Amendment 03 - Q A.pdf
PDF 38 KB Posted
- Attached to
- Multiple Award Task Order Contract (MATOC) at Fairchild AFB WA Federal contract opportunity
- Solicitation number
- FA4620-12-R-B002
About this file
SF30 Amendment 0003
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See page 2
1. CONTRACT ID CODE PAGE OF PAGES
J 1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 30-May-2012
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA4620-12-R-B002
X 9B. DATED (SEE ITEM 11)
09-May-2012
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
30-May-2012
CODE
92 CONTRACTING SQUADRON
110 W ENT STREET
FAIRCHILD AFB WA 99011-8568
FA4620 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
1291424046A Text Box
FA4620-12-R-B002
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
Q & A AMENDMENT 03
The purpose of this amendment is to:
• Answer questions arising from the site vist/preproposal conference held on 16 May 2012
• Incorporate a revised Statement of Work dated 29 May 2012
• Incorporate a revised Hazmat Survey dated 29 May 2012
1. Questions and answers arising from the site vist/preproposal conference:
A. QUESTION: The seed project specs Statement of Work - 4.0-C-3 notes that the disturbed surfaces are to be patched to match paint and texture. In the Lead Based Paint section item 1A – third paragraph it reads that painting of the abated areas is not included in the project.
Please clarify.
ANSWER: Please see revised Hazardous Materials Survey, Section 028399, 1.01A, page 56, dated 29 May 2012.
B. QUESTION: In the lead based paint removal section 1A – third paragraph – it reads that the lead based paint on all stairwell walls and outside perimeter is to be removed. In section D it reads that lead based paint in areas to be disturbed by core drilling and hanging of pipes is to be abated. Please clarify the extent of the lead based paint abatement.
ANSWER: Refer to question A.
C. QUESTION: The specifications call for a Fire Protection Engineer to stamp the drawings.
Many of the fire suppression companies proposing on this job have NICET Level 3 minimum and are able to prepare designs and receive a letter of acceptance from a fire protection engineer. Fire Protection Engineers will not stamp drawings that they do not design themselves. Will a letter of acceptance from a fire protection engineer be acceptable, if the company doing the design has a NICET Level 3 or greater designation?
ANSWER: See revised SOW dated 29 May 2012, paragraph 4.0 C.1
D. QUESTION: Please provide recent water flow information at building site. Water static pressure, Petot psi, Pressure drop from read hydrant, gallons per minute availability.
ANSWER: Collecting this information is part of the Contractors design process. Successful bidder may contact our water department to determine what information is available.
E. QUESTION: Are there any existing code violations with the existing fire sprinkler system that require correction and should these be included in our proposal?
ANSWER: No known code violations. If encountered they would be considered a differing site condition and treated as required.
F. QUESTION: Per SOW page 3 of 4 Paragraph C note 2 . Contractor is to provide abatement as needed for Fire Protection wall penetrations for pipe supports. Confirm these are the only locations lead paint abatement to take place and not as stated in specification section 028301 Lead-based Paint Removal (Paragraph A, Bullet 3) indicating that all lead paint in stairwell is to be removed.
ANSWER: Please see Hazardous Materials Survey dated 29 May 2012 page 56
G. QUESTION: SOW Paragraph C note 3 (Page 4) states to “Restore all disturbed surfaces to match paint color, texture of adjacent surfaces.” Specification Section 028301 states “Repainting of the stairwell walls is not in this scope of work. Please clarify if painting is required and to what extent.
ANSWER: The contractor will only be responsible for painting and texturing stairwell wall areas disturbed by this project. Please see Hazardous Materials Survey dated 29 May 2012
H. QUESTION: Please verify that, in the case of a joint venture, both members of the joint venture are to submit up to five (5) past performance projects each, for a total of ten (10) permissible projects for two joint venture members.
ANSWER: Yes, see paragraph 2.2.2
I. QUESTION: Please advise whether a joint venture should submit a copy of the executed Joint Venture Agreement with the proposal, and, if so, which volume it should be included in.
ANSWER: Yes, see paragraph 1.4. Please submit information in Volume II, section 4.
J. QUESTION: Please advise if any additional documentation related to the joint venture should be provided as a part of a joint venture proposal and where it should be included.
ANSWER: A list of Joint Venture partners with Volume I summary page. All other approved Joint Venture past performance information should be submitted in Volume II.
K. QUESTION: Please verify that the attendence at the pre-proposal conference was not mandatory to be eligible to submit a proposal.
ANSWER: The pre-proposal conference was not mandatory, all qualified 8(a) interested parties are eligible to provide a proposal for this solicitation.
L. QUESTION: Are completed CCASS evaluations from the PPIRS system and/or previously completed Past Performance Questionnaires (on USACE/NAVFAC Questionnaire Form PPQ-0 or equivalent) acceptable in lieu of a completed Attachment 5?
ANSWER: CCASS evaluations are not a suitable substitute for the Past Performance Questionnaire. Please submit a Questionnaire for each project submitted in your past performance Volume.
M. QUESTION: Page 61 of 67 - 2.2.3. Is the last sentence of the paragraph asking for relevance of our past projects to the seed project or the MATOC program as a whole? In general please explain the last sentence.
ANSWER: The past performance should be relevant to the MATOC Program as a whole.
N. QUESTION: Page 61 of 67 – 2.2.4 The paragraph starts out with “may include” and ends with “is required”. Which is it and what exactly is the paragraph asking for?
ANSWER: Paragraph 2.2.4 relates to the identification of specific issues and risks that have been overcome. The prospective offeror should address as deemed appropriate.
O. QUESTION: On the performance questionnaire it indicates that clients are to send their questionnaires to Richard Hedrick, however, 2.2.6 of the solicitation instructions states to send it to Jeremy Howard. The fax and address are the same but who should clients put this attention to?
ANSWER: Both individuals are correct however MSgt Jeremy Howard at Jeremy.howard.2@us.af.mil would be the most appropriate.
P. QUESTION: Section 2.2.2 outlines the requirements for “Past Performance Information Sheets”. Section 2.2.3 outlines the requirements for “Relevant Contracts”
These two sections seem to be requesting the same, if not very similar information. Is the government’s intent to have a response for “projects” and one for “contracts” or is the request for 5 projects in 3 years, following the guidelines found in 2.2.2 and 2.2.3?
ANSWER: The Past Performance Information Sheets described in 2.2.2 will be used to assist the evaluators in determining project relevancy as described in 2.2.3
Q. QUESTION: Also, section 2.2.2 states to submit up to 5 Past Performance Information sheets. However attachment “2012 MATOC Atch 4 Past Performance Info 1 May 12” states in the title “Limitations: 3 Contracts”. I presume the 5 contracts are correct, please verify.
ANSWER: Five Past Performance Information Sheets is correct.
R. QUESTION: Does the Air Force intend to release the questions and answers generated during and/or as a result of the pre-proposal conference, if so, when can we expect them?
ANSWER: Yes, see amendment 03.
2. All others terms and conditions remain the same and unchanged.
3. For any questions please contact 2Lt Conner Van Fossen @ conner.vanfossen.4@us.af.mil or
509-247-4885 or MSgt Jeremy Howard at jeremy.howard.2@us.af.mil or 509-247-2072
Attachments:
• Revised Statement of Work, dated 29 May 2012
• Revised Appendix B Hazardous Material Survey, dated 29 May 12
The following have been deleted:
SUMMARY OF CHANGES
(End of Summary of Changes)