| A. | Project Title: MACC (Multiple Aw ard Construction Contract) Indefinite Delivery/Indefinite Quantity. |
| B. | Government anticipates up to 5 aw ards. This acquisition is a Total Small Business Set-Aside. |
| C. | All quesitons must be submitted NLT 10 days prior to RFP closing date. |
| D. | Project Performance Period: One (1) Base Year and four (4) Option Years. |
| E. | Enter prices on Attachment 1A, Price Schedule |
| F. | Bid Bond required-see Section I, FAR 52.228-1 & Section C, Para 1.19. Bonding Capacity: $10M. |
| G. | Reference Section L, “Instructions, Conditions, and Notices to Offerors or Respondents” and Seciton M “Evaluation Factors for Aw ard,” for |
proper proposal preparation.
H. Guaranteed minimum amount w ill be met via contractor’s participation in Seminar Orientation, Task Order 001, for $500.00. Reference Section C, Paragraph 1.2. Total aggregate maximum amount expendable under all MACC contracts aw arded shall not exceed $95 million.
| I. | Pre-Proposal conference w ill be held 20 Feb 17 at 9:00 AM (PDT), to include Seed Project site visit. |
| J. | Sections K, L, and M w ill not be part of any resultant contract. |
| K. | Past Performance is due by 15 Mar 17. |
| L. | Magnitude of Seed Project is betw een $250,000.00 and $500,000.00. |
| M. | NAICS code is 236 & 237. SB size standard is $36.5M |
PAUL C. BLAIS 509-247-4864
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
24-Feb-2017
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
X
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______ calendar days and complete it w ithin ________ calendar days after receiving aw ard, notice to proceed. This performance period is X mandatory, negotiable. (See _________________________Section F
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________27 Mar 2017 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______150 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
92 CONTRACTING SQUADRON
BLDG 2451
110 W ENT ST
STE 200
FAIRCHILD AFB WA 99011-8568
FA4620
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
04:00 PM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
509-247-8685FAX:TEL: 509-247-2161 TEL: FAX:
FA4620-17-R-B001 68
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
FA4620-17-R-B001
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
Basic Year (11 May 17 to 10 May 18)
FFP
FFP - MACC is a multiple award, competitive construction acquisition based on a general statement of work further defined within each individual task order. The work will consist of multiple disciplines in design and construction to include maintenance, repair, and alteration of real property as well as new construction of facilities supported by Fairchild AFB, Washington.
FOB: Destination
NSN: Z2JZ-17-NEW-MACC
SIGNAL CODE: A
NET AMT
OPTION Option Year 1 (11 May 18 to 10 May 19)
FFP
FFP - MACC is a multiple award, competitive construction acquisition based on a general statement of work further defined within each individual task order. The work will consist of multiple disciplines in design and construction to include maintenance, repair, and alteration of real property as well as new construction of facilities supported by Fairchild AFB, Washington.
FOB: Destination
OPTION Option Year 2 (11 May 19 to 10 May 20)
FFP
FFP - MACC is a multiple award, competitive construction acquisition based on a general statement of work further defined within each individual task order. The work will consist of multiple disciplines in design and construction to include maintenance, repair, and alteration of real property as well as new construction of facilities supported by Fairchild AFB, Washington.
FOB: Destination
OPTION Option Year 3 (11 May 20 to 10 May 21)
FFP
FFP - MACC is a multiple award, competitive construction acquisition based on a general statement of work further defined within each individual task order. The work will consist of multiple disciplines in design and construction to include maintenance, repair, and alteration of real property as well as new construction of facilities supported by Fairchild AFB, Washington.
FOB: Destination
OPTION Option Year 4 (11 May 21 to 10 May 22)
FFP
FFP - MACC is a multiple award, competitive construction acquisition based on a general statement of work further defined within each individual task order. The work will consist of multiple disciplines in design and construction to include maintenance, repair, and alteration of real property as well as new construction of facilities supported by Fairchild AFB, Washington.
FOB: Destination
SECTION B NOTE
NOTE: Prices are not required in this section. Prices will be requested for each Task Order. Seed project price schedule is located in Attachment 1A, Price Schedule, of this solicitaiton.
