Hydro ShopReference Hydro Shop paragraph 2.10: What size drainage line? Does the drainage water get sent to the sanitary line or does it need to be treated, for instance, with acid neutralization or other treatment?Install standard drainage line in accordance with local, state & federal rules, regulations and standards. Drainage water will not need treatment.
Demonstration Project - Hydro ShopReference Hydro Shop paragraph 2.11: What capacity water supply line is required (GPM)? Is backflow prevention required? Is there an existing water supply the mechanical room that can be used?Refer to page 8 of 12 in the SOW. No backflow is required and yes an existing water source is available.
Demonstration Project - Hydro ShopReference paragraph 2.16: Are emergency eyewash stations or emergency eyewash/showers required? This paragraph says emergency eyewash but the plan on p. 11 calls out eyewash/showers. Does the emergency equipment need to meet ADA?A shower is no longer required, only the eyewash station. No ADA required.
Demonstration Project - AirFor the Hydro Shop Test Stand, does the Contractor extend the shop air piping from the existing air compressor to the test stand and connect? What is the required flow?Yes extend air line to equipment location. Refer to page 8 of 12 in the SOW.
Demonstration Project - Hydro ShopFor the Hydro Shop Test Stand, the requirement is for 80 degree water. Does the 15-20 GPM water supply need to be tempered – an instantaneous water heater?No.
Demonstration Project - Hydro ShopFor the Hydro Shop Test Stand, Where is this test stand equipment located on the plan view?It will be located on the west wall of the Hydro Shop.
Demonstration Project - AirDoes the Contractor extend the shop air piping from the existing air compressor and connect? What is the required flow?See question 12
Demonstration Project - HVACIs there existing HVAC equipment that will provide the cooling air required by the load bank (1000 cfm) and drive motor (950 cfm)? Or does the contractor need to prove new HVAC equipment? What conditions of air are required (temp)?No, the contractor is not installing any equipment, only providing the infrastructure for the end users to install the equipment.
Demonstration Project - ElectricalIs the “pad mounted junction box” called out in paragraph 2.2 to be a 15KV, 3-way, sectionalizing switch?Yes.
Demonstration Project - LightingAre lights or receptacles required at the Exterior LOX Shop?No.
Demonstration Project - AwningsThe noted 2 awnings for the Hydro Shop and the exterior LOX Shop need to be clarified. Our design team has proceeded with a tube steel frame design with metal roof system with gutter and down spout in our 35% design. Can we proceed with this or is it the Governments intend to use a conventional canvas type awning at these two locations.There is no requirement for an awning in the Hydro Shop, only outside of the LOX Shop. Awning shall be designed and built in accordance to the Holloman AFB Design Compatibility Standards, all local, state & federal rules, regulations and standards.
Demonstration Project - ElectricalAre the electrical items noted in 2.8 of the SOW, are they required inside the LOX shop or will be required outside below the new patio cover?Inside the LOX Shop
Demonstration Project - LOXInside the LOX shop or Clean Room, does the contractor remove all light fixtures, outlets and switches?Yes.
Demonstration Project - Eye WashI need clarification of the SOW with item no. 2.16. Item 2.16 only identifies one eye was station in the Battery Shop. Is the battery shop the two story offices on the South West corner of the metal bldg.. no. 883? If this is the case, then the new eye wash will be inside the lower floor of the Grnd. Flr. Battery MX. This will be one plumbing fixture inside this office only. The other eye wash station by the new dividing wall is existing. Thus only one eye was station to be roughed in. not two.Correct.
Demonstration Project - AwningsThe Demonstration Project SOW Item 2.12 calls for installation of a 4’ x 6’ concrete slab with awning. This slab and awning is depicted at the top of SOW drawing page 11 of 12 which has the label of “Pwr Panel Pad”. Question: Please clarify why this is called a “Pwr Panel Pad “ . Is there meaning behind that label that is not clear ?This is where the "load bank" will be placed. The contractor is not installing any equipment, only providing the infrastructure for the end users to install the equipment.
