FA4620-17-R-B001_Atch_3_Past_Perf_cover_letter_and_Questionare.doc

DOC document 86 KB Posted

Attached to
FY17 MACC Federal contract opportunity
Solicitation number
FA4620-17-R-B001
Issued by
Department of the Air Force Air Mobility Command

About this file

Attachment 3 Word Version

View the file

Other files for this federal contract opportunity

Other files attached to FY17 MACC, newest first.
File Type Posted
FA4620-17-R-B001_MACC_Seed_Project_Amend_4,_SOW_Atch_B_-_32_01_11_Paint_Removal_CAP1008257.pdf PDF
FA4620-17-R-B001_Amendment_04.pdf PDF
FA4620-17-R-B001_Amendment_2_SF-30.pdf PDF
FA4620-17-R-B001_Amendment_3_SF-30.pdf PDF
Site_Visit_Sign_in_Roster_3_Mar_17.pdf PDF
FY17_MACC_SF1442_Amendment_1.pdf PDF
FA4620-17-R-B001_MACC_Seed_Project_SOW_Atch_A_-_01_35_13_Special_Procedures_CAP1008257.pdf PDF
FA4620-17-R-B001_Atch_11C_WA170001_Highway.pdf PDF
FA4620-17-R-B001_Atch_1A_MACC_Seed_Project_Price_Schedule.pdf PDF
FA4620-17-R-B001_MACC_Seed_Project_SOW_Atch_B_-_32_01_11_Paint_Removal_CAP1008257.pdf PDF
FA4620-17-R-B001_Atch_6_MACC_Specs_25_Oct_16.pdf PDF
FA4620-17-R-B001_Atch_7_2016_Base_Design_Standards.pdf PDF
FA4620-17-R-B001_Atch_8_Architectural_Compatibility_Plan.pdf PDF
FA4620-17-R-B001_Atch_4_Subcontractor_-_Teaming_Arangement_Release.pdf PDF
FA4620-17-R-B001_Atch_2_MACC_Past_Performance_Info_28_Nov_16.pdf PDF
FA4620-17-R-B001_MACC_Seed_Project_SOW_Atch_E_-_BREAKDOWN_OF_PAINTING_CAP1008257.pdf PDF
FA4620-17-R-B001_Atch_9_FAFB_Operational_Climactic_Data.pdf PDF
FY17_MACC_SF1442_Released.pdf PDF
FA4620-17-R-B001_Atch_11B_WA170101_Heavy.pdf PDF
FA4620-17-R-B001_Atch_1_MACC_Seed_Project_TORFP_Letter.pdf PDF
FA4620-17-R-B001_Atch_10_FAFB_Real_ID_Act_Pamphlet.pdf PDF
FA4620-17-R-B001_MACC_Seed_Project_SOW_Atch_C_-_32_17_24_Pavement_Markings_CAP1008257.pdf PDF
FA4620-17-R-B001_Atch_11D_WA170120_Residental.pdf PDF
FA4620-17-R-B001_Atch_11A_WA170042_Building.pdf PDF
FA4620-17-R-B001_Atch_3_Past_Perf_cover_letter_and_Questionare.pdf PDF
FA4620-17-R-B001_Atch_5_MACC_Seminar_SOW_8_Nov_16.pdf PDF
FA4620-17-R-B001_Atch_1B_Seed_Project_SOW_CAP1008257__6_Feb_17.pdf PDF
FA4620-17-R-B001_MACC_Seed_Project_SOW_Atch_D_-_Task_Order_Drawings_CAP_1008257.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS 92D AIR REFUELING WING (AMC)

FAIRCHILD AIR FORCE BASE WASHINGTON

23 Feb 17

MEMORANDUM FOR PROSPECTIVE EVALUATORS

FROM: 92d Contracting Squadron

110 West Ent Street

Fairchild AFB, WA 99011-8568

SUBJECT: Solicitation FA4620-17-R-B001, Multiple Award Construction Contract (MACC) Past Performance Questionnaire

1. The 92d Contracting Squadron of the Air Mobility Command (AMC) is in the process of selecting a contractor for the Multiple Award Construction Contract program for Fairchild AFB WA. The MACC is a multiple award, competitive design-build indefinite delivery/indefinite quantity (IDIQ) design/construction acquisition based upon a general statement of work. The work will consist of multiple disciplines in general construction and design categories to include maintenance, repair, and alteration of real property as well as new construction of base infrastructure, facilities, roads and airfields.

One of the considerations in proposal evaluation is the verification of the offerors’ past and present performance on contracts, which reflect the offeror’s ability to perform on the proposed effort. We depend on information received from agencies such as yours, which have had first hand experience with an offeror, for the evaluation of the offeror’s performance on those contracts.

Our areas of interest in the offeror are summarized in the enclosed questionnaire. Please complete this questionnaire and return your written response no later than 7 calendar days after your receipt of this letter. This schedule will allow us sufficient time to analyze the data within the proposal evaluation period.

2. To assist you in preparing your response and expediting your reply, the questionnaire may be filled out by hand and emailed to paul.blais@us.af.mil, or faxed to 509-247-8685 (Attention: Paul Blais). Please call Paul Blais at 509-247-4864 prior to transmission or if you have any questions. Your completed questionnaire will become a part of the official Source Selection records.

3. When filled in this document is “Source Selection Sensitive Information” IAW FAR 3.104. Your help is greatly appreciated and your prompt response will be one of the keys to the successful and timely completion of this Source Selection.

