PostSV_RFI_Responses.pdf
PDF 98 KB Posted
- Solicitation number
- FA461025Q0011
About this file
This document is a comprehensive post-site visit Questions and Answers (Q&A) document for demolition services of Buildings 533, 541, 886, 887, and 888 at Vandenberg Space Force Base. The Q&A covers critical details for potential contractors, including key requirements such as mandatory asbestos and lead-based paint surveys for each building, which must be conducted by a third-party Certified Asbestos Consultant prior to any work. Environmental considerations are prominent, with specific guidelines about tree and vegetation removal, particularly for coast live oak trees over 6 inches in diameter, and requirements for biological monitoring during bird nesting seasons.
The solicitation is split into two separate requirements: Buildings 533 and 541 are a HUBZone Set-Aside, while Buildings 886, 887, and 888 are a Small Business Set-Aside. Contractors must handle utility disconnections, septic system management, and site restoration, including potential seeding with a native coastal scrub seed mix. Notably, no as-built drawings are available, and contractors must assume potentially unknown site conditions. The demolition work includes removing building structures, adjacent sidewalks, interior elements, and existing equipment, with specific requirements for utility capping, waste tracking through HAZMART, and adherence to environmental restrictions.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Post Site-Visit Q&A for Demolition Services of Buildings 533, 541, and 886, 887, 888
1. B533/541: The solicitation attachments include asbestos testing completed in 1992, reporting “no asbestos present”. Are there more recent testing results/reports available or are the reports from 1992 the only reports available?
a. No, there are no existing usable asbestos and/or lead-based paint surveys that meet the requirements for this demolition for any of the buildings mentioned.
b. Prior to any work starting, the project proponent is responsible for having an asbestos and lead-based paint survey performed by a third-party Certified Asbestos Consultant (CAC) independent of the abatement team, for each building.
2. B533/541: Has ACM testing been done on Building 541 and can it be provided prior to bid?
a. No, there are no existing usable asbestos and/or lead-based paint surveys that meet the requirements for this demolition for any of the buildings mentioned.
b. Prior to any work starting, the project proponent is responsible for having an asbestos and lead-based paint survey performed by a third-party Certified Asbestos Consultant (CAC) independent of the abatement team, for each building.
3. There are LBP reports for buildings 887 and 886 but not for 533, 541 or 888. Has testing been done on those buildings as well and can the reports be provided?
a. No, there are no existing usable asbestos and/or lead-based paint surveys that meet the requirements for this demolition for any of the buildings mentioned.
b. Prior to any work starting, the project proponent is responsible for having an asbestos and lead-based paint survey performed by a third-party Certified Asbestos Consultant (CAC) independent of the abatement team, for each building.
4. Are there sanitary facilities onsite that the contractors can use?
a. No.
5. Who is responsible for the coordination of utilities shut off/capping? Will American Water complete the water shutoff and is the government aware of any specific requirements for the water shutoff and disconnect?
a. Water from the service line to the facility will be for the contractors to remove. American Water (AW) can ensure water is turned off. Contractor to coordinate procedure with AW. See attached for PoD.
6. B886/887/888: Will the contractor be responsible for moving the hydrant? Is there a designated area where they want the water cap and sewer cap?
a. See two attachments for the point of demarcations. Fire hydrants to remain.
7. B886/887/888: How much of the asphalt that appears outside of the red line in the photograph is to be removed?
a. The red outline is for the site visit location information only and does not represent any technical information for the job sites.
8. Will the two additional buildings be included in this proposal?
a. The two additional buildings, 533 and 541 are a separate requirement, set aside for HUBZone businesses only. The SAM posting notice ID is: FA461025Q0011
9. Is a survey available for buildings 533 and 541?
a. No, there are no existing usable asbestos and/or lead-based paint surveys that meet the requirements for this demolition for any of the buildings mentioned.
b. Prior to any work starting, the project proponent is responsible for having an asbestos and lead-based paint survey performed by a third-party Certified Asbestos Consultant (CAC) independent of the abatement team, for each building.
10. Is one technical approach required, or should it be separated by building or RFP?
a. Technical approaches should be separated by RFP.
11. Does the brush surrounding the building need to be cleared and grubbed, etc.?
a. Only for access to the work. All else may remain.
12. What happens to the building footprint—repave, backfill, or both? Is there a spec for topsoil material and quantity?
a. Any soil topsoil imported should be weed free. Soil amendments may be needed for topsoil and/or prepared to ensure native seed germination in any seed mix is used.