SolicitationThe SF 1442 states that we should submit an original and 2 copies, but as you go thru the RFP it states that Volumes: 1 thru 3 you should submit 2 hard copies and 1 cd – please clarify.Please submit one original and two hard copies for a total of three physical copies, and one electronic copy on a disk.
SolicitationOn the bank reference what is HAFB wanting as far as a Financial Information Request? – This is asked for on page 76 of 90Please see Financial_Information_Request.docx provided on 4 June. This helps the Government verify the contractor's financial capability. As stated in Section M - Evaluation Factors for Award, 4.b.i. the proposal must demonstrate access to cash and/or lines of credit totaling at least a minimum of $100,000.00.
NMGRTWe are unable to locate the following contract clause we have seen in other solicitations from Holloman AFB in regards to NMGRT. The RFP states include taxes, which implies NMGRT, but will the following clause be added to the RFP and NMGRT cost be included in the coefficient?HAFB 007 - NEW MEXICO GROSS RECEIPTS TAX (NMGRT) Holloman AFB Special Instructions (May 2012) has been posted as the attachment provided on 15 May and named: Atch 10 Holloman AFB Local Procedures.docx. This tax should be included in the coefficient.
Due DateWould the Government consider postponing the due date to June 28, 2013?Yes, it is under consideration, however, please do not plan on it until you see a formal amendment posted to FBO.
CoefficientDoes the Government desire a written description and/or mathematical equation explanation of methodology and development of how the contractor derived their coefficient? If yes, does the Government have a particular format or is format up to the individual contractor. Also, what section of the proposal should this be provided in?No, the Contractor is not required to provide a description or mathematical equation to explain how the coefficient was derived.
Demonstration Project - QuantitiesDemonstration project in various sections of the SOW, the Government has provided quantities or dimensions. Please advise if we are to utilize Government quantities or Contractor's quantities based on design/field measurements regardless if they vary +/- from Governments.Utilize quanities based on design/field measurments regardless of variance.
Demonstration Project - Hydro ShopDemonstration project Hydro Shop item 2.10 states; Install drainage line to capture and rout cooling water from test equipment. Drainage line shall be embedded with the concrete floor. Specific location will be determined by the end-user. 1.) No determination was made during site visit, please provide location of drains. 2.) Does the drain line tie into the manhole on the east side of the building? 3.) When replacing the concrete for the floor drains do we need to use rebar dowels? 4.) Is capillary fill required under the concrete patch?1.) The drain is located on the west side of the hydro shop. The Contractor is to install a drain clear across to the east side and out to the manhole; 2.) Yes it ties into the manhole on east side of bldg; 3.) No; 4.) No
Demonstration Project - Hydro ShopDemonstration project Hydro Shop item 2.11 states; Construct approximately 40'X22' high wall bisecting the main sheet metal shop area. This wall will include a 6'X7' double door. Wall will be framed, covered & in a fashion to complement existing walls. 1.) Does wall need craft faced fiberglass batt insulation for sound continuation? If so, what R-Value R-11, R-133, R-15, or R-19? 2.) Does the Government desire this wall to be 4", 6", or 8" thick steel or wood studs? 3.) Does customer plan on attaching any equipment/items to the wall that will impact our design for load rating/bracing? 4.) Does the Government desire this wall to be framed at 12", 16", or 24" on center stud spacing? 5.) Does the Government desire a fire rating requirement for this wall? If so, what hour rating?Construct wall in accordance to Holloman AFB Design Compatibility Standards, local, state & federal rules, regulations and standards. Wall will be R-15 insulated; stud spacing, nominal lumber/metal stud size will be determined by contractor. Fire rating will be in accordance to standards.
Demonstration Project - Hydro ShopDemonstration project Exterior Hydro Shop item 2.19 states; Install (approx) 56 linear feet of fencing, 8' high with a 7' gate. Place fence along the perimeter of new LOX cart yard with the gate located at the newly place concrete driveway. 1.) What guage does Government desire fence to be 9ga. or 11.5ga? 2.) Does fence need barb wire? If so, how many strands - 2 or 3? 3.) Does fence need razor wire?9 ga, no barb or razaor wire.
