This file is an attachment defining 10 project categories and their specifications for the WOOKIE MACC construction contract at Vandenberg Space Force Base. The categories cover: (1) Erosion Stabilization for landslides/sinkholes, (2) Electrical Distribution/Generation (12kV-70kV), (3) Asbestos/Hazardous Material Abatement in California, (4) Anti-Terrorism/Force Protection upgrades like blast windows and barriers, (5) General Facility Renovation, (6) Fire Suppression/Alarm Systems, (7) Electrical System Repairs/Upgrades, (8) HVAC Systems including CRAC units, (9) ICD 705 Secured Room Construction, and (10) Environmental/Cultural Projects.

Each category includes detailed technical specifications and scope limitations. For example, erosion projects must involve sinkholes at least 12 inches deep and culverts 24+ inches in diameter, with designs by registered engineers. Electrical distribution work covers lines from 12kV to 70kV and includes SCADA systems. Facility renovations encompass dormitory upgrades, seismic retrofits, and usage conversions. Environmental projects must be driven by NEPA assessments or Installation Restoration Program requirements. The definitions explicitly state what is excluded from each category, such as basic maintenance work, landscaping retaining walls under 3 feet, and standard security features.

View the file

Other files

File Type Posted
Solicitation - FA461025R0006 Conformed Through Amendment 0003.pdf PDF
Solicitation Amendment FA461025R00060003 SF 30.pdf PDF
WOOKIE MACC Industry Day - QR Sign-In Report 2-20-25.pdf PDF
WOOKIE MACC Industry Day - Microsoft Teams Attendance Report 2-20-25.pdf PDF
Solicitation - FA461025R0006 Conformed Through Amendment 0002.pdf PDF
ATT 05_Volume II_HTRO Self-Scoring Worksheet_20250227.xlsx XLSX spreadsheet
WOOKIE MACC_RFI Responses_20250228.pdf PDF
Solicitation Amendment FA461025R00060002 SF 30.pdf PDF
ATT 06_Volume II_Relevant Experience Project Template_20250227.docx DOCX document
ATT 01_SOW_20250219.pdf PDF
WOOKIE MACC_RFI Responses_20250219.pdf PDF
Solicitation Amendment FA461025R00060001 SF 30.pdf PDF
ATT 03_Volume I_Price Proposal Template_20250127.xlsx XLSX spreadsheet
ATT 12_Construction Cost Estimate Breakdown.xlsx XLSX spreadsheet
ATT 09_Monterey - San Mateo Wage Determination_20250207.pdf PDF
ATT 05_Volume II_HTRO Self-Scoring Worksheet_20241029.xlsx XLSX spreadsheet
ATT 15_VSFB CAD Standards_Aug 2019.pdf PDF
ATT 11_Schedule Material Submittals.xlsx XLSX spreadsheet
ATT 02_Volume I_Executive Summary Sheet_20241024.docx DOCX document
ATT 06_Volume II_Relevant Experience Project Template_20241024.docx DOCX document
ATT 13_01 00 00 General VSFB Specs.pdf PDF
Solicitation - FA461025R0006.pdf PDF
ATT 14_01 57 20 Environmental Specs.pdf PDF
ATT 07_SB Wage Determination_20241108.pdf PDF
ATT 08_Ventura Wage Determination_20241108.pdf PDF
ATT 01_SOW_20241120.pdf PDF
ATT 10_AF Form 103.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Categories

1. Erosion Stabilization (e.g. landslide repair, sinkhole remediation, 24"+ culvert repair)

2. Electrical Distribution, Generation, and/or Transmission Lines (e.g. electrical lines from 12kV to 70kV)

3. Asbestos Abatement, Hazardous Material, and/or Lead-Based Paint Abatement (In

California) (Incidental is allowed)

4. Blast resistant windows, Active Vehicle Barriers, Tra ic Check Houses, and/or Entry

Control Points (for Federal Facilities)

5. General Facility Renovation (e.g. dorm renovation, Lightning Protection Systems, changing room purpose, alterations to a facility which require fire suppression and/or seismic upgrades)

6. Fire Suppression, Fire Alarm and/or Mass Notification Systems Repair, Replacement, Upgrade, or Installation

7. Electrical System Repair, Replacement, Upgrade, or Installation including Electrical Generation and/or Switchgear

8. Heating, Ventilation, and Air Conditioning (HVAC) System, including Computer Room Air Conditioning (CRAC) Units; Repair, Replacement, Upgrade, or Installation

9. Secured Room Construction in accordance with Intelligence Community Standard (ICD) 705 Specifications

10. Special Interest Project (Environmental, Cultural, etc.) (California or Federal Standards) (Incidental is allowed)

Definitions

1. Erosion Stabilization: To meet the definition of this category the main purpose of the project must involve the repair and stabilization of soil and geography a ected by either erosion, landslides, sinkholes at least 12 inches in diameter and depth, or damaged culverts at least 24 inches in design diameter. The stabilization e orts must have been completed based upon a design prepared by a registered engineer.

Tasks in this category may include but are not limited to:

Construction, repair, or replacement of retaining walls Sinkhole Repairs Soil stabilization techniques such as benchmarking, and/or Installation of drainage systems associated with stabilization e orts such as rip rap.

WOOKIE MACC

Solicitation: FA461025F0006

Attachment 04

This category does not include general landscaping related retaining walls (i.e.

retaining walls 3 feet or less in height) or drainage systems such as French drains.