CLIN DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND CLIN ORDER VALUE
The minimum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not exceed the maximum quantity and order value stated in the following table.
CLIN
MINIMUM
QUANTITY
MINIMUM
AMOUNT
MAXIMUM
QUANTITY
MAXIMUM
AMOUNT
0001 1.00
$500.00
1,000,000.00
$95,000,000.00
0002 1.00
0003 1.00
0004 1.00
0005 1.00
Section C - Additional Specifications
1.1 MINIMUM/ MAXIMUM CONTRACT AMOUNTS
The contract minimum guarantee is met by award of a MACC Orientation Seminar Task Order for each MACC contract awarded, applicable to the base year of performance only. The MACC Orientation Seminar task order is firm-fixed price with a value of $500.00. The Government makes no representation as to the number of Task Orders or actual amount of work to be ordered in excess of the minimum guarantees specified herein. The maximum aggregate amount of the MACC program, inclusive of all awarded MACC contracts and task orders, including options, shall not exceed $95,000,000.
1.2 MACC ORIENTATION SEMINAR
MACC contractors shall attend and participate in a 1-day MACC Program Orientation Seminar at Fairchild AFB. The seminar shall provide a contract overview covering several program requirements and procedures to include partnering, contract administration, design/engineering perspectives, quality control program, security/base access processes, construction management processes and site specifics associated with each base. Attendance is mandatory.
It will be up to the Contractors to determine which members of their team attend. It is highly encouraged that key team members attend that are intimately involved with design/build, superintendence, quality control and program/project management. An initial task order under each contract will be issued for this requirement not to exceed $500.00. The Government will not be liable for any costs that contractors incur in attending the seminar that exceed the task order amount. The MACC Orientation Seminar task order will satisfy each contract guaranteed minimum. Reference Attachment 5 - SOW for Task Order 0001.
1.3 COMMENCEMENT OF WORK
No work under this contract will commence until such time as the Contracting Officer issues a written Task Order and Notice to Proceed under the Task Order.
1.4 PLACE OF PERFORMANCE
Locations of work will be at Fairchild AFB, WA and other associated sites outside the base proper. All off base sites are within 80 miles of Fairchild AFB (e.g. Survival School off base sites, JPRA training academy). The place of performance will be designated on each individual Task Order.
1.5 PROPOSAL PREPARATION COSTS
The costs for preparation of Task Order proposals shall be the responsibility of the contractor and not directly reimbursable. Each Task Order awarded will include at a minimum all labor wages, management, supervision, mobilization, material and equipment costs, and any costs associated with any required design effort. The contractor shall furnish all project management, planning, estimating, labor, transportation, materials, equipment, tools, supervision, design if applicable, and all other associated costs necessary to fulfill the requirements of the Task Order.
1.6 REQUIRED INSURANCE (IAW FAR 28.306(b)(1))
Reference FAR 52.228-5,"Insurance – Work on a Government Installation" (Jan 1997): the Contractor shall, at its own expense, procure and thereafter maintain the following kinds of insurance with respect to performance under the contract.
(a) Workmen's Compensation and Employers Liability Insurance as required by law except that if this contract is to be performed in a State which does not require or permit private insurance, then compliance with the statutory or administrative requirements in any such State will be satisfactory. The required Workmen's Compensation insurance shall extend to cover employer's liability for accidental bodily injury or death and for occupational disease with a minimum liability limit of $100,000.
(b) General Liability Insurance. Bodily injury liability insurance, in the minimum limits of $500,000 per occurrence shall be required on the comprehensive form of policy.
(c) Automobile Liability Insurance. This insurance shall be required on the comprehensive form of policy and shall provide bodily injury liability and property damage liability covering the operation of all automobiles used in connection with the performance of the contract. At least the minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage shall be required.
(d) The contractor agrees to execute an insurance certificate with the Contracting Office in accordance with Section H, “Required Insurance.” This certificate shall be executed on the form entitled “Acknowledgement and Certification of Compliance with Contract Insurance Requirements”, and be provided upon award of a basic MACC contract.