Demonstration Project7. SOW Seed Project KWRD 13-0050
Demonstration Projecta. Question: Can the government make available As-Built drawings for both the site and Building 883 in CAD electronic files, hard copy or both ?Yes.
Demonstration Projectb. Question: Can the government make available a base standard border and title block in CAD for use in preparing the Demonstration Project Design drawings?Yes.
Demonstration Projectc. Clarification: Item 2.3 indicates installing a new floor mount transformer to feed the existing panel board. Please provide location of the existing panelboard and desired location of the new transformer.For the Contractor to propose within the mech room.
Demonstration Projectd. Clarification: Item 2.4 indicates installing a new panel board. Please provide approximate desired location of new panelboard.Contractor to determine location closest to the location being served.
Demonstration Projecte. Clarification: Item 2.4 indicates providing power to new shop equipment. Addendum 1 seems to indicate 3 pieces of new equipment. Please provide approximate desired location of new equipment.Equipment location will be determined by end-user.
Demonstration Projectf. Clarification: Item 2.6 indicates adding light fixtures to match the existing fixtures in the “Hydraulics Shop”. Are we correct that area is limited to the areas designated as Maintenance Bay/ Test Stand Bay on the provided drawings?Yes.
Demonstration Project - LOXg. Clarification: Item 2.7 indicates installing new Explosion Proof items in the new Liquid Oxygen (LOX) shop. Is the LOX shop indicated on the provided drawing (pg 12 of 12) as the “LOX Maintenance Clean Room? Are we correct that those items to be installed are listed under Item 2.8? Please provide approximate desired location of the items to be installed. Is the ground bar listed in Item 2.8.7 the same as the ground “strip” indicated on the provided drawing (pg 12 of 12).Yes, they are listed under 2.8. Remove and replace.
Demonstration Projecth. Clarification: Item 2.9 indicates installing outlets in the Battery Shop. We assume the area indicated as “Test Stand Bay” is considered the “Battery Shop”. Please provide approximate desired location of outlets.The Battery Shop is located within the Maintenance area/"Ground Floor Battery Mx. Located along the west wall.
Demonstration Projecti. Clarification: Item 2.11 indicates installing double doors in the new wall. Please indicate the desired hardware for the doors.Match existing hardware within the facility.
Demonstration Projectj. Clarification: Item 2.10 indicates installing a drainage line to the test equipment. Please indicate the desired end point of the drainage line(ie sanitary sewer).Tie new drain line to the nearest sanitary sewer line .
Demonstration Projectk. Clarification: Item 2.14 indicates stripping epoxy flooring. Does the flooring get replaced ?No, just strip the epoxy coating from the floor.
Demonstration Projectl. Clarification: Item 2.15 indicates installing double doors in the existing wall. Please indicate the desired hardware for the doors.Match existing hardware within the facility.
Demonstration Project1. Is there HVAC work associated with this project?No.
Demonstration Project2. Test Stand Load Bank and Drive Motor show cooling air flow rates in Table 1-1 on page 9 of 12 in Statement of Work (SOW). Is this an external condensing unit? If not, is the air to be provided by a cooling source and routed to these pieces? Or?N/A. The contractor is not installing any equipment, only providing the infrastructure for the end users to install the equipment.
Demonstration Project3. Is there work for the clean room? It exists already?Refer to sections 2.7, 2.8, 2.14 & 2.15 of the SOW
Demonstration Project4. Is there work associated with the battery charging area? Battery exhaust with gas sensors?Yes, install outlets and eye wash only.
Demonstration Project5. Is the A/C unit for the Comm. Rm. New?There are no requirements for the Comm Room.
Demonstration Project6. Are the HVAC units shown in the Maintenance Bay and Test Stand Bay new or existing?Existing.
Demonstration ProjectThe Seed Project SOW Items 2.8.3 and 2.9 call for installing 240V electrical outlets.
Demonstration ProjectClarification: What is the desired amp rating for those outlets?30 amps.
Demonstration ProjectClarification: Is there specific NEMA configuration required for these outlets?Explosion Proof.
