This Standard Form 30 Amendment of Solicitation/Modification of Contract modifies a federal contract for demolition and fire alarm panel relocation services at Malmstrom Air Force Base. The amendment extends the solicitation response due date from 23 December 2025 to 29 December 2025 and updates several line items, including demolition of Buildings 1879, 29001, and 29002, with modifications to asbestos-related language. A new Line Item 0011 is added for Building 1879 Fire Alarm Panel Relocation, which involves relocating the fire control panel to the east wall of building 1934, including reconnecting pull stations, adding a weather-resistant enclosure, and performing necessary trenching, wiring, and conduit work. The place of performance is the 341 CES CECR BASE SRMC at Malmstrom Air Force Base, Montana, with a delivery timeline of 84 calendar days from the Notice to Proceed. The amendment includes updates to various attachments such as the Statement of Work, Concept Plan, and wage determination.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section A - Solicitation/Contract Form

The following modifications were made:

Information From To Response Due Date 23 Dec 2025 29 Dec 2025

Section B - Supplies or Services & Prices or Costs

Line Item 0003

The following Line Item modifications were made:

Information From To

Description

Demolish Building 1897: Measurement and payment for this item shall be at the contract lump sum price for "Demolish Building 1897". Payment shall include all costs for labor, materials, and equipment to demolish the entire building including foundation, removal of all materials off site to a landfill, cleanup, and all other incidental items necessary to complete the work. If any asbestos containing materials are found during the asbestos survey performed during design, this will constitute unforeseen site conditions and require a Modification to the contract documents.

Demolish Building 1879: Measurement and payment for this item shall be at the contract lump sum price for "Demolish Building 1879". Payment shall include all costs for labor, materials, and equipment to demolish the entire building including foundation, removal of all materials off site to a landfill, cleanup, and all other incidental items necessary to complete the work. If any asbestos containing materials are found during the asbestos survey performed during design, this will constitute unforeseen site conditions and require a Modification to the contract documents.

Line Item 0004

The following Line Item modifications were made:

Information From To

Description

Demolish Building 29001: Measurement and payment for this item shall be at the contract lump sum price for "Demolish Building 29001". Payment shall include all costs for labor, materials, and equipment to demolish the entire building including foundation, dirt berm, removal of all materials off site to a landfill, cleanup, and all other incidental items necessary to complete the work. If any asbestos containing materials are found during the asbestos survey performed during design, this will constitute unforeseen site conditions and require a Modification to the contract documents.

Demolish Building 29001: Measurement and payment for this item shall be at the contract lump sum price for "Demolish Building 29001". Payment shall include all costs for labor, materials, and equipment to demolish the entire building including foundation, dirt berm, removal of all materials off site to a landfill, cleanup, and all other incidental items necessary to complete the work.

Line Item 0005

The following Line Item modifications were made:

Information From To

Description

Demolish Building 29002: Measurement and payment for this item shall be at the contract lump sum price for "Demolish Building 29002". Payment shall include all costs for labor, materials, and equipment to demolish the entire building including foundation, removal of all materials off site to a landfill, cleanup, and all other incidental items necessary to complete the work. If any asbestos containing materials are found during the asbestos survey performed during design, this will constitute unforeseen site conditions and require a Modification to the contract documents.

Demolish Building 29002: Measurement and payment for this item shall be at the contract lump sum price for "Demolish Building 29002". Payment shall include all costs for labor, materials, and equipment to demolish the entire building including foundation, removal of all materials off site to a landfill, cleanup, and all other incidental items necessary to complete the work.

Line Item 0011

The following Line Item(s) were added:

Item Supplies / Services Quantity Unit Unit Price Amount

Building 1879 Fire Alarm Panel Relocation: Measurement and payment for this item shall be at the contract lump sum price for "Building 1879 Fire Alarm Panel Relocation". Payment shall include all costs for labor, materials, and equipment to relocate the fire control panel in 1879 to the east facing wall of building 1934. This shall include but is not limited to reconnecting all pull stations in

FA462626R00030001

the horse stables, adding a new weather resistant enclosed box for the station to remain in, trenching, wiring, and conduit needed to perform the task.

