FA4620-17-R-B001_MACC_Seed_Project_SOW_Atch_C_-_32_17_24_Pavement_Markings_CAP1008257.pdf

PDF 563 KB Posted

Attached to
FY17 MACC
Solicitation number
FA4620-17-R-B001
Issued by

About this file

Seed Project SOW Attachment C

View the file

Other files

File Type Posted
FA4620-17-R-B001_Amendment_04.pdf PDF
FA4620-17-R-B001_MACC_Seed_Project_Amend_4,_SOW_Atch_B_-_32_01_11_Paint_Removal_CAP1008257.pdf PDF
FA4620-17-R-B001_Atch_3_Past_Perf_cover_letter_and_Questionare.doc DOC document
FA4620-17-R-B001_Amendment_2_SF-30.pdf PDF
FA4620-17-R-B001_Amendment_3_SF-30.pdf PDF
Site_Visit_Sign_in_Roster_3_Mar_17.pdf PDF
FY17_MACC_SF1442_Amendment_1.pdf PDF
FA4620-17-R-B001_Atch_7_2016_Base_Design_Standards.pdf PDF
FA4620-17-R-B001_MACC_Seed_Project_SOW_Atch_B_-_32_01_11_Paint_Removal_CAP1008257.pdf PDF
FA4620-17-R-B001_MACC_Seed_Project_SOW_Atch_D_-_Task_Order_Drawings_CAP_1008257.pdf PDF
FA4620-17-R-B001_Atch_6_MACC_Specs_25_Oct_16.pdf PDF
FA4620-17-R-B001_MACC_Seed_Project_SOW_Atch_A_-_01_35_13_Special_Procedures_CAP1008257.pdf PDF
FY17_MACC_SF1442_Released.pdf PDF
FA4620-17-R-B001_Atch_11C_WA170001_Highway.pdf PDF
FA4620-17-R-B001_Atch_11D_WA170120_Residental.pdf PDF
FA4620-17-R-B001_Atch_11A_WA170042_Building.pdf PDF
FA4620-17-R-B001_Atch_3_Past_Perf_cover_letter_and_Questionare.pdf PDF
FA4620-17-R-B001_Atch_1_MACC_Seed_Project_TORFP_Letter.pdf PDF
FA4620-17-R-B001_Atch_11B_WA170101_Heavy.pdf PDF
FA4620-17-R-B001_Atch_5_MACC_Seminar_SOW_8_Nov_16.pdf PDF
FA4620-17-R-B001_Atch_1A_MACC_Seed_Project_Price_Schedule.pdf PDF
FA4620-17-R-B001_Atch_10_FAFB_Real_ID_Act_Pamphlet.pdf PDF
FA4620-17-R-B001_Atch_1B_Seed_Project_SOW_CAP1008257__6_Feb_17.pdf PDF
FA4620-17-R-B001_MACC_Seed_Project_SOW_Atch_E_-_BREAKDOWN_OF_PAINTING_CAP1008257.pdf PDF
FA4620-17-R-B001_Atch_2_MACC_Past_Performance_Info_28_Nov_16.pdf PDF
FA4620-17-R-B001_Atch_9_FAFB_Operational_Climactic_Data.pdf PDF
FA4620-17-R-B001_Atch_8_Architectural_Compatibility_Plan.pdf PDF
FA4620-17-R-B001_Atch_4_Subcontractor_-_Teaming_Arangement_Release.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY17 AIRFIELD PAVEMENT MARKING ATTACHMENT C

PROJECT NUMBER CAP1008257

FAIRCHILD AFB, WA

DIVISION 32 — EXTERIOR IMPROVEMENTS

SECTION 32 17 23 - PAVEMENT MARKINGS Page 1 of 10

SECTION 32 17 23 - PAVEMENT MARKINGS (08/16)

PART 1 GENERAL

1.1. DESCRIPTION OF WORK

The work specified by this section consists of furnishing all labor, equipment, tools, appliances, transportation, materials, and quality control reports required to prepare and mark the airfield pavements on Fairchild AFB as shown in the contract drawings and as otherwise specified herein. The airfield marking must be completed without damage to pavement surface, joints, joint and crack seals, or any other government property. Compliance with specifications for pavement marking materials shall be determined by laboratory analysis as described in paragraph 3.6. Compliance with requirements for proper installation and placement of markings shall be as stated in paragraph 3.5 APPLICATION.

