UAS RQ-4 REPAIR 69 MXS MISSION AREAS B607

GRAND FORKS AFB, ND JFSD201312 1 156-021

PROJECT NO.

JFSD

201312

APPROVED DISAPPROVED

1 Contractor Warranty. Sec. 01000 Para. 3.3 1 Within 30 days of NTP

2 Base CE Work Clearance Request. Sec. 01000, Para. 4.1 3 As Required

3 Welding Certification AF Form 592, Sec. 01000, Para. 6.1 3 Within 10 days of NTP

4 Project Site Plan. Sec. 01000, Para. 7.2.1 3 Within 10 days of NTP

5 Dirt and Dust Control Plan. Sec. 01000, Para. 7.2.2 3 Within 10 days of NTP

6 Contractor's Health and Safety Plan. Sec. 01000, Para. 7.2.3 3 Prior to start of any work

7 Site Superintendent/ Project Manager Designation Letter. Sec.

01000, Para. 10.1.2 3 -30 days of BO

8 Site Conditions Photographs. Sec. 01000, Para. 12.5 3 Beneficial

Occupancy (BO)

9 Critical Path Method (CPM) Network Schedule. Sec. 01000, Para. 12.6.1 3

NLT + 30 days

BO

10 Schedule Showing Procurement Plans for Materials and Equipment. Sec. 01000, Para. 12.6.2.1 3

NLT + 30 days

BO

11 As-Built Redline Markup Drawings Sect. 01000, Para. 12.8.1 1 NLT + 30 days

BO

12 Final As-Built Drawings. Sec. 01000, Para. 12.8.3 1 At Final

Inspection

13 Real Property Record - Form DD1354. Sec. 01000, Para. 12.9 1 NLT + 90 days

14 Environmental Pollution Control Plans. Sec. 01000, Para. 13.3.1 3 NLT + 90 days

15 Storm Water Protection Plan. Sec. 01000, Para. 13.5 3

16 Waste Disposal Plan. Sec. 01000, Para. 13.6 3

17 Hazardous Materials List, Sec. 01000, Para. 13.7 3

18 Spill Control Plan. Sec. 01000, Para. 13.8 3

19 Dust Control Plan. Sec. 01000, Para. 13.10 3

20 Contractor Quality Control Plan. Sec. 01000, Para. 14.4 3

21 O & M Manuals. Sec. 01000, Para. 16 1

23 SCHEDULE OF SUBMITTALS 3 01 30 00

24 BUILDING DEMOLITION 3 02 41 00

25 ASBESTOS REMOVAL AND DISPOSAL 3 1 02 82 14

26 CONCRETE REINFORCEMENT 3 03 20 00

27 CONCRETE MIX DESIGN 3 03 30 00

28 METAL FABRICATIONS 3 05 50 00

29 FINISH CARPENTRY 3 06 20 00

FOLLOW-UPREQUIRED

SUBMITTAL

DATE

DATE

RECEIVED

IN

CONTRACT

ING

O

TH

E R

M A

TE

R

IA

L

O R

D

A

TA

S

E E

IN

D

IV

ID

U A

L S

P E

C S

E C

TI

O

N S

C O

LO

R

S E

LE

C

TI

O

N

M A

N U

FA

C

TU

R

E

'S

E

C O

M M

E N

D A

TI

O

N S

ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE,

TYPE OF SUBMITTAL

C A

TA

LO

G D

A

TA

LI

N

E N

U M

B E

R

S A

M P

LE

S

C E

R

TI

FI

C

A

TI

O N

O F

C O

M P

LI

A

N C

E A

N

C

LO

S

E O

U T

DATE CONTRACTOR NOTIFIED REMARKSFINAL

APPROVAL

CONTRACTOR

RESUBMITTAL

O P

E R

A

TI

G

IN

S

TR

U C

TI

O

N

S DATE

TO

CIVIL

ENGR.

RETURN

SUSPENSE

DATE

S H

O P

D R

A W

IN

G

S

BEFORE CONSTR AFTER CONSTR

W A

R R

A N

TY

C

LO

S E

O U

T

SOLICITATION/CONTRACT NO.PROJECT TITLE

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

UAS RQ-4 REAPIR 69 MXS MISSION AREAS B607

GRAND FORKS AFB, NORTH DAKOTA

SCHEDULE OF MATERIAL SUBMITTALS

(AF Form 66)

NO. OF COPIES REQUIRED

TO BE COMPLETED BY PROJECT ENGINEER

GRAND FORKS AFB, ND JFSD201312 2 156-021

PROJECT NO.