Product Service Code: P400 Pricing Arrangement: Firm Fixed Price

1 Job

Section E - Inspection and Acceptance

Line Item 0011

The following Inspection and Acceptance Location(s) were added:

Inspection and Acceptance Location - DoDAAC: F2W3D5

Information Value Action Both Location Destination

Inspection and Acceptance Location

F2W3D5

341 CES CECR BASE SRMC

AF BPN NO MILSBILLS PROCESSES, 39 78TH ST N BLDG 470

MALMSTROM AFB, MT 59402

UNITED STATES

Instructions See Statement of Work (SOW) or Performance Work Statement (PWS) for Acceptance/inspection criteria.

POC Name Brady Lorenz POC Email brady.lorenz@us.af.mil POC Telephone 4067316144

Section F - Deliveries or Performance

Line Item 0011

The following Delivery Information was added:

Place of Performance - DoDAAC: F2W3D5

Information Value

Address

Place of Performance F2W3D5

341 CES CECR BASE SRMC

AF BPN NO MILSBILLS PROCESSES, 39 78TH ST N BLDG 470

MALMSTROM AFB, MT 59402

UNITED STATES

POC Name Brady Lorenz POC Email brady.lorenz@us.af.mil POC Telephone 4067316144 Delivery 84 Calendar Days, From Date of Notice to Proceed Receipt to completion of performance

Section J - List of Attachments

Header Miscellaneous Text (Modified):

Attachment 1 - Design Build Statement of Work (4 Sept 2025) DSN-CSN Amended Statement of Work dated 16 Dec 2025

Attachment 2 - Combined Specifications

Attachment 3 - Concept Plan Concept Plan Amendment 001

Attachment 4 - 1879 ACM Pb Results East Base Natural Gas Services (31 Oct 2011)

Attachment 5 - 1879 ACM Pb Design Survey Results East Base Natural Gas Services (20 Dec 2011)

Attachment 6 - 1879 ACM Sample Results (2003)

Attachment 7 - Wage Determination MT 20250066 (updated 12 Dec 2025)

Attachment 8 - Sections L and M (updated 18 Dec 2025)

Attachment 9 - Buildings 29001 and 29002 Final Hazmat Report dated (15 Oct 2024)

Attachment 10 - Building 1879 Combined Photos

Attachment 11 - Building 29001 Combined Photos

Attachment 12 - Building 29002 Combined Photos

Attachment 13 - Exterior Box Photos

Attachment 14 - Q&A dated 18 Dec 2025

SUMMARY OF CHANGES
Solicitation/Contract Form
Supplies or Services & Prices or Costs
Inspection and Acceptance
Deliveries or Performance
List of Attachments
IDCode: J
Page: 1
Pages: 4
AmendNo: 0001
EffDate: 18 Dec 2025
ReqNo:
ProjNo: NZAS 23-0008
IssCode: FA4626
AdmCode:
IssuedBy: FA4626 341 CONS LGC

7015 GODDARD DR, BLDG 145 CP 406 731 3744

MALMSTROM AFB, MT 59402-6863

UNITED STATES

JILLIAN URICK, Email: jillian.urick@us.af.mil Telephone: 731-3772 Colleen Goad, Email: colleen.goad.1@us.af.mil Telephone: 632-3473 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: FA462626R0003
SolDate: 09 Dec 2025
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: See Section G - Contract Administration Data
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: This purpose of the Amendment is to:

1. Extend the Solicitation period from 23 Dec 2025 to 29 Dec 2025 (see Attachment 8 dated 18 Dec 2025)

2. Update the Statement of Work (dated 16 Dec 2025), project Concept Plan, and MT Wage Determination.

3. Revise CLINs 0003, 0004, and 0005

4. Add CLIN 0011

5. Add Attachments 9-14

ContNameTitle:
CoNameTitle: COLLEEN T. GOAD
ContDate:
CODate: 18 Dec 2025