FA460025Q0027 - QnA Document.docx

DOCX document 16 KB Posted

Attached to
97 IS NIPR Expansion Project (Offutt AFB, NE)
Solicitation number
FA4600_NIPRExpansion
Issued by

About this file

The document is a Questions and Answers (Q&A) file for the FA460025Q0027 - 97 IS NIPR Expansion Project, providing critical technical details for a network infrastructure upgrade. Key technical specifications include installing OM4-MultiMode-LC/LC-Green fiber optic cabling with 12+ strands, running new cables to a data closet in Room 41G, and requiring fire-rated penetration seals. Contractors will need to supply patch cords and match existing wall jack part numbers (6-port: 1-1933674-3, 4-port: 1-1933671-3).

The associated solicitation is a 100% Small Business set-aside under NAICS code 238210 for the 97th Intelligence Squadron at Offutt Air Force Base in Nebraska. Critical procurement dates include a site visit on 26 February 2025, question submissions due by 3 March 2025, a Q&A document release by 6 March 2025, and offer submissions due by 13 March 2025 at 1:00 PM CST. The project involves network expansion services, with contractors requiring security clearance and coordination with Offutt Security Officers and Communications Squadron for bandwidth and access considerations.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA460025Q0027 – 97 IS NIPR Expansion Project Question and Answer Document

Q: Do we need fire protection/foam for the cabling that runs through penetrations?

A: Per Fire Prevention, penetrations need to be sealed after cable is ran and the seal must be fire rated.

Q: What are the part numbers for the current wall jacks so the new ones can potentially match?

A: 6 Port - 1-1933674-3; 4 Port - 1-1933671-3 Q: What type of approval/vetting is necessary for contractors working within the secure area but only on the NIPR network?

A: Awaiting response from Offutt Security Officers Q: Is there enough bandwidth going to 41G to support an additional 156 drops?

A: Awaiting response from Offutt Comm Squadron Q: Is there any type of data rack layout available for this project?

A: There was a data rack layout, but it is no longer correct. It is also a hardcopy that was printed for the Rack.

Q: Are we pulling all new cabling to these locations?

A: Yes Q: What type of cabling needs to be installed, and what color should it be?

A: OM4-MultiMode-LC/LC-Green Q: Can you please explain the symbols? Specifically, what do the white symbols represent?

A: What white symbols?

Q: Where is the data closet located?

A: The data closet is in RM 41G.

Q: Do you have any riser diagrams available?

A: Civil Engineering may have some electrical diagrams or as-builts. I will reach out to find out if they do.

Q: Is fiber optic cabling involved? If so, what type and how many strands?

A: Yes. OM4-MultiMode-LC/LC-Green; if running to MUTOAs MPO cabling is fine, 12+ strand Q: Do we need to supply patch cords?

A: Yes.