31_25_10_DAFB_Sediment_and_Erosion_Control_(9_April_2018).pdf

PDF 17 KB Posted

Attached to
Repair B793 Foundation and Demo Door Pockets
Solicitation number
FA449719RA006
Issued by

About this file

Dover AFB Sediment and Erosion Control

View the file

Other files

File Type Posted
B793_Utilities_2.pptx PPTX presentation
B793_Site_Visit__2_Questions.pdf PDF
All_Site_Visit_1_Answers.pdf PDF
Bldg_793_Mezzanine_Floor_Plan.ppt PPT presentation
B793_Utilities.pptx PPTX presentation
Solicitation_Amendment_FA449719RA0060001_SF_30.pdf PDF
DAFB_Local_Design_Guide_w_Appendix_D_(9_April_2017).pdf PDF
FBO_posted_pre-site_visit_questions_2.docx DOCX document
01_11_10_DAFB_General_Requirements_(9_April_2018).pdf PDF
02_61_10_DAFB_Environmental_Control_(9_April_2018).pdf PDF
DAFB_Architectural_Compatibility_Plan.pdf PDF
2_of_16_.pdf PDF
15_of_16_M793.3.pdf PDF
6_of_16.pdf PDF
9_of_16.pdf PDF
12_of_16.pdf PDF
5_of_16_M793.2.pdf PDF
7_of_16.pdf PDF
10_of_16.pdf PDF
16_of_16.pdf PDF
13_of_16_M793.1.pdf PDF
4_of_16_E793.1_(1).pdf PDF
3_of_16_E793.1_.pdf PDF
1_of_16_.pdf PDF
14_of_16.pdf PDF
8_of_16.pdf PDF
11_of_16.pdf PDF
FBO_posted_questions_1_pre-site_visit.docx DOCX document
Foundation.pdf PDF
Solicitation_-_FA449719RA006.pdf PDF
Wage_Determination_Bldg_1-4-19_DE190007.pdf PDF
SOW_-_B793_Rpr_Foundation_(19_Oct_18).pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

9 April 2017

31 25 10 - 1

31 25 10

DOVER AFB SEDIMENT AND EROSION CONTROL

PART 1 – CONTRACTOR PLAN SUBMITTALS

1.1 Sediment and Erosion Control Plans. The project drawings contain a compliant sediment and erosion control plan. It is labeled RECOMMENDED SEDIMENT & EROSION CONTROL PLAN and has been reviewed and approved by Dover AFB Base Civil Engineering personnel to ensure compliance with Environmental Protection Agency (EPA) and Delaware Department of Natural Resources and Environmental Control (DNREC) regulations.

1.2 The Contractor shall submit a sediment and erosion control plan for this project. The plan can consist of the plan contained in the contract drawings or a modified version of the contract drawing, or another plan prepared by the Contractor. Whichever plan is selected, the Contractor must submit the plan to Dover AFB Base Civil Engineering for review and coordination to ensure compliance with applicable federal and state regulations.

1.3 Dover AFB Base Civil Engineering will review the submitted plan for compliance and provide comments for incorporation or provide a “Review Complete” status for the plans. Upon receiving a “Review Complete” status, the contractor must file the Notice of Intent with the EPA for this project. The contractor is the holder of the sediment and erosion control permit, not Dover AFB. A copy of the filed Notice of Intent shall be provided to Dover AFB. Note, the EPA does not review drawings, but if they perform an inspection, the drawings must be made available.

1.4 Before initiating construction, the Contractor must schedule a pre-construction meeting for the purposes of discussing sediment and erosion control on the project, to include the Contractor, the associated certified construction reviewer (CCR) and Dover AFB Base Civil Engineering representatives. No construction can begin until the plans have been reviewed, the Notice of Intent filed and the pre-construction meeting has occurred.

PART 2 - CONTRACTROR RESPONSIBILITIES DURING CONSTRUCTION

2.1 The Contractor is required to ensure permit compliance during the term of the permit. To ensure continued compliance, the contractor must have a licensed CCR, as defined by the DNREC sediment and storm water regulations; perform weekly inspections as required by those same regulations.

2.2 A copy of the completed CCR reports shall be provided to Dover AFB Base Civil Engineering at the end of each month. Dover AFB reserves the right to request these reports more frequently if problems persist, or an issue of non-compliance is observed.

9 April 2017

31 25 10 - 2

2.3 The Dover AFB CCR will perform an independent inspection at their discretion to ensure continued compliance with the submitted plan and contract requirements. A copy of the Dover AFB CCR reports can be obtained by the contractor upon written request.

2.4 In-field changes must be submitted prior to implementation and must be reviewed by Dover AFB Base Civil Engineering. Particularly, environmental compliance changes, i.e. changes to sediment and erosion control practices, will be reviewed by Dover AFB Base Civil Engineering. These requested changes must still comply with all applicable federal and state environmental regulations.

PART 3 – PENALTIES FOR NON-COMPLIANCE

3.1 Dover AFB Non-Compliance Issues

3.1.1 Should non-compliance issues be identified on either the Contractor’s internal CCR report or a Dover AFB CCR report, the Contractor shall correct the issue within the work week (5 work days). If long term repairs are necessary, a continuance of 5 days can be granted. Repeated non-compliance or ignoring non-compliance issues will result in a deficiency notice issued through the Contracting Officer. Deficiency notices shall constitute a violation of environmental requirements and will result in less favorable reviews pertaining to environmental compliance on subsequent projects at Dover AFB.

3.1.2 Continued deficiency notices may result in work stoppage by the Contracting Officer to correct sediment and erosion control issues. This type of work stoppage will not extend the contract completion date.

3.2 Regulatory Non-Compliance Issues

3.2.1. Continued non-compliance issues identified on contractor’s CCR or Dover AFB CCR reports may be forwarded to the EPA enforcement division for their action. EPA enforcement issues resulting from forwarding of CCR reports or from an unannounced EPA inspection will be resolved between the permit holder (Contractor) and the EPA.

END OF SECTION