1.2. REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

AASHTO M 247 (2013) Standard Specification for Glass Beads Used in Pavement Markings

AASHTO M 248 (1991; R 2012) Standard Specification for Ready-Mixed White and Yellow Traffic Paints

AASHTO M 249 (2012; R2016) Standard Specification for White and Yellow Reflective Thermoplastic Striping Material (Solid Form)

ASTM INTERNATIONAL (ASTM)

ASTM D2621 (1987; R 2011) Infrared Identification of Vehicle Solids from Solvent-Reducible Paints

ASTM D2697 (2003; R 2014) Volume Nonvolatile Matter in Clear or Pigmented Coatings

ASTM D3335 (1985a; R 2014) Low Concentrations of Lead, Cadmium, and Cobalt in Paint by Atomic Absorption Spectroscopy

ASTM D3718 (1985a; R 2015) Low Concentrations of Chromium in Paint by Atomic Absorption Spectroscopy

ASTM D3924 (2016) Standard Specification for Environment for Conditioning and Testing Paint, Varnish, Lacquer, and Related Materials

ASTM D3960 (2005; R 2013) Determining Volatile Organic Compound (VOC) Content of Paints and Related Coatings

ASTM D4060 (2014) Abrasion Resistance of Organic Coatings by the Taber Abraser

ASTM D4061 (2013) Standard Test Method for Retroreflectance of

FA4620-17-R-B001

SOW Atch C - 32 17 24 Pavement Markings

SECTION 32 17 23 - PAVEMENT MARKINGS Page 2 of 10

Horizontal Coatings

ASTM D4541 (2009; E 2010) Pull-Off Strength of Coatings Using Portable Adhesion Testers

ASTM D471 (2016a) Standard Test Method for Rubber Property - Effect of Liquids

ASTM D476 (2015) Dry Pigmentary Titanium Dioxide Pigments

ASTM D6628 (2003; R 2015) Standard Specification for Color of Pavement Marking Materials

ASTM D711 (2010; R 2015) No-Pick-Up Time of Traffic Paint

ASTM D7234 (2012) Standard Test Method for Pull-Off Adhesion Strength of Coatings on Concrete Using Portable Pull-Off Adhesion Testers

ASTM D823 (1995; E 2012; R 2012) Producing Films of Uniform Thickness of Paint, Varnish, and Related Products on Test Panels.

ASTM E1347 (2006; R 2011) Color and Color Difference Measurement by Tristimulus (Filter) Colorimetry

ASTM E1710 (2011) Standard Test Method for Measurement of Retroreflective Pavement Marking Materials with CEN- Prescribed Geometry Using a Portable Retroreflectometer

ASTM E2177 (2011) Standard Test Method for Measuring the Coefficient of Retroreflected Luminance (RL) of Pavement Markings in a Standard Condition of Wetness

ASTM E2302 (2003; R 2016) Standard Test Method for Measurement of the Luminance Coefficient Under Diffuse Illumination of Pavement Marking Materials Using a Portable Reflectometer

ASTM G154 (2016) Standard Practice for Operating Fluorescent Light Apparatus for UV Exposure of Nonmetallic Materials

INTERNATIONAL CONCRETE REPAIR INSTITUTE (ICRI)

ICRI 03732 (1997) Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, and Polymer Overlays

MASTER PAINTERS INSTITUTE (MPI)

MPI 97 (2015) Traffic Marking Paint, Latex

U.S. FEDERAL AVIATION ADMINISTRATION (FAA)

FAA AC 150/5370-10 (2014; Rev G; Errata 1 2015; Errata 2 2016) Standards for Specifying Construction of Airports

U.S. GENERAL SERVICES ADMINISTRATION (GSA)