1.7 DAVIS BACON WAGE DETERMINATION
Individual task orders will be subject to one or more of the applicable Wage Determinations as the work dictates at the time of contract award (see Section J, Attachments).
Upon exercise of an option period, the most current wage determinations will be incorporated, and contractors will be required to comply with the revised wages on future Task Orders. See FAR Clause 52.222-30, “Davis-Bacon Act – Price Adjustment (None or Separately Specified Method)” in Section I, “Contract Clauses.”
1.8 NOTICE OF CONSTRUCTIVE CHANGES
No order, statement or direction of the Contracting Officer, an authorized representative of the Contracting Officer whether or not acting within the limits of his authority, or any other representatives of the Government, shall constitute a change order under the “Changes” clause of this contract or entitle the contractor(s) to an equitable adjustment of the price or delivery schedule, unless such a change is issued in writing and signed by the Contracting Officer.
1.9 PRE-DESIGN AND/OR PRE-CONSTRUCTION CONFERENCE
Prior to commencing work under a Task Order, the Contractor shall meet with the Contracting Officer and/or designated technical personnel at a mutually agreeable time to discuss and develop mutual understandings concerning schedule and administering work.
1.10 PARTNERING
Partnering is a structured process, as well as a philosophy of doing business with contractors and customers, that recognizes common goals through communication and teamwork. It helps create an environment where trust and teamwork prevents disputes, fosters good working relationships to everyone’s benefit, and facilitates the completion of a successful contract. In support of the command’s goals of teamwork and customer satisfaction, our policy is to practice the philosophy of Partnering on every contract we administer. The contractor’s key personnel may be required to attend formal partnering meetings for the basic contract at the expense of the contractor. In addition, formal partnering may be required prior to and/or during performance of an individual Task Order, if determined necessary by the Government. Partnering shall be held during normal work hours.
1.11 PERFORMANCE EVALUATIONS
At the conclusion of each Task Order, the Contracting Office will complete a contractor’s performance evaluation and input into the Contractor Performance Assessment Reporting System (CPARS). The evaluation will take into account all aspects of the contractor’s performance. Performance evaluations may be completed at any time the Contractor’s performance is considered less than satisfactory. Contractors are required to obtain PKI certificates and register at the CPARS web site (www.cpars.gov). Performance evaluations will be provided electronically through CPARS and contractors will be afforded an opportunity to review and respond to performance evaluations through CPARS. After considering input from the contractor, the Contracting Officer makes the final determination on ratings for all performance evaluations. The performance evaluations may have an impact on the award of future contracts.
1.12 PAYMENT FOR MATERIALS STORED ON SITE
(a) This clause implements, but does not replace, FAR 52.232-5 (May 2014), Payments Under Fixed-Price
Construction Contracts, with regard to material payments.
(b) Consideration for payment under this contract for materials stored on site is subject to the following conditions:
http://www.cpars.gov/
(1) The contractor shall furnish the contracting officer a list of the major high-cost items to be incorporated into the contract and for which payment, prior to installation, will be requested. Those items approved by the contracting officer will be entered on the AF Form 3064, Contract Progress Schedule, as a percentage factor, or factors if items are listed individually.
(2) Payment is limited to major high-cost items. Payment of major high-cost items does not include contractor overhead and profit. Costs such as sales tax, freight, handling, pallets, etc., are excluded.
(3) Payment requests shall be consistent with approved material submittals and shall be supported by the following documents:
a) Certified paid vendor invoices
b) Inventory checklists, jointly validated by the contractor, contracting personnel, and/or construction inspector.
c) Accepted delivery tickets, if applicable.
(4) All material for which payment is requested shall be delivered to an approved location on-site, and certified that none will be removed without written permission of the contracting officer. Materials may also be stored in a bonded warehouse offsite if no adequate storage space is available on base.
(5) Payments will be made monthly, or at more frequent intervals as determined by the contracting officer.
(6) The contractor shall remain responsible and retain title to the materials until incorporated into the work.
1.13 GOVERNMENT FURNISHED PROPERTY
Government Furnished Property is not anticipated.