Demonstration Project2.9 Location of (4) 240 electrical outlets?In the battery shop.
Demonstration Project2.11 Are metal studs and drywall approved materials for high wall. If so what size and gage?Contractor to determine correct size and guage.
Demonstration Project2.12 What PSI strength concrete is required here?4,000 psi.
Demonstration Project2.13 John Seamon had mentioned he would prefer light under the 8' x 6' x 7' H awning?N/A - no lights required.
Demonstration ProjectWill a French drain suffice or do we need to tie into the existing drain line? Location of eye wash?No french drains, tie into existing sanitary sewer lines.
Demonstration Project2.17 Will light be requested under the 30' x 20' awning? Is this awning 7' high as well?8' high ceiling.
Demonstration Project2.19 Does 8' high fence include barb wire or is that the height of the fabric?No barb wire required, just 8' of fabric.
Demonstration Project - Plumbing1. Does the eyewash station need tepid water supply of cold water only?cold water.
Demonstration Project - Plumbing2. Is there an existing air compressor to provide shop air per test equipment requirements?Yes.
Demonstration Project - Electrical1. Looking at Figure 1"Location site with overhead electrical lines shown," it appears that the existing overhead medium voltage line continues to another building. Should we plan on a Loop Feed Pad Mount Transformer?Yes.
Demonstration Project - Electrical2. Is the compressor shown on page 12 of 12 existing?Yes.
Demonstration Project - Electrical3. Is the swamp cooler shown on page 12 of 12 existing?Yes.
Demonstration Project - Electrical4. Where are the existing distribution panels located?Inside building on the northeast wall of the Hydro Shop.
Demonstration Project - Electrical5. What is the voltage of the existing panels?208/120V.
Demonstration Project - Electrical6. What is the amperage of the existing panels?400A Max, 300A MCB (MDP).
Demonstration Project - Electrical7. What size is the existing 208/120 volt panel that we are providing the new dry type transformer for?400A Max, 300A MCB.
Demonstration Project - Electrical8. Can you provide us with information on the existing light fixtures in the Hydraulics Shop so that we can match them for this project?Assume MH-HID.
Demonstration Project - Electrical9. Are there record drawings of the building available for our use?Yes - see attached.
Demonstration Project - Electrical10. Are there special mechanical and electrical requirements for the clean room?No mechanical, refer to SOW for electrical requirements.
Question SubmittalPlease confirm we have 15 days prior to the to the solicitation closing date to submit questions.You may submit questions up until that time. However, it is the Contracting Officer's discretion whether a question willl be answered. For instance, if a question has already been answered, or if the information is clearly available in the solicitation, then it need not be answered.
Past PerformancePlease confirm past performance of teaming partners or subcontractors will not be considered.Correct - Past Performance of teaming partners and/or subcontractors will not be considered, but Joint Venture partner Past Performance will be considered.
Drafting/SurveyorPlease clarify if the table on page 86 Drafting/Surveyor is stating that you are looking for two different bodies; one drafter and one surveyor? Or one body to perform both functions?Two bodies.
Demonstration ProjectIs there 1 or 2 eyewash stations???1
Demonstration Project2.3 What size does the dry type transformer need to be?Contractor to determine.
Demonstration Project2.8.3 What amperage does the 240v outlets need to be?30 amps.
Demonstration Project2.8.5 What type of HVAC electronic controls are needed?Explosion Proof.
Demonstration Project2.8.6 Does the heat detector for the fire alarm need to be class A and B?Class B.
Demonstration Project2.9.4 What amperage does the 240v outlets need to be?30 amps.
Demonstration Project2.10 Is a counterpoise system or are ground rods needed for the grounding points in the building exterior?Ground rods are needed.
Demonstration ProjectIs there any drainage issues we need to be aware of???No.
Demonstration ProjectWill the demo project require architectural and engineering stamps???No.
Demonstration ProjectWhat does the HVAC Controller control - no heating and cooling stated in scope.HVAC
Demonstration ProjectDo you have as-builts and CAD files?Yes.