13. Is there a septic system at any building location, and are there any special requirements?
a. Septic system components should be cut and capped to prevent short circuiting of groundwater movement through any piping conveyances. Septic tanks shall be removed or demolished in place and holes punched through the bottom plate to allow groundwater percolation. Soil backfilling shall match hole volume by at least 100% to prevent soil subsidence.
14. Do all materials entering and leaving have to be logged thru hazmart on base?
a. Yes, all hazardous materials used onsite will be logged into the HAZMART system. In addition, any solid wastes (C&D) being removed must be tracked through the Solid Waste Program.
15. Where do existing utilities get capped?
a. See attached for PoDs. For the sewer it’ll be from the clean out and beyond is American Water. Water from the service line to the facility will be the contractors to remove. AW can insure water is turned off.
16. Can we combine the 103 to cover all the buildings in the group 888,887,886?
a. Yes.
17. Will government be removing batteries from 886?
a. No.
18. Are there environmental or habitat (gnatcatcher or similar) working restrictions?
a. This would be discussed in the 332 or 813 that was completed for this project (assuming that the project is still as described in the 332/813).
19. How deep below the surface will tree roots have to be removed?
a. With regard to any coast live oak tree > 6-inch dbh, avoid if at all feasible. This would potentially be in the vicinity of B886.
Trimming is preferred as needed. If any oak tree greater than 6-inches in diameter (dbh) is removed, an oak mitigation plan for replacement shall be developed with 1 year of maintenance. Coordinate plan with CEIEA at least one year prior to oak removal for approval or as soon as practicable. Replacement shall consist of 5-gallon size (minimum) trees obtained from locally-occurring saplings or seed stock of 10 for every 6-inch diameter or greater oak tree to be removed or significantly disturbed.
20. What distance from all sides of the building will foliage, and trees be removed?
a. With regard to any coast live oak tree > 6-inch dbh, avoid if at all feasible. This would potentially be in the vicinity of B886.
Trimming is preferred as needed. If any oak tree greater than 6-inches in diameter (dbh) is removed an oak mitigation plan for replacement shall be developed with 1 year of maintenance. Coordinate plan with CEIEA at least one year prior to oak removal for approval or as soon as practicable. Replacement shall consist of 5-gallon size (minimum) trees obtained from locally occurring saplings or seed stock of 10 for every 6-inch diameter or greater oak tree to be removed or significantly disturbed.
21. Is the removal of the asphalt/pavement parking lot at buildings 886, 887, and 888 to be included in the demolition?
a. No, they may remain for contractor use and staging and then we will abandon in place.
22. Will septic tank(s) and leach line(s) be included in the demolition contract?
a. 800s appear to be on sewer line (see attached). No indication of leach at 533 per existing plan. 541 was part of an existing complex of building that were situated downslope and have since been removed. Assume leach is gone, cap sewer if it exists, departure from building.
23. What buildings have septic tanks and leach lines?
a. Unknown.
24. Will the contractor assume each building does not have unseen site conditions such as concrete vaults, basements, main water lines, main sewer lines, electrical pipe/duct banks, and gas lines within or under each building?
a. May request what info is available from CES GEO Office, but info may not be available. With the info they have, there is no indication of a basement at 533.
25. Is the contractor required to provide a Hazardous Material Survey for all buildings 886, 887, and 888?
a. Yes, prior to any work starting, the project proponent is responsible for having an asbestos and lead-based paint survey performed by a third-party Certified Asbestos Consultant (CAC) independent of the abatement team, for each building.
26. After the building(s) removal and the finish grade is completed, will the entire site be seeded?
a. If a seed mix is needed, approval is required by CEIEA. Coordinate native coastal scrub seed mix and approval with CEIEA.
27. Is there a specific topsoil mix required?
a. Any soil topsoil imported should be weed free. Soil amendments may be needed for topsoil and/or prepared to ensure native
28. Is there a specific soil mix for the backfill material for all buildings?
a. Any soil topsoil imported should be weed free. Soil amendments may be needed for topsoil and/or prepared to ensure native
29. Building 541 is near Liquide Hydrogen tanks. What precautions will the contractor be responsible for during demolition? Answer still pending.
a. Mark Stortecky from Occupational Safety may provide more info. DP: 805-606-8811 CP: 805-588-2148 mark.stortecky@spaceforce.mil
30. If the building’s footing thickness and depth are unknown. What thickness and depth are to be assumed by the contractor?
a. Only info is on 533 (rubble pile). 6” slab, continuous footings 16” x 30” for each section, 40’ x 60’ and 16’ x 20’.