FED-STD-595 (Rev C; Notice 1) Colors Used in Government Procurement

FS TT-B-1325 (Rev D; Notice 1) Beads (Glass Spheres) Retro-Reflective (Metric)

FS TT-P-1952 (2015; Rev F) Paint, Traffic and Airfield Markings, Waterborne

FA4620-17-R-B001

SECTION 32 17 23 - PAVEMENT MARKINGS Page 3 of 10

1.3. SUBMITTALS

Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES of the BDS:

Product Data:

Equipment: Lists of proposed equipment, including descriptive data, and notifications of proposed Contractor actions as specified in this section. List of removal equipment shall include descriptive data indicating area of coverage per pass, pressure adjustment range, tank and flow capacities, and safety precautions required for the equipment operation.

Manufacturer's current printed product description and Material Safety Data Sheets (MSDS) for each type paint/color proposed for use and the reflective media.

Qualifications

Documentation on personnel qualifications, as specified.

Test Reports:

Sampling and Testing

Certified copies of the test reports, prior to the use of the materials at the jobsite. Testing shall be performed in an approved independent laboratory.

Certificates:

Volatile Organic Compound (VOC)

Certificate stating that the proposed pavement marking paint meets the VOC regulations of the local Air Pollution Control District having jurisdiction over the geographical area in which the project is located.

Manufacturer's Instructions:

Waterborne Paint

1.5. DELIVERY AND STORAGE

All materials shall be delivered and stored in original sealed containers that plainly show the designated name, formula or specification number, batch number, color, date of manufacture, manufacturer's name, and directions, all of which shall be plainly legible at time of use. The Contractor shall store equipment and materials only in areas approved by the CO or authorized representative.

PART 2 PRODUCTS

2.1. EQUIPMENT

2.1.1. Application Equipment: Submit application equipment list appropriate for the material(s) to be used. Include manufacturer's descriptive data and certification for the planned use that indicates area of coverage per pass, pressure adjustment range, tank and flow capacities, and all safety precautions required for operating and maintaining the equipment. Provide and maintain machines, tools, and equipment used in the performance of the work in satisfactory operating condition, or remove them from the work site. Provide mobile and maneuverable application equipment to the extent that straight lines can be followed and normal curves can be made in a true arc.

FA4620-17-R-B001

SECTION 32 17 23 - PAVEMENT MARKINGS Page 4 of 10

2.1.2. Marking Machinery: The equipment used for marking shall be mounted on pneumatic tires and shall be capable of applying lines of paint only, or paint and beads simultaneously, in widths of ((from) (102 mm (4 inches)) (to) (1 m (3 feet)) at a speed of at least 5 miles per hour. Equipment shall be sufficiently mobile and maneuverable to allow application of straight lines or curves in a true arc. It shall be adjustable to allow application of single lines of single colors and multiple lines (at least three) of different colors, at least 150 mm (6 inches) wide, and skip-lines in variable lengths at least 102 mm (6 inches) wide. All spray applicators and bead dispensers shall produce markings of uniform thickness, width, and appearance, with clean-cut edges, all three lines at the rate specified in paragraph 3.5.1.1. The Contractor shall equip mobile marking equipment with a hand-operated spray applicator to mark areas that are otherwise inaccessible or provide separate equipment to apply legends and markings in spaces where large equipment cannot be manipulated.

2.1.3. Reflective Media Dispenser: Provide pressurized or drop-on type bead dispenser capable of uniformly dispensing reflective glass spheres at controlled rates of flow. Attach the dispenser for applying the reflective media to the paint dispenser and designed to operate automatically and simultaneously with the applicator through the same control mechanism. The bead applicator must be capable of adjustment and designed to provide uniform flow of reflective media over the full length and width of the stripe at the rate of coverage specified in paragraph APPLICATION. The bead dispenser must operate automatically to begin flow prior to the flow of binder to assure that the strip is fully reflectorized.