RICHARD A. HEDRICK

Contracting Officer Attachment:

Past Performance Questionnaire (3 pages) Past Performance Evaluation Questionnaire

Solicitation FA4620-17-R-B001, Fairchild AFB WA-MACC

SECTION 1: Contractor Information (to be completed by the contractor requesting evaluation prior to mailing)

A. Contractor’s name and address:

B. Point of Contact:

C. Phone Number (with area code):

D. Contract Number:

E. Project Title or Description of Work performed under this project:

F. Contract Type:

FORMCHECKBOX

Firm Fixed Price

FORMCHECKBOX

Indefinite Deliver/Indefinite Quantity Task Order

FORMCHECKBOX

Cost Reimbursement

G. Project Award Date:

H. Schedule Completion Date:

I. Estimated / Actual Completion Date:

J. Total Dollar Value:

K. Current/Final Project Amount:

I. Contractor being evaluated performed as the

Prime Contractor

FORMCHECKBOX

Subcontractor

M. Authorization is hereby granted to provide the information requested in SECTION B of this Questionnaire.

(Signature)

(Name and Title of Authorizing Official)

(Date)

SECTION 2: Respondent Information (to be completed by respondent) Evaluated By:

(Signature)

(Date)

Address:

(Typed or Printed Name)

(Title)

Phone Number:

Number of years evaluator worked on subject contract:

SECTION 3: Performance Information: Choose the number on the scale of 1 to 5 that most accurately describes the contractor’s performance or situation. Please Provide A Narrative Explanation For Any Ratings Of 1 Or 2.

1
2
3
4
5
Unsatisfactory
Marginal
Satisfactory
Very Good
Exceptional
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being evaluated reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.
Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory
Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with some minor problems for which corrective actions taken by the contractor was effective.
Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being evaluated was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

Evaluation Areas

1. Customer Satisfaction:

Customer would have no reservations in awarding another contract to the Contractor.
1
2
3
4
5
N/A

2. Quality:

a
Contractor provided effective quality control and/or inspection procedures to meet contract requirements
1
2
3
4
5
N/A
b
Contractor provided well researched and clearly identified submittals that matched contract requirements
1
2
3
4
5
N/A
c
Contractor completed all work with good workmanship and in conformance with the specifications
1
2
3
4
5
N/A
d
Contractor corrected deficiencies in a timely manner and pursuant to their quality control plan
1
2
3
4
5
N/A

3. Timeliness:

a
Contractor met established project schedules to complete the project on time
1
2
3
4
5
N/A
b
Contractor provided timely cost/design proposals
1
2
3
4
5
N/A
c
Contractor submitted the progress schedule and progress reports as required
1
2
3
4
5
N/A
d
Contractor provided on-time submittals as required
1
2
3
4
5
N/A
e
Contractor provided timely resolution of all punch list items
1
2
3
4
5
N/A

4. Responsiveness:

a
Contractor acted promptly to resolve problems, ensuring compliance with contract requirements and safety regulations
1
2
3
4
5
N/A
b
Contractor was reasonable and cooperated to resolve problems, attended meetings as needed, and maintained communication with the government to keep the project on schedule or minimize the delay
1
2
3
4
5
N/A
c
Contractor identified problems as the occurred; suggested approaches to the problems; displayed initiative to solve problems; and performed as a Team Member
1
2
3
4
5
N/A
d
Contractor responded to warranty issues within the time frames specified in the contract
1
2
3
4
5
N/A

5. Subcontracts and Management:

a
Contractor provided experienced/qualified managers and supervisors with the technical and administrative abilities needed to meet contract requirements
1
2
3
4
5
N/A
b
Contractor hired quality subcontractors and effectively managed and coordinated their work
1
2
3
4
5
N/A
c
Contractor hired, maintained, and replaced as necessary, qualified personnel and subcontractors/suppliers
1
2
3
4
5
N/A
d
Contractor ensured site superintendent and quality control representative were consistently present on site when work was performed
1
2
3
4
5
N/A

6. Design:

a
Contractor provided complete, supportable, technically sound designs for the project
1
2
3
4
5
N/A
b
Contractor demonstrated the ability to incorporate user’s requirements into the design
1
2
3
4
5
N/A
c
Contractor completed designs that were constructed in the same manner as they were designed
1
2
3
4
5
N/A

7. Change/Cost Control:

a
Contractor responsive to contract changes and provided accurate, reasonable and supportable cost proposals
1
2
3
4
5
N/A
b
Contractor demonstrated the ability to control costs and/or design projects or modifications within the magnitude specified
1
2
3
4
5
N/A
c
Contractor validated subcontractor cost proposals prior to submission to the Government
1
2
3
4
5
N/A

REMARKS:

SECTION 4: Narrative Summary

1. What were the contractor’s greatest strengths in the performance of the contract?

2. What were the contractor’s greatest weaknesses in the performance of the contract?

3. Please provide any additional comment concerning the contractor’s performance, as desired.

4. Government Contracts Only: Has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations?

FORMCHECKBOX

No

FORMCHECKBOX

Yes

FORMCHECKBOX

Default

FORMCHECKBOX

Convenience

FORMCHECKBOX

Pending Terminations

If yes, please explain (e.g., inability to meet cost, performance, or delivery schedules, etc.)

5. Government Contracts Only: Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain outcome in “Remarks”.

No

FORMCHECKBOX

Yes

Thank you for your prompt response and assistance!

Please return this completed questionnaire to:

Mailing address:

Paul Blais

92d Contracting Squadron

110 West Ent Street

Fairchild AFB WA 99011-8568

Or Email:

paul.blais@us.af.mil

Or FAX to:

Paul Blais at 509-247-8685

File details come from the government source that posted it. Updated .