2. Electrical Generation, Distribution, and/or Transmission Lines: To meet the definition of this category the main purpose of the project must involve the installation, repair, replacement, or upgrade of electrical generation, distribution and transmission lines, ranging from 12kV to 70kV, and their associated control systems using a design prepared by a registered engineer. Tasks in this category may include but are not limited to:

Installation of new distribution and/or transmission lines The replacement of damaged or outdated distribution or transmission lines The upgrade of existing lines to meet current safety and performance standards.

Installation, repair or capability upgrades to pole mounted transformers, substations, and large-scale power generation, For purposes of this category large scale power generation consists of permanently installed generators of 1MW or greater output, designed to service more than one facility as primary or backup power; this does not include facility level emergency power generators.

This category includes Supervisory Control and Data Acquisition (SCADA) systems and other controls associated with the items above.

This category does not include tasks associated with typical maintenance of substations or distribution lines such as cleaning or like-for-like replacements of poles and hardware

3. Asbestos Abatement, Hazardous Material, and/or Lead-Based Paint Abatement (In California): To meet the definition of this category the project must involve the safe and e ective removal and disposal of hazardous materials, including asbestos, lead-based paint, and other federal, state, or county permit-requiring hazardous substances, from buildings and other structures in California. This category does not include soil remediation.

4. Department of Defense (DoD) Anti-Terrorism/Force Protection (AT/FP) Upgrades: To meet the definition of this category the main purpose of the project must involve the installation, repair, replacement, or upgrade of major anti-terrorism/force protection (AT/FP) compliant security features for DoD facilities.

Major AT/FP compliant security features mean security features which require calculations and a design from registered engineers to ensure compliance with AT/FP regulations. Tasks in this category may include but are not limited to:

WOOKIE MACC

Blast resistant windows installation Active vehicle barrier installation Tra ic check houses and entry control points installation/upgrade

These tasks may include, but are not limited to, the installation of new security features, the replacement of damaged or outdated features, and the upgrade of existing features to meet current security standards. This category would not include simplified security features such as man-bars or visual screens.

5. General Facility Renovation: To meet the definition of this category the main purpose of the project must involve the renovation of facilities for various purposes based upon a design prepared by a registered engineer. Tasks in this category may include but are not limited to:

Dormitories, or whole building renovations Renovations changing the usage type of the facility (e.g. Industrial Support being converted to o ice space) Lightning protection system installation Seismic upgrades Potable water, non-potable water, and sewer/septic system installation, repair or upgrade.

6. Fire Suppression, Fire Alarm and/or Mass Notification Systems Repair, Replacement, Upgrade, or Installation: To meet the definition of this category the main purpose of the project must involve the installation, repair, replacement, or upgrade of fire suppression, fire alarm, and/or mass notification systems using a design prepared by a registered engineer and stamped by a fire protection engineer or NICET (National Institute for Certification in Engineering Technologies) Level IV certified technician.

7. Electrical System Repair, Replacement, Upgrade, or Installation including Electrical Generation and/or Switchgear, Transformers, and Facility specific Generators: To meet the definition of this category the main purpose of the project must involve the installation, repair, replacement, or upgrade of facility level electrical systems using a design prepared by a registered engineer. Tasks in this category may include but are not limited to:

Repairs, replacements or upgrades of permanently installed electrical generation (primary, backup, or emergency)

Switchgear replacement and/or upgrades

WOOKIE MACC

Electrical panels replacement and/or upgrades Pad-mounted transformers replacement

8. Heating, Ventilation, and Air Conditioning (HVAC) System, including Computer Room Air Conditioning (CRAC) Units Repair, Replacement, Upgrade, or Installation: To meet the definition of this category the main purpose of project must involve the installation, repair, replacement, or upgrade of HVAC systems, including computer room air conditioning (CRAC) units, using a design prepared by a registered engineer. Tasks in this category may include but are not limited to:

Installation of new HVAC systems Replacement of damaged or outdated systems Upgrade of existing systems to meet current code Repair, replacement or installation of HVAC piping Controls system replacement, upgrade, and programming

9. Secured Room Construction in accordance with ICD 705 Specifications: To meet the definition of this category the main purpose of the project must involve the construction of secured rooms or facilities in accordance with ICD 705 specifications using a design prepared by a registered engineer. This may include, but is not limited to, the installation of specialized security features, such as reinforced walls, secure doors, communication systems, and other security measures, to meet current security standards. This project type may also include, but is not limited to, any necessary renovations to existing facilities to meet current security standards, including the construction of secure perimeters within a facility.

10. Environmental or Culturally Sensitive Project (California or Federal Standards) (Incidental is allowed): This project type involves projects related to environmentally or culturally sensitive issues, which must meet California or federal standards. These projects shall have required construction requirements or remediation driven by a National Environmental Policy Act (NEPA) Environmental Assessment (EA) or Environmental Impact Statement (EIS), or Installation Restoration Program (IRP) or equivalent site. This shall not include basic monitoring requirements or basic site restoration (hydroseeding after completion). This may include, but is not limited to, projects that are incidental to other project types, but which still require special attention to meet the relevant standards. Tasks in this category may include but are not limited to:

Soil or water remediation at an IRP or EPA Superfund designated site Construction changes to avoid environmentally sensitive areas

WOOKIE MACC

Construction remediation of environmentally sensitive areas Construction e orts requiring cultural/archaeological excavation or cultural artifact collection

WOOKIE MACC