Attachment 12 -AF 66.xls
XLS spreadsheet 52 KB Posted
- Attached to
- Replace Utility Well #9 Beale AFB Federal contract opportunity
- Solicitation number
- FA468624R0006
About this file
This document is a schedule of material submittals for a federal contract to replace utility well number 9 at Beale Air Force Base. The contract requires the contractor to submit design documents, plans, specifications, test results and other deliverables on specified dates ranging from notice to proceed to final project closeout. Key submittals and dates include 100% design documents due 45 days after notice to proceed, structural connection details due 45 days after notice to proceed, HVAC, fire alarm and communication layouts due 45 days after notice to proceed, demolition and asbestos plans due 7 and 45 days after notice to proceed respectively, and operation and maintenance manuals and as-built drawings due 14 and 7 days after final acceptance inspection. The related federal contract opportunity is a solicitation to design, drill, install, develop, equip, test and commission a replacement well and connect it to existing electrical, piping and communication networks at Beale Air Force Base for the Department of the Air Force Air Combat Command.
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal 1
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT NAME | SOLICITATION /CONTRACT NUMBER | |||||||||||||||||||
| 1134784 | Repair by Replace Well #9 | FA468624R0006 | ||||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | |||||||||||||||||||||
| LINE NUMBER | Note: 3 copies required per submittal. Government will retain all submittals. Provide an electronic copy for each submittal. | CERTIF. OF COMPLIANCE | SHOP DRAWINGS | COLOR SELECTION | MANUFATURUR'S RECOMMENDATION | CATALOG DATA | O&M RECOMMENDATIONS | CALCULATIONS | WARRANTY | DRAWINGS | REPORT | TEST RESULTS | REQUIRED SUBMISSION DATE | DATE TO CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | APPROVED | DISAPPROVED | CONTRACTOR SUBMITTAL | FINAL APPROVAL | |
| GENERAL | ||||||||||||||||||||||
| Project Specific Form 66 | X | NTP + 3 | ||||||||||||||||||||
| Construction Schedule | X | NTP + 7 | ||||||||||||||||||||
| TCN Schedule (electronic required, hard copy optional) | NTP + 7 | |||||||||||||||||||||
| Contractor's Health, Safety, and Environment Plan | X | NTP + 7 | ||||||||||||||||||||
| Contractor's QA/QC Plan | NTP + 7 | |||||||||||||||||||||
| Copy of Engineering License(s) of person or consultancy responsible for design | X | DESIGN | ||||||||||||||||||||
| DESIGN | ||||||||||||||||||||||
| 100% design document to be provided electronically as pdf. and (DWG optional) | X | X | X | X | NTP + 7 (100%) | |||||||||||||||||
| Roof Drain Storm Sewer Tie In | NTP+45 | |||||||||||||||||||||
| Wind Loading Diagrams for Roof | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||||
| Structural Connection Details for Shear Walls | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||||
| Structural Connection Details for Framing | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||||
| Structural Connection Details for Blast Resistant Doors & Windows | NTP+45 | PE STAMP REQ'D | ||||||||||||||||||||
| HVAC Calculations | NTP+45 | |||||||||||||||||||||
| Sprinkler Layout | NTP+45 | FPE or NICET Tech stamp req'd | ||||||||||||||||||||
| Fire Alarm Layout | NTP+45 | FPE or NICET Tech stamp req'd | ||||||||||||||||||||
| Communications Layout | X | NTP+7 | ||||||||||||||||||||
| Technical Specifications | X | NTP+15 | ||||||||||||||||||||
| DEMOLITION/ASBESTOS | ||||||||||||||||||||||
| Demolition Plan | X | X | X | NTP+7 | ||||||||||||||||||
| Asbestoes Plan | NTP+45 | |||||||||||||||||||||
| CIVIL | ||||||||||||||||||||||
| Soil Gradations for each type of soil used | Install -7 | |||||||||||||||||||||
| Moisture-Density curve for each type of soil used | Install -7 | |||||||||||||||||||||
| Nuclear Densometer Calibration | Install -7 | |||||||||||||||||||||
| Soil Compaction Test Results for Utilities, Facilities & Pavement | Install+7 | |||||||||||||||||||||
| Storm Pipe | Design+14 | |||||||||||||||||||||
| ARCHITECTURAL | ||||||||||||||||||||||
| Blast Resistant Doors and Frames | NTP+45 | |||||||||||||||||||||
| Door Hardware | NTP+45 | Hardware Schedule | ||||||||||||||||||||
| Gypsum Board-Type X | NTP+45 | |||||||||||||||||||||
| Gypsum Board-Type X-Mold Resistant | NTP+45 | |||||||||||||||||||||
| Wood Paneling | NTP+45 | |||||||||||||||||||||
| Wood Chair Rails | NTP+45 | |||||||||||||||||||||
| Wood Ceiling Cloud | NTP+45 | |||||||||||||||||||||
| Sheet Vinyl Flooring | NTP+45 | |||||||||||||||||||||