31. What is each building's footing thickness and depth?
a. Only info is on 533 (rubble pile). 6” slab, continuous footings 16” x 30” for each section, 40’ x 60’ and 16’ x 20’.
32. If the building's foundation thickness is unknown, what thickness is to be assumed by the contractor?
a. Only info is on 533 (rubble pile). 6” slab, continuous footings 16” x 30” for each section, 40’ x 60’ and 16’ x 20’.
33. What is each building's foundation thickness?
a. Only info is on 533 (rubble pile). 6” slab, continuous footings 16” x 30” for each section, 40’ x 60’ and 16’ x 20’.
34. Will As-builts be provided for each building?
a. No, there is only an incomplete paper copy of plan for B533. May be viewed by request from CES GOE Office.
35. Are buildings 533 and 541, HUBZone Set-Aside and/or a Small Business Set-Aside?
a. The requirement for buildings 533 and 541 is a HUBZone Set-Aside only. The requirement for buildings 886, 887, and 888 is a Small Business Set-Aside.
36. PWS 5.3 Engineering Data states, “For reference, as-built drawing is provided at Figure 5.” In reviewing the Solicitation documents it does not appear that this was included. Can the government provide the references as-built drawings?
a. This was a mistake in the PWS.
37. Can large steel track excavators be used? Can a 30’ x 30’ area of asphalt be removal directly next to the 886 building? This will give contractors a starting point to access the structures with steel track machines while preserving the surrounding asphalt.
a. Yes.
38. PWS 1.0 Introduction reads, “The Contractor shall furnish all parts, labor material, equipment, transportation and supervision necessary to demolish vacant Buildings 886, 887, and 888, including its basement, slabs, adjacent sidewalks, interior floor/walls/ceiling, exterior walls/roof/, and existing equipment (e.g. heating/sprinkler systems) and any furnishings within the building, as well as two shipping containers and abate and dispose of any Asbestos Containing Material (ACM) or lead-based paint (LBP) within or on the building, at Vandenberg SFB, CA.” During the self-guided tour, there was no evidence of a basement in any of the buildings. Can the government confirm that the buildings do not have basements?
a. Can not confirm. May request what info is available from CES GEO Office, but info may not be available. With the info they have, there is no indication of a basement at 533.
39. PWS 7.0 Environmental Requirements states, “The demolition of the buildings can only occur during bird non-nesting season, 15Aug- 15Feb. The demolition of the sidewalks and/or associated works can occur at any time during the year, although demolition may be delayed during the rainy season (November-March).” Does the government have an idea of when this project is scheduled for completion and confirm that it will not be during these restricted dates?
a. Demolition can occur year-round; however, between 15 Feb and 15 Aug if demolition is to occur, then a biological monitor will be required for the project to ensure no nesting birds are in the structures. The cost of the monitor(s) is a requirements of the project. All monitors must be pre-approved through the 30 CES/CEIE (Environmental) Office.
40. There are asbestos reports for buildings 533,541, and 866 but not for 887 or 888. Has testing been done on those buildings as well and can the reports be provided?
a. No, there are no existing usable asbestos and/or lead-based paint surveys that meet the requirements for this demolition for any of the buildings mentioned.
b. Prior to any work starting, the project proponent is responsible for having an asbestos and lead-based paint survey performed by a third-party Certified Asbestos Consultant (CAC) independent of the abatement team, for each building.
41. There is a seed mix supplied for buildings 533 and 541. Can the government confirm that this seed mix is also required for the 800 buildings?
a. If a seed mix is needed, approval is required by CEIEA. Coordinate native coastal scrub seed mix and approval with CEIEA.
42. The attachment provided with the Site Visit details via email on March 12, 2025 displays a red line around the project site. Please confirm if this was for the purpose of the site inspection or if this is the area that will require demolition/seeding/etc.
a. The red outline is for the site visit location information only and does not represent any technical information for the job sites.
43. The response to a previous RFI-QA doc states that a performance and payment bond is required for this project. After reviewing the
1449 I do not see any reference to bonding requirements or a clause substantially the same as the clause at 52.228-16.
a. Bonding requirements have been/will be removed.