1.14 TASK ORDER ISSUANCE PROCEDURES
(a) Work under this contract will be ordered by written Task Orders issued on DD Form 1155 (Order for Supplies or
Services) to the contractor by the Contracting Officer.
(b) Each award as a result of this solicitation will cite an individual task order number. Individual Task Orders will be placed in a sequential numbering system, which relate back to the basic contract and their assigned Task Order Number.
(c) The Government will not be obligated to reimburse the contractor for work performed, items delivered, or any costs incurred, nor shall the contractor be obligated to perform, deliver, or otherwise incur costs except as authorized by duly executed Task Orders. Requests for proposals will indicate funds availability. The government may request proposals with no assurance of funding and provides no assurance that task orders will be issued.
(d) Task Orders will be firm fixed price and clearly define the specific work required or the performance desired.
Each Task Order may contain additional, site or project specific, provisions. Any such additional provisions shall be a part of the Request for Proposal.
(e) Task Order projects may include complex performance oriented tasks requiring design development for design-build construction, may be construction or government provided design, or a combination thereof. The Task Order may or may not have traditional plans and specifications but may include sketches, and requests for catalog cuts, and other submittals. The ordering procedures are defined in the basic MACC Specifications at Attachment 6.
(f) Task Orders may be modified by the Contracting Officer. Modifications to task orders will be issued on Standard Form (SF) 30 and cite the Task Order Number.
(g) Submission of proposals for Task Orders is not required. However, contractors are required to contact the Contracting Officer within two days after receipt of Task Order Request for Proposal (TORFP) if a contractor will not participate in the walk through or submit a proposal on a Task Order. Repeated non-submission may be grounds for the Contracting Officer to not execute the contract option for the following year.
1.15 DESCRIPTION OF SUBSEQUENT TASK ORDERS
Task Orders will normally range from $600K to $10M, with most Task Orders falling in the range of $1M to $5M.
Task Order projects may require either a single discipline or multidiscipline design services for airfield pavement or all aspects of general building construction for new, renovation and addition-type projects. Projects may also require comprehensive interior design, lead and asbestos abatement and incorporation of sustainable features. Some projects may require only minimal design.
1.16 SUBSEQUENT TASK ORDER EVALUATION CRITERIA
Subsequent Task Orders may be awarded on price, past performance, best value, performance price tradeoff process or low price, technically acceptable basis. If the Government decides to issue the Task Order as a best value using the tradeoff process, award factors will vary depending on the unique requirements of each Task Order. The following sample criteria may be evaluated, in addition to price or cost:
(a) Past Performance - Task Order past performance or prior past performance on other contracts
(b) Quality of Deliverables
(c) Ability to Meet Schedule Requirements
(d) Relevant Experience
(e) Cost Control
(f) Potential impact on other orders placed with the contractor
(g) Current workload
(h) Design
(i) The contractor’s technical understanding of the work.
(j) The most efficient and effective plan to accomplish the work.
(k) Rationale for proposed materials, type and quantities.
(l) Sustainable design features
1.17 COMPETITION
Occasionally, (generally during the last quarter of the fiscal year), the government will solicit offers for projects for which funds are not certified or readily available. AMC refers to these acquisitions as “Special Advance Authority” or “SAA” projects. The contracting officer may solicit offers from MACC awardees or other sources. Submission of proposals for these acquisitions is at the sole discretion of the respective MACC awardees and their declination to participate in any or all such solicitations will not reflect negatively upon them.
(a) Only the contractors awarded contracts as a result of this RFP will compete for subsequent Task Orders. These contractors are encouraged to participate in all site visits and submit proposals. Failure by offerors to participate responsibly in site visits and submit proposals may result in the Government not exercising the option to extend the contract or exclusion of the contractor from further competition.
(b) As imposed by 10 U.S.C. 2306(d) and 41 U.S.C. 254(b), note that for those task orders [excluding Non-appropriated Funds (NAF) task orders] requiring design effort (i.e. design-build), the contracting officer is restricted from negotiating a price for fee for the production and delivery of designs, plans, drawings, and specifications exceeding 6% of the estimated cost of construction.
(c) A minimum of two proposals on Task Orders will satisfy competition requirements and preclude the necessity of soliciting for a replacement contractor if for any reason one of the contracts is terminated or one of the contractors is excluded from participation in the process.
