Questions and Answers 4.docx

DOCX document 11 KB Posted

Attached to
Remodel Dorm 740 Federal contract opportunity
Solicitation number
FA4626-10-R-0021
Issued by
Department of the Air Force Global Strike Command

View the file

Other files for this federal contract opportunity

Other files attached to Remodel Dorm 740, newest first.
File Type Posted
Questioins and Answers 7.docx DOCX document
Questions and Answers 6.docx DOCX document
BIRD COVE DETAIL.pdf PDF
Questions and Answers 5.docx DOCX document
Amendment 0002.doc DOC document
085113-revised on Sept 9 2010.doc DOC document
Amendment 0001.doc DOC document
010100-Revised.9-9-2010.doc DOC document
TOC.Revise.9-9-2010doc.doc DOC document
Question and Answers 3.docx DOCX document
Questions 2.docx DOCX document
740 Site Visit.pdf PDF
Questions 1.docx DOCX document
Attach 1 Specifications.zip ZIP file
Attach 2 Material Submital.xlsx XLSX spreadsheet
Attach 5 Wage Determination Building.docx DOCX document
Attch 3 Schedule of Drawings.DOC DOC document
Attach 5 Wage Determination Heavy.docx DOCX document
Attch 4 Drawings.zip ZIP file
Solicitation.doc DOC document
Attch 6 Past Performance Questionnaire.docx DOCX document
Attch 7 - Subcontractor Consent Form - 10R0027.docx DOCX document
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1) Tile clarification on page A7.1 elevations 1 and 2- Interior restroom elevations A, parts of C, E, F show some definite ceramic tile locations, while the remaining walls appear to be whitewashed out, and we are uncertain if tile should be on all walls 3’7” AFF. Will you clarify if just the ½ wall and the wall on the east side of shower are to receive tile, or if it is all walls, excluding the shower.

Answer:

All walls that show tile, whether it is shown “whitewashed out” or with a darker line, will all get new tile. There is no tile shown for the shower. The “whitewashed” lines are to help denote different planes of depth. The lighter lines are to represent a wall at a distance beyond. All tile is to be new.

2) Elevation 7 on A7.1 also is whitewashed out showing the pattern on the tile bench and half wall, is there a pattern that is different.

Answer:

All walls are to receive new tile. See answer above.

3) Elevations 3 and 4 on A7.1- Will you clarify that if just the column in the unique restroom elevation is the only area to receive tile, or if all remaining walls, excluding shower are to get tile.

Answer:

All walls, excluding shower, are to receive now tile.