The provided document is a Statement of Need (SON) for a federal contract opportunity to replace Well #9 at Beale Air Force Base in California. The project scope includes designing, drilling, installing, developing, equipping, testing, and functionally completing a new community water supply well to replace the existing Well #9, which does not have a required sanitary/annular seal. Key tasks include properly abandoning the existing well, installing a new well, pump, and control system, connecting the new well to the existing drinking water supply piping network, and performing industry-standard well testing. The new well must meet all local, state, regional, and federal requirements for a community drinking water supply. The contract opportunity is solicitation number FA468624R0006, issued by the Department of the Air Force Air Combat Command. The SON provides detailed technical requirements, environmental constraints, submittal requirements, and applicable standards for the project.
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF NEED:
Project Title: Repair by Replace Well #9 (Bldg. 8999) Project #: 1134784 Date: 20 Nov 2023 – highlighted sections 3.4.2. and 3.5.2 updated on 4/3/2024.
SUMMARY OF WORK
1. PURPOSE OF THE SECTION: The Statement of Need (SON) explains the general intent of the requirement listed above. It documents the major line items of work the Government expects to see accomplished, but it does not attempt to explain the exact details and/or method of execution for requirement; the Contractor will be responsible for providing specific performance details in their proposal. The Contractor must comply with all provisions and requirements of this contract.
STATEMENT OF NEED
1 BACKGROUND: This project is located at Building 8999, located on the car path to the north side of North Beale Road, Beale Air Force Base, California (See Attachment 1 – Site Map for exact location). Well #9 does not have a sanitary/annular seal, which is required by Department of Water Resources (DWR) Bulletin 74, California Well Standards. It was originally constructed in 1966, Sump pump installed in 2015 and Minor repair and clean off occurred in 2017. Well #9 is approx. 354 ft deep, its static water level is 108ft, with 2500gpm pump rate.
Well, is situated in undeveloped site, surrounded by perimeter fencing with adequate space for the planned project. Refer to the site plan and photo log attached.
2 PROJECT GENERAL SCOPE: The intent of this project is to replace Well #9 and connect the new well to the existing electrical, communications and piping network. The project will include all work necessary to Design, drill, install, develop, equip, test, and properly functional according to the requirements provided. Well #9 is a community water supply well as defined by the Section 13710 of the Water Code and the planned replacement well must meet standards for a community water supply well.
3 ITEMS OF WORK: Work includes but is not limited to the following items:
3.1 Plan/Permits
3.1.1 Contractor shall provide 100% and final IFC after review phases of design for the project using the standard applicable requirements listed below and to show the surface structures (existing/new), equipment, connections, sections to show the details of the underground installations, and dimensions of the new well and relative installation. design must also clarify the environmental protection measures according to the applicable requirements given.
3.1.2 Permitting; Provide all permits required. A well permit from the Yuba County Environmental Health Department is anticipated for both well destructions. And well installation. Acquiring the permits will need a water well installation plan to satisfy Yuba County and scope relative UFGS -33 11 13 requirements.
3.1.3 Submit a water and spill discharge plan to 9CES/CEI for approval prior to start of construction. Elements for the plan can be observed from AF-813 attached.
3.1.4 Perform a pre-drilling site inspection to identify location for new well, identify the existing underground utilities, and arrange for environmental limitations to prevent damages while digging.
3.2 Construction.
3.2.1 Properly abandon and seal the existing Well #9 including demolition of concrete, piping, casing, wires, pump, and all relative removable elements and dispose them off base, by following the Environmental/permit regulations and available Local, Federal, and State requirements.
3.2.2 Install new water well, pump, and control system with industry standard casing to a sufficient depth capable of maintaining flow of 1,200 gallons per minute (GPM) and connect to the existing drinking water supply piping network. Well installation shall be completed by a State of California C-57 licensed drilling contractor.
3.2.3 Provide borehole and well construction log.
3.2.4 Casing. The new water well casing shall be steel construction as defined in the
California DWR well standards. Screen perforations shall be selected in conjunction to filter pack design, to maximize well production and minimize infiltration of filter materials in well.
3.2.5 The existing well fittings are under the 100-year flood level, surface completion of the well shall be installed to the level of the existing transformer pad. The intent of this requirement is to eliminate the possibility of surface water entering through well head.
3.2.6 Provide new reinforced concrete pad estimated to be 6 feet by 10 feet by 4 inches thick.
3.2.7 Well shall conform to all local, state, regional and federal requirements for a community drinking water supply, including sanitary/annular seal to a minimum required depth not less than 50 ft.
3.2.8 Furnish new downhole water level sensing equipment to be connected to Siemens automated system.
3.2.9 Provide industry standard well testing to show the well meets the minimum requirements for production rate and water quality.
3.2.10 Paint the new and existing piping according to the submittal approved by base civil engineer.
3.2.11 File well construction and well destruction reports with the DWR.
3.3 Electrical
3.3.1 The well system will be powered by existing underground electrical system that feeds by a 225 KVA, 3 phase pad mounted transformer.