(d) Unless the Contracting Officer applies the exceptions noted below, each Task Order will be awarded, as a result of competition to the contractor who offers the best value to the Government considering the criteria specified.
The Contracting Officer’s decision as to the selection for award of a Task Order may not be protested unless the protest is on the grounds that the order increases the scope, period, or maximum value of the contract program.
(e) The Contracting Officer reserves the right to award a Task Order without competition based upon a determination that:
(1) The agency need for the supplies or services are so urgent that providing a fair opportunity would result in unacceptable delays;
(2) Only one awardee is capable of providing the supplies or services required at the level of quality required because the supplies or services being ordered are unique or highly specialized.
(3) The order must be issued on a sole-source basis in the interest of economy and efficiency as a logical follow-on to an order already issued under the contract, provided that all awardees were given a fair opportunity to be considered for the original order.
(4) In accordance with section 1331 of Public Law 111-240 (15 U.S.C. 644(r)), contracting officers may, at their discretion, set aside orders for any of the small business concerns identified in FAR 19.000(a)(3). When setting aside orders for small business concerns, the specific small business program eligibility requirements identified in FAR Part 19 apply.
1.18 PERFORMANCE AND PAYMENT BONDS – APPLICABLE TO INDIVIDUAL TASK ORDERS
Contractor shall furnish Performance and Payment Bonds (Standard Form 25/25A) with good and sufficient surety or sureties, acceptable to the Government. A list of the certified companies can be found on the Department of the Treasury's Listing of Approved Sureties (http://www.fms.treas.gov/c570/c570.html). The penal sums of the bond will be as shown below. A notice to proceed shall not be issued and no work shall begin until good and sufficient surety, as identified below has been received and accepted by the Contracting Officer.
(a) Performance Bond: Unless the Contracting Officer determines that a lesser amount is adequate for the protection of the Government, the penal sum of the performance bonds (Standard Form 25) shall equal one hundred percent (100%) of the contract price for each Task Order.
(b) Payment Bond:
(1) Shall equal 100% of the contract price for each Task Order.
(2) One of the following is required:
(i) A payment bond.
(ii) An irrevocable letter of credit (ILC).
(iii) A tripartite escrow agreement. The prime contractor establishes an escrow account in a federally insured financial institution and enters into a tripartite escrow agreement with the financial institution, as escrow agent, and all of the suppliers of labor and material. The escrow agreement shall establish the terms of payment under the contract and of resolution of disputes among the parties. The Government makes payments to the contractor's escrow account, and the escrow agent distributes the payments in accordance with the agreement, or triggers the disputes resolution procedures if required.
(iv) Certificates of Deposit. The contractor deposits certificates of deposit from a federally insured financial institution with the Contracting Officer, in an acceptable form, executable by the Contracting Officer.
(v) A deposit of the types of security listed in FAR 28.204-1 and 28.204-2.
(3) Bonds are due within 10 days of the receipt of the task order.
1.19 PROPOSAL GUARANTEE (BID BOND)
• SEED PROJECT: A bid bond is required for the seed project. Additionally, a letter from an acceptable surety is required indicating bonding capacity of at least $10 million.
• SUBSEQUENT TASK ORDERS: The requirement for a guarantee will be included in the TORFP.
Individual proposal guarantees of at least 20% of the proposed price may be required from all offerors competing for award of all subsequent Task Orders.
• Bid Bonds will only be waived at the discretion of the Contracting Officer.
1.20 REPLACING MACC CONTRACTORS
Should one or more of the incumbent MACC contractor’s options not be exercised, or if termination of contract(s) occurs, the process for selecting replacement contracts shall, if determined necessary, follow the same process and procedures as used in selecting and awarding the basic MACC awards.
1.21 ENVIRONMENTAL COMPLIANCE
Offerors are reminded of the environmental requirements contained in the solicitation to comply with all applicable federal state, and local environmental statutes and regulations. In addition to the scrutiny of civil environmental regulatory agencies, environmental compliance incidental to Air Force activities or on Air Force Property is subject to Air Force scrutiny. The Air Force routinely investigates environmental violations and compliance.