Demonstration ProjectAre there as-built or cad drawings available for this building?Yes.
Demonstration ProjectWhat does the Primary feed? Will there be any special base shut down when addressing the power, and if so which surrounding buildings?The transformer. It is the contractor's responsibility to plan and coordinate in advance with the bldg occupants & Civil Engineer squadron prior power outage.
Demonstration ProjectIs the entire liquid oxygen room Class I Div. II?Yes.
Demonstration ProjectIn the liquid oxygen room, does the venting system on the west wall get relocated or demo'd? There is possible issues with the bent and the new double door that will be installed.Venting system will be demo'd.
Demonstration ProjectThe building does not have a fire suppression system, will it be recommended to install one?No.
Demonstration ProjectWhat is the size of existing service and SCS?Define "exsting service and SVS."
Demonstration ProjectWill there be any electrical or lighting requirements at the canopy location?No.
Demonstration ProjectThe drawing doesn't show an exterior access gate in the fenced area at the canopy location. Will one be needed?Yes.
Demonstration ProjectThe design guide references lightning protection at all buildings. Will the building require lightning protection?Yes.
Site VisitAre you going to be publishing a copy of the pre proposal/ site visit attendee sign in sheet? Please advise if you have published it and I have just missed it.No. The FBO solicitation allows vendors to add/remove their information from the "interested vendors list" and to view interested vendors list.
Coefficient ContentsThe SABER RFP draws into question the exhaustive list of items within the SABER SOW that state the coefficient should cover, but there are cost items within RS Means UPB divisions 1 and 2 that should allow it to be a job cost. We believe this list creates a wild card coefficient with numerous areas of risk that are technically job cost addressed by the RS Means UPB. In future task order proposals, will we be allowed to include such costs as direct costs, and if not, how can we possibly estimate our coefficient rates without knowing what these costs will be?The exhaustive list is the result of our years of experience during which we have found that these costs are better handled through the coefficient. Offerors should use their own experience as a guide and make their best estimate as to what these costs will be and factor that into the coefficient as appropriate. These costs will not be allowed as direct costs on future projects.
Volume III CopiesWe submitted two hard copies and one electronic copy of Volume III, Past Performance on May 31st, 2013. Per the Q&As answered on June 4th, 2013 it was clarified we should submit one original and two copies. Can we submit our Copy 2 with the remainder of the proposal package on June 21, 2013 or would it be best we send It beforehand?Yes, you can submit the final copy with the remainder of the proposal package by June 21 2013.
FormattingPlease confirm all pages can be single spaced.Yes.
AmendmentReference Amendment 2, SF 30, Block 2 – The Amendment/modification number is shown as 0001. Will you be releasing an SF 30 that shows Amendment 0002?FBO is separate from our contract writing system. FBO Amendment 2 was used to post Solicitation (SF30) Amendment 0001.
Location of PrimeSolicitation, Offer, and Award Pg. 1 of 90 (A) – ‘This is an 8(a) set-aside restricted to New Mexico and El Paso, TX 8(a) concerns’: Question. Does this mean that the 8(a) ‘concern’ must have its servicing office in either Albuquerque or El Paso? As an example, would an 8(a) business or 8(a) Joint Venture ‘not’ serviced by El Paso or Albuquerque be able to set up a ‘bona-fide’ office in these regions and qualify to bid the proposal?No, and No. This acquisition is set aside for 8(a)s currently located within the stated geographical area. If any 8(a) can set up an office to bid, then what is the point of having a geographical set-aside? (Effectively, there is no geographical set-aside in such a scenario.)
EstimatePg. 87 of 90 (3) ‘Estimating Capability, - Includes a filled in AF Form 3052, Construction Cost Estimate…’ : Question. In lieu of providing a AF 3052, can the proposer or bidder use a detailed line item estimate produced from an estimating program such as e4Clicks, Pulsar, WinEst, etc.? With the Demonstration Project potentially having a very large amount of line(s) included from the RS Means Catalog – it is very arduous to attempt to break out man-hours, and production rates from individual lines. The LIE produced from a commercial estimating tool such as e4Clicks is industry standard and provides the baseline detail provided from RS Means.Yes. Offers utilizing the form 3052, or a similar contractor-provided format, will be considered. Please note the offerors need to provide enough detail and narrative explanation of estimating methods and assumptions to allow for effective government analysis, as stated in sections L and M.