2.1.2. Lighting: The Contractor shall furnish all lighting necessary for night operations at no cost to the Government. Lighting will be directed or shaded to prevent interference with aircraft, the ATC tower, and other airfield operations. The Contractor shall be capable of removing all lighting equipment from the runway within 20 minutes of notification of an emergency. Night work must be coordinated with the Airfield Manager and approved in advance by the CO or authorized representative. The Government reserves the right to accept or reject night work on the day following night activities by the Contractor.

2.2. MATERIALS

2.2.1. Paint: The paint shall be homogeneous, easily stirred to smooth consistency, and shall show no hard settlement or other objectionable characteristics during a storage period of 6 months. Paints for airfields shall conform to FS TT-P-1952E, color as indicated. Pavement marking paints shall comply with applicable state and local laws enacted to ensure compliance with Federal Clean Air Standards. Paint materials shall conform to the restrictions of the local Air Pollution Control District.

Color of markings are indicated on the drawings and must conform to FED-STD-595 for airfields.

Provide materials conforming to the requirements specified herein.

2.2.1. Reflective Media: Reflective media for airfields shall conform to FS TT-B-1325D, Type I, Low Index of Refraction, Gradation A (Course, Drop-on) or Type III, High Index of Refraction, Drop-on.

2.3. SAMPLING AND TESTING

Materials proposed for use shall be stored on the project site in sealed and labeled containers, or segregated at source of supply, sufficiently in advance of needs to allow 60 days for testing. Upon notification by the Contractor that the material is at the site or source of supply, a sample shall be taken by random selection from sealed containers in the presence of the Contracting Officer. Samples shall be clearly identified by designated name, specification number, batch number, manufacturer's formulation number, project contract number, intended use, and quantity involved. Testing shall be performed in an

FA4620-17-R-B001

SECTION 32 17 23 - PAVEMENT MARKINGS Page 5 of 10 approved independent laboratory. If materials are approved based on reports furnished by the Contractor, samples will be retained by the Government for possible future testing should the material appear defective during or after application.

2.4. GOVERNMENT FURNISHED MATERIALS AND EQUIPMENT

2.4.1. Communications Equipment: The Government will furnish radios to the Contractor for communication with Air Traffic Control (ATC) during each work day. Radios will only be required for work in the CMA (runway and the helicopter landing area -if the helicopter landing pad is not closed). Closure of the helicopter landing pad may be obtained if requested in advance. The Contractor will be provided radios with the proper frequencies (obtained from the Construction Manager at the pre-performance conference).

2.4.2. Water: Water will be furnished at no cost to the Contractor from a fire hydrant designated by the CO or authorized representative and located within a reasonable proximity to the work area. The Contractor shall install a gate valve and a Washington State approved, double back-flow prevention device on the fire hydrant tap. The Contractor shall furnish all equipment, material, and labor required to obtain and deliver water from the designated fire hydrant to the work area(s).

PART 3 EXECUTION

3.1. WORK AREA PREPARATION

3.1.1. Work Zones: The Contractor shall establish and maintain work zones as necessary throughout the period of the contract, prominently identifying potential hazards and dangers to personnel and traffic in or near the work area. Work has been accomplished in the past using coordination with the Airfield Manager and by providing traffic control thus eliminating the requirement for physical barriers. The Contractor shall provide coordination with the Airfield Manager to insure that the Contractor’s work activities do not interfere with aircraft traffic. The Contractor shall provide all temporary markings and traffic controls necessary to establish a safe and adequate work zone and to minimize airfield interruptions. Markings and controls must comply with the requirements of paragraph 3.8.

3.1.1.1. As a minimum, the Contractor shall comply with AFI 32-1042, ETL 04-2, AFI 32-1044, and FAA AC 150/5370-2 for temporary pavement closures on airfields. Work on the helicopter landing pad must be scheduled ahead of time so that a NOTAM can be issued to close the landing pad.

3.1.2. Surfaces.

3.1.2.1. Surface Inspection. Before marking begins, the Contractor shall inspect each general work area to determine the extent of cleaning required, document the results of the inspection, and clean each area as described below.