3.3.2 The existing generator at well #9’s house must be tested to be prepared as an emergency power resource.
3.3.3 Provide and install new 75-Hourspower submersible well pump, wiring, Pump controller (VFD) and associated parts and equipment.
3.3.4 Install a new water flow meter.
3.4 Connections and Valves
3.4.1 Modify existing piping as required to connect with new well. All piping shall meet appropriate code requirements and at a minimum shall match existing systems.
3.4.2 Provide new automatic valve “CLA-VAL” or similar automatic valve for water supply piping and flush piping. Reconfiguration of the piping, relocation of the existing check valve (if needed) and requirements for the new cla-valve must be clarified within the design.
3.5 Fencing
3.5.1 Contractor shall remove existing fencing around well piping and foundation, keep fence caps for re-use.
3.5.2 Contractor shall install new chain link fencing, posts, and barbed wire topping around new well, associated piping and new transformer.
2. ENVIRONMETNAL CONSTRIAINTS, DISPOSAL, SPILL, AND RECYCLING
REQUIREMENTS:
a. Contractor is responsible to follow the requirements incorporated with the attached
AF-813/USFWS consultation as part of the SON.
b. There are no waste or disposal areas available on the base property. The Contractor shall plan an off-base location in accordance with local and state codes for disposal of waste generated from the site.
c. Contact the Hazardous Waste Program Manager (HWPM) at 530-634-0744 prior to shipment of hazardous waste off site, and the Post Spill Response Team at 530- 301-9413.
d. Any scrap metal needs to be collected by Beale's QRP, please contact Mr. Shane Morris at 530-368-0744 for a metal recycling bin. C&D Debris reports need to be sent to Solid Waste Manager at: shane.morris.5@us.af.mil
e. Clean water generated from well testing and pumping activities cannot be discharged directly onto the ground surface. (RWQCB GO 2014-0194-DWQ, CAG140001 Section I.B.
f. Test/pumping water must be discharged into Brophy canal, done manually using hose. Proper infiltration and erosion control measure must be in place before and during the discharge. (See the attached Af-813/USFWS Consultation for further requirements).
3. OTHER ENVIRONMENTAL CONSTRAINTS: Environmental surveys shall be coordinated with the Contracting Officer, 9 CES and the 9 CES Environmental staff.
Equipment and vehicle traffic shall be restricted to existing roads or a 9 CES Environmental approved haul route. Temporary construction fencing and/or staking/flags may be required to clearly define vehicle and equipment routes.
4. Base Access. All contractor vehicles must enter the base via the Wheatland Gate and shall be subject to inspection. All contractor personnel must obtain base passes or be listed on the Entry Access List (EAL) throughout duration of work performance. Expect 72 hours minimum to process EAL’s.
AF 103: The Contractor shall apply for and obtain an approved Air Force Form 103, Base Civil Engineering Work Clearance Request. Permit application shall be submitted a mailto:shane.morris.5@us.af.mil minimum of thirty (30) calendar days prior to work as the Air Force requires adequate time to investigate facilities affected by outage and notify occupants. A copy of the unapproved AF 103 with number assigned by Customer Service shall be submitted to the Contracting Officer within 2 calendar days after submission. After approval is obtained a copy of the approved AF 103 shall be submitted to the Contracting Officer within 3 calendar days of approval.
5. SUBMITTALS: All submittals will be documented on an AF 66 Submittal Schedule submitted to the Contracting Officer and PM for approval. Required Submittals seeking approval will be submitted on an AF 3000.
6. Design: Contractor shall provide a complete 100% design drawing, submit for government review, following by submitting the final approved IFC (Issued for Construction), using the applicable criteria required and list in the SON.
A. Project Management/Reporting: Contractor must conduct the required meetings, site visits, including providing agendas, and notes as needed. Contractor shall perform the required quality control, inspection, status, and monitoring reports.
7. SCHEDULE: The Contractor shall develop a schedule to submit after contract award.
The schedule shall consist of a Performance Period which includes the construction schedule in calendar days.
8. Expected Warranties and Guarantees. All warranties and guarantees will be industry standards. This will include as a minimum a standard 1-year warranty of construction in addition to any standard manufacturer's warranties more than this period.
9. Work hours. All work shall be accomplished between 0700-1700 Mon- Fri. The work hours can be adjusted after it is coordinated and approved by the contracting officer and end user.
10. APPLICABLE STANDARDS: It is the contractor’s responsibility to identify and comply with all applicable requirements. Within of the following:
a. Air Force Design Guides/Standards (AFDG)
b. Air Force Handbooks (AFH)
c. Policies and Guidance for AF Design and Construction
d. Air Force Regulations (AFR)
e. Department of Defense Unified Facilities Guide Specifications (UFGS), with particular attention paid to:
i. UFGS Section 33 11 13- Potable Water Supply Wells
f. OSHA, Occupational, Safety and Health Act
g. Americans with Disability Act (ADA)
11. ATTACHMENTS:
i. UFGS Section 33 11 13- Potable Water Supply Wells
ii. AF-813/USFWS Consultation