Questions and Answers 4.docx
DOCX document 11 KB Posted
- Attached to
- Remodel Dorm 740 Federal contract opportunity
- Solicitation number
- FA4626-10-R-0021
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questioins and Answers 7.docx | DOCX document | |
| Questions and Answers 6.docx | DOCX document | |
| BIRD COVE DETAIL.pdf | ||
| Questions and Answers 5.docx | DOCX document | |
| Amendment 0002.doc | DOC document | |
| 085113-revised on Sept 9 2010.doc | DOC document | |
| Amendment 0001.doc | DOC document | |
| 010100-Revised.9-9-2010.doc | DOC document | |
| TOC.Revise.9-9-2010doc.doc | DOC document | |
| Question and Answers 3.docx | DOCX document | |
| Questions 2.docx | DOCX document | |
| 740 Site Visit.pdf | ||
| Questions 1.docx | DOCX document | |
| Attach 1 Specifications.zip | ZIP file | |
| Attach 2 Material Submital.xlsx | XLSX spreadsheet | |
| Attach 5 Wage Determination Building.docx | DOCX document | |
| Attch 3 Schedule of Drawings.DOC | DOC document | |
| Attach 5 Wage Determination Heavy.docx | DOCX document | |
| Attch 4 Drawings.zip | ZIP file | |
| Solicitation.doc | DOC document | |
| Attch 6 Past Performance Questionnaire.docx | DOCX document | |
| Attch 7 - Subcontractor Consent Form - 10R0027.docx | DOCX document |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1) Tile clarification on page A7.1 elevations 1 and 2- Interior restroom elevations A, parts of C, E, F show some definite ceramic tile locations, while the remaining walls appear to be whitewashed out, and we are uncertain if tile should be on all walls 3’7” AFF. Will you clarify if just the ½ wall and the wall on the east side of shower are to receive tile, or if it is all walls, excluding the shower.
Answer:
All walls that show tile, whether it is shown “whitewashed out” or with a darker line, will all get new tile. There is no tile shown for the shower. The “whitewashed” lines are to help denote different planes of depth. The lighter lines are to represent a wall at a distance beyond. All tile is to be new.
2) Elevation 7 on A7.1 also is whitewashed out showing the pattern on the tile bench and half wall, is there a pattern that is different.
Answer:
All walls are to receive new tile. See answer above.
3) Elevations 3 and 4 on A7.1- Will you clarify that if just the column in the unique restroom elevation is the only area to receive tile, or if all remaining walls, excluding shower are to get tile.
Answer:
All walls, excluding shower, are to receive now tile.