3.1.2.2. Surface Cleaning.

a. Removal of Surface Contamination. The Contractor shall use a solution of trisodium phosphate or other approved detergent or degreaser to clean pavement areas (such as intersections and parking lots, maintenance aprons, engine run-up areas, blast pads, and the threshold and rotation area of the runway) that reveal signs of surface contamination by fuel, FA4620-17-R-B001

SECTION 32 17 23 - PAVEMENT MARKINGS Page 6 of 10 oil, hydraulic fluid, or other contaminants that could inhibit the bond between the paint and the pavement. After cleaning, the area shall be thoroughly rinsed. The Contractor shall remove all curing compounds from rigid pavements by water blasting.

b. Cleaning Existing Markings. The Contractor shall clean the existing areas that are to be remarked and remove any loose or poorly bonded paint that would inhibit adhesion of the new marking to the pavement surface. Paint that is intact and bonded to the pavement does not have to be removed. The Contractor shall remove dust, dirt, peeling or poorly bonded paint, and granular surface deposits from all other pavement areas by sweeping, blowing with compressed air, and/or rinsing with pressurized water. Any areas exposed to rain or traffic after cleaning shall be cleaned again before marking. Some of the areas with flaking paint are designated for complete removal each year. There will still be some other areas with existing loose paint; power-brush these areas removing only the readily removable paint. Full removal and repainting will take place in another year.

c. Testing for Moisture. Pavement markings shall be applied to dry pavement only. The Contractor shall test the pavement surface for moisture before beginning work after each period of rainfall, fog, high humidity, or cleaning, or when the ambient temperature has fallen below the dew point. Do not commence marking until the pavement is sufficiently dry and the pavement condition has been approved by the CO or authorized representative. Employ the “plastic wrap method” to test the pavement for moisture as follows: Cover the pavement with a 300 mm by 300 mm (12 inch by 12 inch) section of clear plastic wrap and seal the edges with tape. After 15 minutes, examine the plastic wrap for any visible moisture accumulation inside the plastic. Do not begin marking operations until the test can be performed with no visible moisture accumulation inside the plastic wrap.

3.2. TEST STRIPE DEMONSTRATION

Before beginning work, the Contractor shall mark test stripes within the work area to demonstrate the proposed materials and equipment to be used for the contract. Apply separate test stripes in each of the line widths and configurations (for both paint and thermoplastic markings) required in the contract, using the equipment proposed for the contract. Mark the test stripes long enough to determine the proper speed and operating pressures for the vehicle(s) and machinery, but not less than 15 meters (50 feet) long.

3.2.1. Surface Preparation Demonstration: Prior to surface preparation, demonstrate the proposed procedures and equipment. Prepare areas large enough to determine cleanliness, adhesion of remaining coating, and rate of cleaning. Perform a demonstration removal of pavement marking in an area designated by the Contracting Officer.

3.2.2. Demonstration of Application Rates: In applying the test stripes, the Contractor shall demonstrate the ability to comply with the application rates specified in paragraph 3.5.1.1. Document the equipment speed and operating pressures required to meet the specified rates in each configuration of the equipment and provide a copy of the documentation to the CO or authorized representative before proceeding with the work.

3.2.3. Demonstration of Retroreflective Values: After the test stripes have cured to a “no-track” condition, the Contractor shall demonstrate compliance with the average retroreflective values specified in paragraph 3.5.2. Take a minimum of ten readings on each test stripe with a Mirolux 12 Retroreflectometer, or similar instrument with the same measuring geometry and direct readout in millicandelas per square meter per lux (mcd/m2/lx).

3.2.4. Demonstration of Level of Performance: The CO or authorized representative will be present at the test area to observe the result obtained on the test stripe and validate the operating parameters of

FA4620-17-R-B001

SECTION 32 17 23 - PAVEMENT MARKINGS Page 7 of 10 the vehicle(s) and equipment. The application of test stripes shall be used to determine if the proposed methods and equipment can achieve the level of performance required for the contract. If accepted by the CO or authorized representative, the test stripe shall be the measure of performance required of the Contractor for the marking project. The Contractor shall not proceed with the work until the results of the test stripes are satisfactory to the CO or authorized representative.

