This is a self-scoring worksheet template attachment that is part of RFP FA4610-25-R-0006 for the Western-Range Operational Ordering Contract for Infrastructure Enhancement (WOOKIE) Multiple Award Construction Contract (MACC). The worksheet is a simple Excel file requiring offerors to input their company name and includes fields for number of projects, bonding capacity of $60M, and yes/no responses.
The associated solicitation is for an 8(a) set-aside IDIQ contract for construction services at Vandenberg Space Force Base and remote locations, with NAICS code 236220 and a size standard of $45M. The Air Force plans to award up to five contracts with a 5-year base period and one 2-year option. Proposals are due March 13, 2025 by 12:00 PM Pacific Time. An Industry Day is scheduled for February 20, 2025, and questions are due February 27, 2025. The contract will cover maintenance, repair and new construction of buildings, facilities, and base infrastructure using design/build or bid/build processes at Vandenberg SFB and various remote locations including Oak Mountain, Pillar Point AFS, Naval Base Ventura County, and others. Awards will be made using Highest Technically Rated Offeror with Fair and Reasonable Price procedures.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Self-Scoring Worksheet
| SELF-SCORING WORKSHEET | Lists | Number Projects | Bonding | ||||||
| OFFEROR NAME: [FILL IN OFFEROR NAME HERE] | YES | 0 | $60M - <$90M | ||||||
| Note: See Solicitation FA461025R0006 Sections L and M for Additional Information | NO | 1 | $90M - <$120M | ||||||
| Note: Offerors only fill in the orange shaded blocks throughout. Offerors shall not alter any other rows, columns, or forumlas within the Self-Scoring Worksheet. | 2 | Over $120M | |||||||
| 3 | |||||||||
| Evaluation Criteria Section | Category | Point Value | Select the appropriate response for each question as applicable | Offeror's Self-Score | 4 | ||||
| Section L Paragraph L-2 Subparagraph 2.2.1.6 | I. Relevant Experience Projects (max 3 projects per category/30 projects maximum): | 5 | |||||||
| 1. Erosion Stabilization (e.g. landslide repair, sinkhole remediation, 24"+ culvert repair) | 6 | ||||||||
| Project 1: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 7 | ||||||
| Project 2: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 8 | ||||||
| Project 3: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 9 | ||||||
| 2. Electrical Distribution and/or Transmission Lines (e.g. electrical lines from 12kV to 70kV) | 10 | ||||||||
| Project 1: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 11 | ||||||
| Project 2: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 12 | ||||||
| Project 3: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 13 | ||||||
| 3. Asbestos Abatement, Hazardous Material, and/or Lead-Based Paint Abatement (In California) (incidental is acceptable) | 14 | ||||||||
| Project 1: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 15 | ||||||
| Project 2: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 16 | ||||||
| Project 3: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 17 | ||||||
| 4. Blast resistant windows, Active Vehicle Barriers, Traffic Check Houses, and/or Entry Control Points (for Federal Facilities) | 18 | ||||||||
| Project 1: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 19 | ||||||
| Project 2: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 20 | ||||||
| Project 3: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 21 | ||||||
| 5. General Facility Renovation (e.g. dorm renovation, Lightning Protection Systems, changing room purpose, alterations to a facility which require fire suppression and/or seismic upgrades) | 22 | ||||||||
| Project 1: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 23 | ||||||
| Project 2: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 24 | ||||||
| Project 3: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 25 | ||||||
| 6. Fire Suppresion, Fire Alarm and/or Mass Notification Systems Repair, Replacement, Upgrade, or Installation | 26 | ||||||||
| Project 1: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 27 | ||||||
| Project 2: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 28 | ||||||
| Project 3: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | 29 | ||||||
| 7. Electrical System Repair, Replacement, Upgrade, or Installation including Electrical Generation and/or Switchgear | 30 | ||||||||
| Project 1: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | |||||||
| Project 2: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | |||||||
| Project 3: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | |||||||
| 8. Heating, Ventilation, and Air Conditioning (HVAC) System, including Computer Room Air Conditioning (CRAC) Units; Repair, Replacement, Upgrade, or Installation | |||||||||
| Project 1: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | |||||||
| Project 2: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | |||||||
| Project 3: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | |||||||
| 9. Secured Room Construction in accordance with ICD 705 Specifications | |||||||||
| Project 1: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | |||||||
| Project 2: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | |||||||
| Project 3: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | |||||||
| 10. Special Interest Project (Environmental, Cultural, etc) (California or Federal Standards) (Incidental is allowed) | |||||||||
| Project 1: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | |||||||
| Project 2: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | |||||||
| Project 3: [Fill in Contract Number (including Task Order Number if applicable) and Page Number in Volume] | 1000 | 0 | |||||||
| SUBTOTAL SCORE FOR SECTION L PARAGRAPH L-2 SUBPARAGRAPH 2.2.1.6 ONLY: | 30,000 | 0 | |||||||
| Section L Paragraph L-2 Subparagraph 2.2.1.8 | II. Number of Design-Build Projects as Prime Contractor: | ||||||||
| In California | 125 per project | 0 | |||||||
| In Santa Barbara County | 100 per project | 0 | |||||||
| With Santa Barbara County Air Pollution Control District | 100 per project | 0 | |||||||
| CONUS/HI/AK US Military Bases | 300 per project | 0 | |||||||
| SUBTOTAL SCORE FOR SECTION L PARAGRAPH L-2 SUBPARAGRAPH 2.2.1.8 ONLY: | 18,750 | 0 | |||||||
| Section L Paragraph L-2 Subparagraph 2.2.1.9 | III. Experience in Complex Projects: | ||||||||
| With 5 or more tasks | 600 | 0 | |||||||
| With 4 tasks | 400 | 0 | |||||||
| With 3 tasks | 300 | 0 | |||||||
| SUBTOTAL SCORE FOR SECTION L PARAGRAPH L-2 SUBPARAGRAPH 2.2.1.9 ONLY (Category will be capped at 15,000 points): | 15,000 | 0 | |||||||
| Section L Paragraph L-2 Subparagraph 2.2.1.10 | IV. Staffing: | ||||||||
| Number of qualified Project Managers | 250 per (750 max) | 0 | |||||||
| Number of qualified Superintendents | 250 per (1,500 max) | 0 | |||||||
| Number of qualified Quality Control Managers | 250 per (1,500 max) | 0 | |||||||
| SUBTOTAL SCORE FOR SECTION L PARAGRAPH L-2 SUBPARAGRAPH 2.2.1.10 ONLY: | 3,750 | 0 | |||||||
| Section L Paragraph L-2 Subparagraph | |||||||||
| 2.2.1.11 | V. Contractor has an Aggregate Bonding Capacity of: | ||||||||
| Equal to $60M but less than $75M | 1,250 | 0 | |||||||
| Equal to or Greater Than $75M but less than $90M | 2,500 | ||||||||
| Equal to or Greater Than $90M | 3,750 | ||||||||
| SUBTOTAL SCORE FOR SECTION L PARAGRAPH L-2 SUBPARAGRAPH 2.2.1.11 ONLY: | 3,750 | 0 | |||||||
| Section L Paragraph L-2 Subparagraph | |||||||||
| 2.2.1.12 | VI. Contractor has a California General Contractor's License: | ||||||||
| Type A | 1,875 | 0 | |||||||
| Type B | 1,875 | 0 | |||||||
| SUBTOTAL SCORE FOR SECTION L PARAGRAPH L-2 SUBPARAGRAPH 2.2.1.12 ONLY: | 3,750 | 0 | |||||||
| TOTAL POINTS SCORED: | 75,000 | 0 |