1.22 INSTALLATION RULES AND REGULATIONS
The rules and regulations of the installation where services are performed shall apply to the contractor and his employees while on the premises of such installation. These regulations included but are not limited to: presenting valid identification for base entrances (Real ID Attachment 10), obtaining and using vehicle passes for all contractor-owned and/or privately owned vehicles, ban on cell phone use in any form while driving to include texting, obeying all posted directives, and providing strict adherence to security police direction in instances where security police have been dispatched to a particular location.
1.23 UTILITY SERVICES (IAW FAR 36.514)
The Contractor will be required to participate in all Air Force energy conservation programs. Utility services furnished to the contractor by the Government from the Government’s existing system outlets and supplies will be at no cost to http://www.fms.treas.gov/c570/c570.html the Contractor, but see contract clause titled FAR 52.236-14, “Availability and Use of Utility Services,” in Section I, “Contract Clauses.”
1.24 SPECIAL UTILITY PROVISION
The contractor shall be responsible for any and all damages to accurately marked utilities resulting from its operations.
Further, the contractor shall be held liable for all costs associated with such damages. Such costs include not only the costs to properly repair the damaged utility, but any direct costs incurred by the government to provide emergency response to the site, as well as for any other monetary losses. Such loss may also include the value of loss of productivity experienced by the government due to loss of power and /or facility evacuation arising from the utility damage. Contractors are to field verify and mark location of utilities shown on construction permit.
1.25 DESIGNATION OF GOVERNMENT INSPECTOR
A Construction Manager from the base Civil Engineer Squadron will be designated as the Contracting Officer Representative (COR) for the purpose of performing Construction Contract Quality Assurance for the Government, which includes performing technical surveillance, monitoring workmanship, compliance with the plans and specification under this contract, and reporting in the CORT tool as required. This provision in no way authorizes anyone other than the Contracting Officer to commit the Government to changes in the terms of this contract.
1.26 PREPARATION OF SCHEDULES FOR CONSTRUCTION CONTRACTS
The reports contemplated by FAR Clause 52.236-15 titled "Schedules for Construction Contracts" in Section I shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, “Contract Progress Schedule,” and AF Form 3065, “Contract Progress Report” unless a network schedule is specifically requested.
1.27 PHYSICAL DATA/WEATHER CONDITIONS (SEE ATTACHMENT 9)
The Operational Climatic Data Summary is furnished for the contractor’s information. The Climatic Data shows the average weather pattern at Fairchild AFB WA. This chart will be used to evaluate any request for time extension due to unusually severe weather.
Section E - Inspection and Acceptance
FEDERAL HOLIDAYS
The following Federal legal holidays are observed by this base:
New Year’s Day January 1st Martin Luther King Day Third Monday in January Presidents Day Third Monday in February Memorial Day Last Monday in May Independence Day July 4th Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day November 11th Thanksgiving Day Fourth Thursday in November Christmas Day December 25th Holidays falling on a Saturday will be observed on the preceding Friday.
Holidays falling on a Sunday will be observed on the following Monday.
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A N/A Government 0002 N/A N/A N/A Government 0003 N/A N/A N/A Government 0004 N/A N/A N/A Government 0005 N/A N/A N/A Government
CLAUSES INCORPORATED BY REFERENCE
52.246-12 Inspection of Construction AUG 1996 52.246-13 Inspection--Dismantling, Demolition, or Removal of
Improvements
AUG 1996
Section F - Deliveries or Performance
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC
0001 POP 11-MAY-2017 TO
10-MAY-2018
N/A N/A
FOB: Destination
0002 POP 11-MAY-2018 TO
10-MAY-2019
0003 POP 11-MAY-2019 TO
10-MAY-2020
0004 POP 11-MAY-2020 TO
10-MAY-2021
0005 POP 11-MAY-2021 TO
10-MAY-2022
52.211-13 Time Extensions SEP 2000
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within as specified in each Task Order after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than as specified in the Task Order. The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of (as specified on each individual Task Order) for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
Section G - Contract Administration Data
1.1 REMITTANCE ADDRESS
If the remittance address is different from the mailing address, enter the remittance address below.