3.3. ENVIRONMENTAL LIMITATIONS

Pavement marking will be suspended when wind conditions interfere with uniform application of pavement marking materials. Pavements shall be marked only when both the pavement surface and air temperature are at least 7 degrees C (45 degrees F) and rising, and the pavement surface temperature is at least 2.7 degrees C (5 degrees F) above the dew point. Pavement marking must be suspended during rain or when the pavement surface is wet. Before resuming work, test the pavement surface for excess moisture using the plastic-wrap method described in paragraph 3.1.2.1.c. The Contractor shall clean debris from the runway surface as the work proceeds.

3.4. SURFACE PREPARATION

Thoroughly clean surfaces to be marked before application of the pavement marking material. Dust, dirt, and other granular surface deposits shall be removed by sweeping, blowing with compressed air, rinsing with water or a combination of these methods as required. Rubber deposits, surface laitance, existing paint markings, and other coatings adhering to the pavement shall be completely removed with scrapers, wire brushes, sandblasting, approved chemicals, or mechanical abrasion when directed. Areas of pavement affected with oil or grease shall be scrubbed with several applications of trisodium phosphate solution or other approved detergent or degreaser, and rinsed thoroughly after each application.

Whenever grinding, scraping, sandblasting or other operations are performed the work must be conducted in such a manner that the finished pavement surface is not damaged or left in a pattern that is misleading or confusing. When these operations are completed the pavement surface shall be blown off with compressed air to remove residue and debris resulting from the cleaning work. Pavement surfaces shall be allowed to dry, when water is used for cleaning, prior to striping or marking.

3.5. APPLICATION

All pavement markings and patterns shall be placed as shown on the plans.

3.5.1. Paint: Paint shall be applied to clean, dry surfaces, and only when air and pavement temperatures are above 40 degrees F and less than 95 degrees F. Paint temperature shall be maintained within these same limits. New asphalt pavement surfaces and new Portland concrete cement shall be allowed to cure for a period of not less than 30 days before applications of paint.

Paint shall be applied pneumatically with approved equipment at rate of coverage specified. Provide guide lines and templates as necessary to control paint application. Special precautions shall be taken in marking numbers, letters, and symbols. Edges of markings shall be sharply outlined.

3.5.1.1. Rate of Application

a. Nonreflective Markings: Paint shall be applied evenly to the pavement surface to be coated at a rate of 0.310 to 0.360 millimeters (12 to 14 mils) wet film to cover 3 square meters, 0.15 square meters, per liter (121 plus or minus 6 square feet per gallon).

b. Reflective Markings: Paint shall be applied and glass spheres shall be applied uniformly to the wet paint on airfield pavement at the rates provided in Table I.

FA4620-17-R-B001

SECTION 32 17 23 - PAVEMENT MARKINGS Page 8 of 10

TABLE I

Bead Type Paint Type Paint Application Rate Bead Application Rate

Type I (Gradation A)

Type I, II, III 121 plus or minus 6 Sq Ft/Gallon

8 plus or minus 1 lb/gallon

Type III Type I, II, III 121 plus or minus 6 Sq Ft/Gallon

10 plus or minus 1 lb/gallon

3.5.1.2. Drying: The maximum drying time requirements of the paint specifications shall be strictly enforced to prevent undue softening of bitumen, and pickup, displacement, or discoloration by tires of traffic. If there is a delay in drying of the markings, painting operations shall be discontinued until cause of the slow drying is determined and corrected.

3.5.2. Reflective Media: Application of reflective media shall immediately follow paint application.

Drop-on application of glass spheres shall be accomplished to insure that reflective media is evenly distributed at the specified rate of coverage. Should there be malfunction of either paint applicator or reflective media dispenser, operations shall be discontinued immediately until deficiency is corrected.