Past PerformanceIt is understood from the proposal instruction that only the 8(a) concern’s past performance shall be evaluated in the event that a ‘teaming’ partnership is presented for technical evaluation - In the case of an 8(a) Joint Venture proposal between a large business mentor and a small business protégé, will the 8(a) small business need to provide adequate past performance or capability to the JV, or can the proposed JV solely rely on the past performance of the large business partner for the technical evaluation?The scenario you present would not, in and of itself, automatically result in a past performance rating of unacceptable.
Demonstration ProjectAre record drawings for the subject Building #883 available.Yes.
Demonstration ProjectWhat is the actual square footage of Building #883?See attached as-builts
Demonstration ProjectWhat is the actual height of the ceiling AFF, at its highest and lowest points in Building 83?See attached as-builts
Demonstration Project - Eye WashIs the new eyewash station required to be connected to the building drain, waste and vent system?No.
Demonstration Project - AwningsAs to means, methods and materials, do you have a preference for the new awning?Construct in accordance with the Holloman AFB Design Compatibility Standards, local, state, and federal rules, regulations and standards.
Estimate/SoftwareContained within the Solicitation Synopsis is the following verbiage; "The cost proposal will be comprised of the base costs in the Facilities Construction Cost Data by RS Means (e4clicks Project Estimator) multiplied by the contractor's coefficient." Is the 4Clicks software required to be used for the cost proposal for the demonstration project, or can the RS Means Facilities Data be used with other software, for example Sage Timberline? Further, will it be a requirement of this SABER contract to exclusively utilize 4Clicks software for the purpose of preparing proposals, or can other software be utilized. Also, if the use of 4Clicks software is a requirement of the contract, please indicate how many copies are required, if there is a requirement to supply the Government with any copies of same and if so, will CLINS be added to the proposal schedule for same?Any RS Means-based software is permitted. The SOW requires the contractor to provide 3 copies of the RS Means book to the Govt. This is part of mobilization (task order 0001) but the cost is included in the coefficient.
Demonstration Project - UtilitiesDoes the government have a survey of the existing limit of work showing the underground and/or buried utilities? If none exists, does the government require us to carry the cost for having one done?See utilities drawings.
Demonstration Project - Geotechnical InfoDoes the government have geotechnical information for the existing limit of work? If non exists, does the government require us to carry the cost for having one done?No and no.
Demonstration Project - ElectricalPlease confirm the overhead primary voltage.13.2 kV.
Demonstration Project - ElectricalPlease confirm the need for exterior lighting and power for the concrete pads. Please quantify each.N/A.
Demonstration Project - ConcretePlease confirm the finish for the exterior concrete pads.Broom finish.
Demonstration Project - PanelsThe SOW states that "Wall will be framed, covered & in a fashion to complement existing walls". The existing walls are insulated metal panels. Please confirm that metal panels are acceptable by the government.Not for an interior wall.
Demonstration Project - HVACPlease confirm that there is no HVAC or ventilation work in this project.Confirmed.
Demonstration Project - ElectricalThe MC2000 has an exterior load bank. Can the government provide guidance on where and how this load bank is to be installed?Government will install.
Demonstration Project - ElectricalThe RFP requires 750KVA pad mount, which will proved approximately 900A at 480V three phase, and is asking for a 600A, 480V panel. Out of the 600A panel there are two pieces of equipment that will draw 450A and the 600A panel is to feed a 208V transformer for the existing service. Since 80% of 600A is 480A, the two pieces of equipment essentially load the panel to capacity. We recommend that the panel should be at least 800A, not 600A in order to effectively feed a 208V transformer.Contractor to determine the correct size.
FormsI am looking for form 3052 and 3064 in the RFP or SOW… Is there somewhere that I can locate these forms easily?Please see attached forms.