Attachment 12 -AF 66.xls

XLS spreadsheet 52 KB Posted

Attached to
Replace Utility Well #9 Beale AFB Federal contract opportunity
Solicitation number
FA468624R0006
Issued by
Department of the Air Force Air Combat Command

About this file

This document is a schedule of material submittals for a federal contract to replace utility well number 9 at Beale Air Force Base. The contract requires the contractor to submit design documents, plans, specifications, test results and other deliverables on specified dates ranging from notice to proceed to final project closeout. Key submittals and dates include 100% design documents due 45 days after notice to proceed, structural connection details due 45 days after notice to proceed, HVAC, fire alarm and communication layouts due 45 days after notice to proceed, demolition and asbestos plans due 7 and 45 days after notice to proceed respectively, and operation and maintenance manuals and as-built drawings due 14 and 7 days after final acceptance inspection. The related federal contract opportunity is a solicitation to design, drill, install, develop, equip, test and commission a replacement well and connect it to existing electrical, piping and communication networks at Beale Air Force Base for the Department of the Air Force Air Combat Command.

View the file

Other files for this federal contract opportunity

Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittal 1

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT NAMESOLICITATION /CONTRACT NUMBER
1134784Repair by Replace Well #9FA468624R0006
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBERNote: 3 copies required per submittal. Government will retain all submittals. Provide an electronic copy for each submittal.CERTIF. OF COMPLIANCESHOP DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYDRAWINGSREPORTTEST RESULTSREQUIRED SUBMISSION DATEDATE TO CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSAPPROVEDDISAPPROVEDCONTRACTOR SUBMITTALFINAL APPROVAL
GENERAL
Project Specific Form 66XNTP + 3
Construction ScheduleXNTP + 7
TCN Schedule (electronic required, hard copy optional)NTP + 7
Contractor's Health, Safety, and Environment PlanXNTP + 7
Contractor's QA/QC PlanNTP + 7
Copy of Engineering License(s) of person or consultancy responsible for designXDESIGN
DESIGN
100% design document to be provided electronically as pdf. and (DWG optional)XXXXNTP + 7 (100%)
Roof Drain Storm Sewer Tie InNTP+45
Wind Loading Diagrams for RoofNTP+45PE STAMP REQ'D
Structural Connection Details for Shear WallsNTP+45PE STAMP REQ'D
Structural Connection Details for FramingNTP+45PE STAMP REQ'D
Structural Connection Details for Blast Resistant Doors & WindowsNTP+45PE STAMP REQ'D
HVAC CalculationsNTP+45
Sprinkler LayoutNTP+45FPE or NICET Tech stamp req'd
Fire Alarm LayoutNTP+45FPE or NICET Tech stamp req'd
Communications LayoutXNTP+7
Technical SpecificationsXNTP+15
DEMOLITION/ASBESTOS
Demolition PlanXXXNTP+7
Asbestoes PlanNTP+45
CIVIL
Soil Gradations for each type of soil usedInstall -7
Moisture-Density curve for each type of soil usedInstall -7
Nuclear Densometer CalibrationInstall -7
Soil Compaction Test Results for Utilities, Facilities & PavementInstall+7
Storm PipeDesign+14
ARCHITECTURAL
Blast Resistant Doors and FramesNTP+45
Door HardwareNTP+45Hardware Schedule
Gypsum Board-Type XNTP+45
Gypsum Board-Type X-Mold ResistantNTP+45
Wood PanelingNTP+45
Wood Chair RailsNTP+45
Wood Ceiling CloudNTP+45
Sheet Vinyl FlooringNTP+45
Rubber BaseNTP+45
Ceiling TilesNTP+45
Blast Resistant WindowNTP+45
GlazingNTP+45
Solid Surface CountertopsNTP+45
Kitchen CabinetsNTP+45
Garbage DisposalNTP+45
Interior PaintNTP+45
Exterior PaintXXXXXXNTP+30
Roofing SystemNTP+45
Roofing InsulationNTP+45
Roof DrainsNTP+45
ScuppersNTP+45
CopingNTP+45
FlashingNTP+45
STRUCTURAL
Reinforcing Steel DrawingsXXNTP+15
Concrete Mix DesignNTP+45
Concrete Curing Compounds, Admixtures, Joint Sealants, Expansion JointsNTP+45
Concrete Field Test ResultsNTP+45
Reinforcing Steel Mill CertificationsNTP+45
Slump Test results & Concrete Truck Tickets (per truck)Test + 3
7-Day Concrete Compressive Strength TestTest + 3
28-Day Concrete Compressive Strength TestTest + 3
Blast Resistant Window AttachmentDesign + 14
MECHANICAL
HVAC BalancingDesign+14
RegistersDesign+14
DampersDesign+14
DuctworkDesign+14
Sprinkler HeadsNTP+14
Ductwork Pressure Drops Before RemovalNTP+14
Ductwork Pressure Drops After InstallationNTP+14
DuctworkNTP+14
ControlsDesign+14
PipingXXXXDesign+14
HeatersDesign+14
ValvesXXXXDesign+14
PumpsXXXXXDesign+14
Thermal InsulationDesign+14
InstrumentationDesign+14
PLUMBING
Plumbing FixturesXXXXXXXNTP+14
Piping for WaterXXXXXNTP+14
Garbage DisposalXNTP+14
Waste and VentXXXXXXNTP+14
INTERIOR ELECTRICAL
Cables(electrical,comm,fire alarm)XXXXXXXXXXNTP+14
Switches (IF NEEDED)XXXXXXXXNTP+14
Receptacles (IF NEEDED)XXXXXXXXNTP+14
PanelsNTP+45
BreakersNTP+45
ConduitsXXXXXXXXNTP+14
Lighting FixturesNTP+45
Lighting UPS units (if req'd)NTP+45
Communication System Outlets(incl jacks)NTP+45
Communications patch panelsNTP+45
PA SpeakersNTP+45
Fire Alarm Devices (All)NTP+45
Occupancy SensorsNTP+45
Power PacksNTP+45
EXTERIOR ELECTRICAL
ConduitsXXNTP+14
TransformerXXXXXXNTP+14
MeterXXXXXNTP+14
Cables(med & low voltage)XXXXNTP+14
SwitchesNTP+14
ContactorsNTP+14
PanelsNTP+14
BreakersNTP+14
Controller (VFD)XXXXNTP+14
Junction CabinetNTP+14
Heating MatNTP+14
CLOSEOUT
O&M maint data and maint manuals & Manufacturer's Warranty for Communications EquipmentXXXInstall + 14
Factory and Field Test Certificates, Logs and Test ResultsXXBefore Acceptance
Inspection LogbookXBefore Acceptance
As Builts (electronic in AutoCAD and hard copies on Mylar)XFinal + 7