| Rubber Base | NTP+45 | |||||||||||||||||||||
| Ceiling Tiles | NTP+45 | |||||||||||||||||||||
| Blast Resistant Window | NTP+45 | |||||||||||||||||||||
| Glazing | NTP+45 | |||||||||||||||||||||
| Solid Surface Countertops | NTP+45 | |||||||||||||||||||||
| Kitchen Cabinets | NTP+45 | |||||||||||||||||||||
| Garbage Disposal | NTP+45 | |||||||||||||||||||||
| Interior Paint | NTP+45 | |||||||||||||||||||||
| Exterior Paint | X | X | X | X | X | X | NTP+30 | |||||||||||||||
| Roofing System | NTP+45 | |||||||||||||||||||||
| Roofing Insulation | NTP+45 | |||||||||||||||||||||
| Roof Drains | NTP+45 | |||||||||||||||||||||
| Scuppers | NTP+45 | |||||||||||||||||||||
| Coping | NTP+45 | |||||||||||||||||||||
| Flashing | NTP+45 | |||||||||||||||||||||
| STRUCTURAL | ||||||||||||||||||||||
| Reinforcing Steel Drawings | X | X | NTP+15 | |||||||||||||||||||
| Concrete Mix Design | NTP+45 | |||||||||||||||||||||
| Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion Joints | NTP+45 | |||||||||||||||||||||
| Concrete Field Test Results | NTP+45 | |||||||||||||||||||||
| Reinforcing Steel Mill Certifications | NTP+45 | |||||||||||||||||||||
| Slump Test results & Concrete Truck Tickets (per truck) | Test + 3 | |||||||||||||||||||||
| 7-Day Concrete Compressive Strength Test | Test + 3 | |||||||||||||||||||||
| 28-Day Concrete Compressive Strength Test | Test + 3 | |||||||||||||||||||||
| Blast Resistant Window Attachment | Design + 14 | |||||||||||||||||||||
| MECHANICAL | ||||||||||||||||||||||
| HVAC Balancing | Design+14 | |||||||||||||||||||||
| Registers | Design+14 | |||||||||||||||||||||
| Dampers | Design+14 | |||||||||||||||||||||
| Ductwork | Design+14 | |||||||||||||||||||||
| Sprinkler Heads | NTP+14 | |||||||||||||||||||||
| Ductwork Pressure Drops Before Removal | NTP+14 | |||||||||||||||||||||
| Ductwork Pressure Drops After Installation | NTP+14 | |||||||||||||||||||||
| Ductwork | NTP+14 | |||||||||||||||||||||
| Controls | Design+14 | |||||||||||||||||||||
| Piping | X | X | X | X | Design+14 | |||||||||||||||||
| Heaters | Design+14 | |||||||||||||||||||||
| Valves | X | X | X | X | Design+14 | |||||||||||||||||
| Pumps | X | X | X | X | X | Design+14 | ||||||||||||||||
| Thermal Insulation | Design+14 | |||||||||||||||||||||
| Instrumentation | Design+14 | |||||||||||||||||||||
| PLUMBING | ||||||||||||||||||||||
| Plumbing Fixtures | X | X | X | X | X | X | X | NTP+14 | ||||||||||||||
| Piping for Water | X | X | X | X | X | NTP+14 | ||||||||||||||||
| Garbage Disposal | X | NTP+14 | ||||||||||||||||||||
| Waste and Vent | X | X | X | X | X | X | NTP+14 | |||||||||||||||
| INTERIOR ELECTRICAL | ||||||||||||||||||||||
| Cables(electrical,comm,fire alarm) | X | X | X | X | X | X | X | X | X | X | NTP+14 | |||||||||||
| Switches (IF NEEDED) | X | X | X | X | X | X | X | X | NTP+14 | |||||||||||||
| Receptacles (IF NEEDED) | X | X | X | X | X | X | X | X | NTP+14 | |||||||||||||
| Panels | NTP+45 | |||||||||||||||||||||
| Breakers | NTP+45 | |||||||||||||||||||||
| Conduits | X | X | X | X | X | X | X | X | NTP+14 | |||||||||||||
| Lighting Fixtures | NTP+45 | |||||||||||||||||||||
| Lighting UPS units (if req'd) | NTP+45 | |||||||||||||||||||||
| Communication System Outlets(incl jacks) | NTP+45 | |||||||||||||||||||||
| Communications patch panels | NTP+45 | |||||||||||||||||||||
| PA Speakers | NTP+45 | |||||||||||||||||||||
| Fire Alarm Devices (All) | NTP+45 | |||||||||||||||||||||
| Occupancy Sensors | NTP+45 | |||||||||||||||||||||
| Power Packs | NTP+45 | |||||||||||||||||||||
| EXTERIOR ELECTRICAL | ||||||||||||||||||||||
| Conduits | X | X | NTP+14 | |||||||||||||||||||
| Transformer | X | X | X | X | X | X | NTP+14 | |||||||||||||||
| Meter | X | X | X | X | X | NTP+14 | ||||||||||||||||
| Cables(med & low voltage) | X | X | X | X | NTP+14 | |||||||||||||||||
| Switches | NTP+14 | |||||||||||||||||||||
| Contactors | NTP+14 | |||||||||||||||||||||
| Panels | NTP+14 | |||||||||||||||||||||
| Breakers | NTP+14 | |||||||||||||||||||||
| Controller (VFD) | X | X | X | X | NTP+14 | |||||||||||||||||
| Junction Cabinet | NTP+14 | |||||||||||||||||||||
| Heating Mat | NTP+14 | |||||||||||||||||||||
| CLOSEOUT | ||||||||||||||||||||||
| O&M maint data and maint manuals & Manufacturer's Warranty for Communications Equipment | X | X | X | Install + 14 | ||||||||||||||||||
| Factory and Field Test Certificates, Logs and Test Results | X | X | Before Acceptance | |||||||||||||||||||
| Inspection Logbook | X | Before Acceptance | ||||||||||||||||||||
| As Builts (electronic in AutoCAD and hard copies on Mylar) | X | Final + 7 |
File details come from the government source that posted it. Updated .