JFSD

201312

APPROVED DISAPPROVED

FOLLOW-UPREQUIRED

SUBMITTAL

DATE

DATE

RECEIVED

IN

CONTRACT

ING

O

TH

E R

M A

TE

R

IA

L

TA

S

E E

IN

D

IV

ID

U A

L S

P E

C S

E C

TI

O

N S

C O

LO

R

S E

LE

C

TI

O

N

M A

N U

FA

C

TU

R

E

C O

M M

E N

D A

TI

O

N S

ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE,

TYPE OF SUBMITTAL

C A

TA

LO

G D

A

TA

LI

N

E N

U M

B E

R

S A

M P

LE

S

C E

R

TI

FI

C

A

TI

O N

O F

C O

M P

LI

A

N C

E A

S

E O

U T

DATE CONTRACTOR NOTIFIED REMARKSFINAL

APPROVAL

CONTRACTOR

RESUBMITTAL

O P

E R

A

TI

TR

U C

TI

O

N

S DATE

TO

CIVIL

ENGR.

RETURN

SUSPENSE

DATE

S H

O P

D R

A W

IN

G

S

BEFORE CONSTR AFTER CONSTR

W A

R R

A N

TY

C

LO

S E

O U

T

SOLICITATION/CONTRACT NO.PROJECT TITLE

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

UAS RQ-4 REAPIR 69 MXS MISSION AREAS B607

GRAND FORKS AFB, NORTH DAKOTA

SCHEDULE OF MATERIAL SUBMITTALS

(AF Form 66)

NO. OF COPIES REQUIRED

TO BE COMPLETED BY PROJECT ENGINEER

30 ARCHITECTURAL CASEWORK 3 3 3 06 40 00

31 BUILDING INSULATION 3 07 20 00

32 SHEET METAL FLASHING 3 3 3 3 1 07 60 00

33 JOINT SEALERS 3 3 3 07 92 00

34 METAL DOORS AND FRAMES 3 3 08 11 13

35 ALUMINUM DOORS, FRAMES AND WINDOWS 3 3 3 3 1 1 08 11 16

36 WOOD DOORS 3 3 3 1 08 14 00

37 ACCESS DOORS 3 08 30 00

38 HARDWARE 3 3 08 71 00

39 LAMINATED GLASS 3 1 1 08 81 00

40 INSULATED TRANSLUCENT ROOF PANELS 3 3 3 3 1 1 1 08 95 00

41 ACOUSTIC CEILING TILE AND GRID 3 3 1 09 51 00

42 RESILIENT FLOORING 3 3 09 65 00

43 CARPET 3 3 3 1 1 09 68 00

44 WALLCOVERING 3 3 1 09 72 00

45 PAINT AND STAIN 3 3 1 09 90 00

46 MARKERBOARDS 3 3 3 1 10 10 10

47 BLINDS 3 3 3 1 12 51 00

48 FIRE SPRINKLER PRODUCT DATA LAYOUT

DRAWINGS AND CALCULATIONS 3 3 3 1 1 1 1 21 05 00

49 PLUMBING METERS AND GAGES 3 3 3 22 05 00

50 PLUMBING VALVES AND SPECIALTIES 3 3 3 22 05 00

51 PLUMBING IDENTIFICATION 3 3 3 22 05 00

52 JOINT SEALANTS 3 3 3 22 05 00

53 PLUMBING HANGERS, SUPPORTS AND ACCESS

PANELS 3 3 3 22 05 00

54 PLUMBING PIPING AND EQUIPMENT 3 3 3 22 10 00

55 PLUMBING FIXTURES AND RECORD DRAWINGS 3 3 3 22 40 00

GRAND FORKS AFB, ND JFSD201312 3 156-021

PROJECT NO.

JFSD

201312

APPROVED DISAPPROVED

FOLLOW-UPREQUIRED

SUBMITTAL

DATE

DATE

RECEIVED

IN

CONTRACT

ING

O

TH

E R

M A

TE

R

IA

L

TA

S

E E

IN

D

IV

ID

U A

L S

P E

C S

E C

TI

O

N S

C O

LO

R

S E

LE

C

TI

O

N

M A

N U

FA

C

TU

R

E

C O

M M

E N

D A

TI

O

N S

ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE,

TYPE OF SUBMITTAL

C A

TA

LO

G D

A

TA

LI

N

E N

U M

B E

R

S A

M P

LE

S

C E

R

TI

FI

C

A

TI

O N

O F

C O

M P

LI

A

N C

E A

S

E O

U T

DATE CONTRACTOR NOTIFIED REMARKSFINAL

APPROVAL

CONTRACTOR

RESUBMITTAL

O P

E R

A

TI

TR

U C

TI

O

N

S DATE

TO

CIVIL

ENGR.

RETURN

SUSPENSE

DATE

S H

O P

D R

A W

IN

G

S

BEFORE CONSTR AFTER CONSTR

W A

R R

A N

TY

C

LO

S E

O U

T

SOLICITATION/CONTRACT NO.PROJECT TITLE

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

UAS RQ-4 REAPIR 69 MXS MISSION AREAS B607

GRAND FORKS AFB, NORTH DAKOTA

SCHEDULE OF MATERIAL SUBMITTALS

(AF Form 66)