Failure to provide this information may impact payment.
1.2 ADMINISTRATIVE MATTERS
The address and telephone number for Construction Flight:
92d Contracting Squadron 110 West Ent Street Fairchild AFB WA 99011-8568
(509) 247-4867
1.3 CONTRACTOR’S CONTRACT ADMINISTRATION
To be completed by Contractor –
Name and Title:
Responsible Office:
Address:
Phone #:
E-mail:
CAGE Code:
DUNS #:
Tax Identification #:
1.4 INDIVIDUALS AUTHORIZED TO NEGOTIATE OR DISCUSS PROPOSAL
Primary: Alternate:
Phone #: Phone #:
Alternate Phone#:
Alternate Phone #:
Fax #: Fax #:
Email: Email:
CLAUSES INCORPORATED BY FULL TEXT
252.232-7003 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS AND RECEIVING REPORTS
(JUNE 2012)
(a) Definitions. As used in this clause–
(1) Contract financing payment and invoice payment have the meanings given in section 32.001 of the Federal Acquisition Regulation.
(2) Electronic form means any automated system that transmits information electronically from the initiating system to all affected systems. Facsimile, e-mail, and scanned documents are not acceptable electronic forms for submission of payment requests. However, scanned documents are acceptable when they are part of a submission of a payment request made using Wide Area WorkFlow (WAWF) or another electronic form authorized by the Contracting Officer.
(3) Payment request means any request for contract financing payment or invoice payment submitted by the Contractor under this contract.
(4) Receiving report means the data required by the clause at 252.246-7000, Material Inspection and Receiving Report.
(b) Except as provided in paragraph (c) of this clause, the Contractor shall submit payment requests and receiving reports using WAWF, in one of the following electronic formats that WAWF accepts: Electronic Data Interchange, Secure File Transfer Protocol, or World Wide Web input. Information regarding WAWF is available on the Internet at https://wawf.eb.mil/.
(c) The Contractor may submit a payment request and receiving report using other than WAWF only when–
(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor. In such cases, the Contractor shall include a copy of the Contracting Officer's determination with each request for payment;
(2) DoD makes payment for commercial transportation services provided under a Government rate tender or a contract for transportation services using a DoD-approved electronic third party payment system or other exempted vendor payment/invoicing system (e.g., PowerTrack, Transportation Financial Management System, and Cargo and Billing System);
(3) DoD makes payment for rendered health care services using the TRICARE Encounter Data System (TEDS) as the electronic format; or
(4) When the Governmentwide commercial purchase card is used as the method of payment, only submission of the receiving report in electronic form is required.
(d) The Contractor shall submit any non-electronic payment requests using the method or methods specified in Section G of the contract.
(e) In addition to the requirements of this clause, the Contractor shall meet the requirements of the appropriate payment clauses in this contract when submitting payments requests.
(End of clause)
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause--
Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.
Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
As specified in the individual Task Order
(Contracting Officer: Insert applicable document type(s). Note: If a “Combo” document type is identified but not supportable by the Contractor's business systems, an “Invoice” (stand-alone) and “Receiving Report” (stand-alone) document type may be used instead.)
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
As specified in the individual Task Order
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table* Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC F1X3Q2 Issue By DoDAAC FA4620 Admin DoDAAC FA4620 Inspect By DoDAAC F1X3Q2 Ship To Code N/A Ship From Code N/A Mark For Code N/A Service Approver (DoDAAC) F1X3Q2 Service Acceptor (DoDAAC) FA4620 Accept at Other DoDAAC F1X3Q2 LPO DoDAAC N/A DCAA Auditor DoDAAC N/A Other DoDAAC(s) F1X301
DoDAAC information will be specified as an attachment to each individual Task Order
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
As specified in the individual Task Order
(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
As specified in the individual Task Order
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
Section I - Contract Clauses
52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
OCT 2010
52.203-13 Contractor Code of Business Ethics and Conduct OCT 2015 52.203-15 Whistleblower Protections Under the American Recovery and
Reinvestment Act of 2009
JUN 2010
52.203-16 Preventing Personal Conflicts of Interest DEC 2011 52.203-17 Contractor Employee Whistleblower Rights and Requirement
To Inform Employees of Whistleblower Rights
APR 2014
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper
MAY 2011
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2015
52.204-13 System for Award Management Maintenance OCT 2016 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.204-19 Incorporation by Reference of Representations and
Certifications.