3.5.2.1. Retroreflectivity Levels: The Contractor shall collect and record readings for white and yellow retroreflective markings to ensure they provide a reasonable level of retroreflectivity for night operations. The minimum acceptable average for white markings will be 200 millicandelas per square meter per lux (mcd/m2/lx) (measured with Mirolux 12 Retroreflectometer). The minimum acceptable average for yellow markings will be 175 millicandelas per square meter per lux (mcd/m2/lx). The Contractor shall document a retroreflectivity reading for each 300 linear meters (1000 linear feet) marked. The reading shall be computed by averaging a minimum of 10 readings taken within the area at random locations. Areas not meeting the retroreflective requirements stated above shall be re-marked at the Contractor’s expense. Testing is not required if the reflective beads are certified per paragraph 2.2 and approved in the submittal process, and the application rates are ensured per paragraph 3.2.1.1.a.

3.5.3. Placement of Markings: The Contractor shall ensure that all markings are installed properly and placed in strict compliance with this specification and the contract drawings. The longitudinal edges of markings shall not vary from a straight line by more than 25 millimeters (1 inch) per 15 meters (50 feet). The overall dimensions of the markings shall not vary from the drawings by more than 5 percent. All stripes must touch provide a clean edge, not appear blocked. When restarting a stripe or line it must match in width, not appear blocked. Yellow lines must touch black lines the entire length and width, red lines must touch while lines the entire length and width no gaps in either sets of colors. Any markings that are improperly placed or fail to meet the requirements of this specification, including placement, retroreflectivity, and final color, shall be removed and reinstalled at the Contractor’s expense. Materials used for repairs shall be from the same lot and batch as those approved for the performance of the contract or shall be subjected to the same requirements and approved by the CO or authorized representative prior to beginning repairs.

3.5.4. Cleanup and Waste Disposal: Keep the worksite clean and free of debris and waste from the removal and application operations. Immediately cleanup following removal operations in areas subject to aircraft traffic. Dispose of debris at approved sites.

3.6. FIELD QUALITY CONTROL

3.6.1. Sampling and Testing: As soon as the paint materials and reflective media are available for

FA4620-17-R-B001

SECTION 32 17 23 - PAVEMENT MARKINGS Page 9 of 10 sampling, obtain by random selection from the sealed containers, two quart samples of each batch in the presence of the Contracting Officer. Accomplish adequate mixing prior to sampling to ensure a uniform, representative sample. A batch is defined as that quantity of material processed by the manufacturer at one time and identified by number on the label. Clearly identify samples by designated name, specification number, batch number, project contract number, intended use, and quantity involved. Test samples by an approved laboratory. If a sample fails to meet specification, replace the material in the area represented by the samples and retest the replacement material as specified above. Submit certified copies of the test reports, prior to the use of the materials at the jobsite. Include in the report of test results a listing of any specification requirements not verified by the test laboratory.

3.6.2. Material Inspection: Examine material at the job site to determine that it is the material referenced in the report of test results or certificate of compliance. A certificate of compliance shall be accompanied by test results substantiating conformance to the specified requirements.

3.6.3. Dimensional Tolerances: Apply all markings in the standard dimensions provide in the drawings. New markings may deviate a maximum of 10 percent larger than the standard dimension.

The maximum deviation allowed when painting over an old marking is up to 20 percent larger than the standard dimensions.

3.6.4. Bond Failure Verification: Inspect newly applied markings for signs of bond failure based on visual inspection and comparison to results from Test Stripe Demonstration paragraph.

3.6.5. Reflective Media and Coating Application Verification: Use a wet film thickness gauge to measure the application of wet paint. Use a microscope or magnifying glass to evaluate the embedment of glass beads in the paint. Verify the glass bead embedment with approximately 50 percent of the individual bead spheres embedded and 50 percent of the individual bead spheres exposed.

3.6.6. Retroreflective Markings: Collect and record readings for white and yellow retroreflective markings at the rate of one reading per 305 linear m 1000 linear feet. The minimum acceptable average for white markings is 200 millicandelas per square meter per lux (mcd/m2/lx) (measured with Retroreflectometer). The minimum acceptable average for yellow markings is 175 millicandelas per square meter per lux (mcd/m2/lx). Compute readings by averaging a minimum of 10 readings taken within the area at random locations. Re-mark areas not meeting the retroreflective requirements stated above.