NO. OF COPIES REQUIRED

TO BE COMPLETED BY PROJECT ENGINEER

56 O & M MANUALS 1 23 00 00

57 RECORD DRAWINGS 1 23 00 00

58 MECHANICAL IDENTIFICATION 3 3 3 23 05 00

59 MECHANICAL VIBRATION CONTROL, ACCESS PANELS

AND JOINT SEALANTS 3 3 3 23 05 00

60 PIPE SUPPORTS & ANCHORS 3 3 3 23 05 00

61 PIPING VALVES, FITTINGS, METERS, GAUGES AND

SPECIALTIES 3 3 3 23 05 00

62 TEST & BALANCE REPORTS 3 3 1 23 05 93

63 HVAC INSULATION DATA SHEETS AND MATERIAL

SCHEDULE 3 3 3 23 07 00

ELECTRIC CONTROL AND FACILITIES MANAGEMENT

EQUIPMENT, INSTALLATION DRAWINGS AND

CONTROLS SEQUENCES

3 3 1 23 09 00

65 ELECTRIC CONTROL AND FACILITIES MANAGEMENT

OPERATION AND MAINTENANCE MANUALS 3 3 1 23 09 00

66 VARIABLE FREQUENCY DRIVES 3 3 3 23 09 33

HYDRONIC PIPING, SPECIALTIES, LAYOUT

DRAWINGS, SYSTEM TESTING AND SYSTEM

CLEANING

3 3 3 23 21 13

68 BRAZING CERTIFICATION 3 3 3 23 21 13

69 HYDRONIC SYSTEM TESTING AND CLEANING 3 3 3 23 25 00

70 GLYCOL SOLUTION AND CHEMICAL FEEDERS 3 3 3 23 25 00

71 DIFFUSERS, REGISTERS, GRILLES AND LOUVERS 3 3 3 23 30 00

72 AIR DISTRIBUTION DUCTWORK, DUCT LINER,

SPECIALTIES AND LAYOUT DRAWINGS 3 3 3 23 30 00

73 AIR FILTERS, DAMPERS, FIRE DAMPERS AND SMOKE

DAMPERS 3 3 3 23 30 00

74 AIR TERMINAL UNITS 3 3 3 23 30 00

75 FANS 3 3 3 23 34 00

76 AIR HANDLING UNITS 3 3 3 23 73 13

77 FAN COILS 3 3 3 23 82 00

78 PANELBOARDS 3 3 3 1 1 26 24 16

79 TRANSFORMERS 3 3 3 1 1 26 22 13

80 CONDUIT AND JUNCTION BOXES 3 3 3 1 26 05 33

GRAND FORKS AFB, ND JFSD201312 4 156-021

PROJECT NO.

JFSD

201312

APPROVED DISAPPROVED

FOLLOW-UPREQUIRED

SUBMITTAL

DATE

DATE

RECEIVED

IN

CONTRACT

ING

O

TH

E R

M A

TE

R

IA

L

TA

S

E E

IN

D

IV

ID

U A

L S

P E

C S

E C

TI

O

N S

C O

LO

R

S E

LE

C

TI

O

N

M A

N U

FA

C

TU

R

E

C O

M M

E N

D A

TI

O

N S

ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE,

TYPE OF SUBMITTAL

C A

TA

LO

G D

A

TA

LI

N

E N

U M

B E

R

S A

M P

LE

S

C E

R

TI

FI

C

A

TI

O N

O F

C O

M P

LI

A

N C

E A

S

E O

U T

DATE CONTRACTOR NOTIFIED REMARKSFINAL

APPROVAL

CONTRACTOR

RESUBMITTAL

O P

E R

A

TI

TR

U C

TI

O

N

S DATE

TO

CIVIL

ENGR.

RETURN

SUSPENSE

DATE

S H

O P

D R

A W

IN

G

S

BEFORE CONSTR AFTER CONSTR

W A

R R

A N

TY

C

LO

S E

O U

T

SOLICITATION/CONTRACT NO.PROJECT TITLE

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

UAS RQ-4 REAPIR 69 MXS MISSION AREAS B607

GRAND FORKS AFB, NORTH DAKOTA

SCHEDULE OF MATERIAL SUBMITTALS

(AF Form 66)

NO. OF COPIES REQUIRED

TO BE COMPLETED BY PROJECT ENGINEER

81 JUNCTION BOXES 3 3 3 1 26 05 34

82 CONDUCTORS 3 3 3 1 26 05 19

83 WIRING DEVICES - SWITCHES, RECEPTACLES AND

DEVICE WALL PLATES 3 3 3 3 3 1 1 26 27 26

84 FUSES 3 3 3 1 1 26 28 13

85 INTERIOR LIGHTING FIXTURES 3 3 3 3 1 1 26 51 13

86 EXTERIOR LIGHTING FIXTURES 3 3 3 3 1 1 26 51 13

87 FIRE ALARM SYSTEMS 3 3 3 1 1 28 31 10

88 CIRCUIT AND MOTOR DISCONNECTS 3 3 3 1 1 26 28 16

89 MOTOR STARTERS 3 3 3 1 1 26 29 13

90 OCCUPANCY SENSORS 3 3 3 1 1 SEE LIGHTING PLANS

NOTE: This Submittal Schedule is for the Contractor's use in assembling and organizing the Submittals to be made to the Government. See individual specification sections for possible additional submittal requirements.