DEC 2014
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
OCT 2015
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.210-1 Market Research APR 2011 52.211-18 Variation in Estimated Quantity APR 1984 52.215-2 Audit and Records--Negotiation OCT 2010 52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.215-10 Price Reduction for Defective Certified Cost or Pricing Data AUG 2011 52.215-11 Price Reduction for Defective Certified Cost or Pricing Data--
Modifications
AUG 2011
52.215-12 Subcontractor Certified Cost or Pricing Data OCT 2010 52.215-13 Subcontractor Certified Cost or Pricing Data--Modifications OCT 2010 52.215-21 Requirements for Certified Cost or Pricing Data and Data
Other Than Certified Cost or Pricing Data -- Modifications
OCT 2010
52.219-6 Notice Of Total Small Business Set-Aside NOV 2011 52.219-8 Utilization of Small Business Concerns NOV 2016 52.219-14 Limitations On Subcontracting JAN 2017 52.222-1 Notice To The Government Of Labor Disputes FEB 1997 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards- Overtime
Compensation
MAY 2014
52.222-5 Construction Wage Rate Requirements--Secondary Site of the Work
MAY 2014
52.222-6 Construction Wage Rate Requirements MAY 2014
52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records MAY 2014 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.222-30 Construction Wage Rate Requirements--Price Adjustment (None or Separately Specified Method)
MAY 2014
52.222-35 Equal Opportunity for Veterans OCT 2015 52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014 52.222-37 Employment Reports on Veterans FEB 2016 52.222-40 Notification of Employee Rights Under the National Labor
Relations Act
DEC 2010
52.222-50 Combating Trafficking in Persons MAR 2015 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration
Equipment and Air Conditioners.
JUN 2016
52.223-15 Energy Efficiency in Energy-Consuming Products DEC 2007 52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
MAY 2008
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving
AUG 2011
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.227-1 Authorization and Consent DEC 2007 52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.227-17 Rights In Data-Special Works DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets JAN 2012 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014 52.228-14 Irrevocable Letter of Credit NOV 2014 52.228-15 Performance and Payment Bonds--Construction OCT 2010 52.229-3 Federal, State And Local Taxes FEB 2013 52.230-2 Cost Accounting Standards OCT 2015 52.230-6 Administration of Cost Accounting Standards JUN 2010 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-17 Interest MAY 2014 52.232-18 Availability Of Funds APR 1984 52.232-23 Assignment Of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
JUL 2013
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
DEC 2013
52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Alt I Specifications and Drawings for Construction (Feb 1997) -
Alternate I
APR 1984
52.236-22 Design within Funding Limitations APR 1984 52.236-23 Responsibility of the Architect-Engineer Contractor APR 1984 52.236-25 Requirements for Registration of Designers JUN 2003 52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-4 Changes JUN 2007 52.243-6 Change Order Accounting APR 1984 52.244-6 Subcontracts for Commercial Items JAN 2017 52.246-21 Warranty of Construction MAR 1994 52.248-3 Value Engineering-Construction OCT 2015 52.249-1 Termination For Convenience Of The Government (Fixed
Price) (Short Form)
APR 1984
52.249-2 Termination For Convenience Of The Government (Fixed- Price)
APR 2012
52.249-2 Alt I Termination for Convenience of the Government (Fixed- Price) (Apr 2012) - Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Alt A System for Award Management Alternate A FEB 2014 252.205-7000 Provision Of Information To Cooperative Agreement Holders DEC 1991 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By
The Government of a Country that is a State Sponsor of Terrorism
OCT 2015
252.215-7000 Pricing Adjustments DEC 2012
252.223-7001 Hazard Warning Labels DEC 1991 252.223-7004 Drug Free Work Force SEP 1988 252.223-7006 Prohibition On Storage, Treatment, and…