3.6.7. Material Bond Verification and Operations Area Cleanup for Airfields: Vacuum sweep the aircraft operating area before it is opened for aircraft operations to preclude potential foreign object damaged to aircraft engines. Visually inspect the pavement markings and the material captured by the vacuum. Verify that no significant loss of reflective media has occurred to the pavement marking due to the vacuum cleaning.

3.7. MARKING REMOVAL

Pavement marking, including plastic tape, shall be removed in the areas shown on the drawings.

Removal of marking shall be as complete as possible without damage to the surface. Aggregate shall not be exposed by the removal process. After the markings are removed, the cleaned pavement surfaces shall exhibit adequate texture for remarking as specified in paragraph 3.4 SURFACE PREPARATION.

Demonstrate removal of pavement marking in an area designated by the Contracting Officer. The demonstration area will become the standard for the remainder of the work.

3.7.1. Cleanup and Waste Disposal: The worksite shall be kept clean of debris and waste from the

FA4620-17-R-B001

SECTION 32 17 23 - PAVEMENT MARKINGS Page 10 of 10 removal operations. Cleanup shall immediately follow removal operations in areas subject to air traffic. Debris shall be disposed of at approved sites.

3.8. DAMAGE REPAIR AND CLEANUP

3.8.1. Protection and Cleanup: The Contractor shall protect all areas of pavement adjacent to the work area from splatter, splash, spills, and drips. Any disfigurement shall be removed by the Contractor at the Contractor’s expense. The Contractor shall remove completely all improperly placed or improperly applied markings and disfigurements without damage to the pavement, joints, and joint and crack seals. Obliterating the markings with paint will not be allowed unless the removal process leaves marking patterns that could mislead or confuse pilots or motorists. The Contractor and the CO or authorized representative shall jointly inspect the work area before marking operations commence.

During this inspection, proper layout of new markings shall be verified and existing damage to the pavement systems, joints, and joint and crack seals shall be documented.

3.8.2. Pavement Damage Repair: The Contractor shall repair any damage to the pavement system, joints, joint and crack seals, or other Government property resulting from pavement marking. Repairs shall be made at the Contractor’s expense using materials and methods approved by the CO or authorized representative and shall be completed within the contract performance period.

3.8.3. Excess Materials: Unused paint and beads shall remain the property of the Contractor and shall be recycled or disposed off base.

3.9. METHOD OF OPERATION AND EXECUTION

3.9.1. Safety: The Contractor shall conduct all marking operations in strict compliance with all local, state, and Federal environmental statutes and regulations, including, but not limited to, regulations promulgated under 29 C.F.R. 1910, et seq., 42 U.S.C. 6901, et seq.; and 42 U.S.C. 9601, et seq.

3.9.2. Traffic Controls: The Contractor shall provide all cones, barriers, lights, signs, placards, flags, and flagging personnel necessary to establish an adequate and safe work zone and control traffic in and around the work area until newly applied markings are dry. The Contractor shall establish and maintain work zones as necessary throughout the period of the contract, prominently identifying potential hazards and dangers to personnel and traffic in or near the work area. As a minimum, the Contractor shall comply with the provisions of AFI 32-1042, ETL 04-2, AFI 32-1044 and FAA AC 150/5370-2 for temporary pavement closures on airfields.

3.9.3. Environmental Regulations: The Contractor shall remove all debris, waste, spillage, and by-products generated by the marking operations from the base and shall strictly comply with all applicable state, local, and Federal environmental statutes and regulations regarding disposal, including, but not limited to, regulations promulgated under 42 U.S.C. 6901, et seq.; 42 U.S.C. 9601, et seq.; and 49 U.S.C. 1801, et seq.

3.9.4. Airfield Coordination: The performance of work in the CMAs shall be coordinated with the CO and Airfield Manager. Verbal communications shall be maintained with ATC before and during work in the controlled movement areas. ATC shall be advised when the work is completed. A radio for this purpose shall be provided to the Contractor by the CO.

-- END OF SECTION 32 17 23--