Attach 4 - 01010 Unique Site Requirements.pdf

PDF 10 KB Posted

Attached to
Replace Broken Storm Drain Pipe, B 764 Parking Lot Federal contract opportunity
Solicitation number
FA4488-09-R-0033
Issued by
Department of the Air Force Air Mobility Command

About this file

Attch 4 Spec 01010 Unique Site Requirements

View the file

Other files for this federal contract opportunity

Other files attached to Replace Broken Storm Drain Pipe, B 764 Parking Lot, newest first.
File Type Posted
Drawing of area.pdf PDF
Site Visit Questions Answers.pdf PDF
Site Visit Agenda.pdf PDF
Site Visit Minutes.pdf PDF
Attach 1 - SOW Replace Storm Drain Pipe.pdf PDF
Attach 6 Copy of AF Form 66.pdf PDF
Attach 3 - 001002 Greem Procurement.pdf PDF
Attach 5 - 01300 Submittals -.pdf PDF
Attach - 7 Spec 01 57 20 00 10-Env Protection During Const.pdf PDF
Attach 10 Davis Bacon WD NC11 07-24-2009.pdf PDF
Solication FA4488-09-R-0033.pdf PDF
Attach 8 - 01770 Contract Closeout Procedures.pdf PDF
Attach 1 - SOW Replace Storm Drain Pipe.pdf PDF
Attach 9 - Storm Drainage Spec.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4488-09-R-0033

Attachment 4

01010 Summary of Work 1 of 1

Replace Broken Storm Drain Pipe Bldg 764 Parking Lot

SECTION 01010 – UNIQUE SITE REQUIREMENTS

PART 1 GENERAL

1.1 AVAILABILITY OF WORK SITE

Government personnel will occupy sites adjacent to the work location during the contract period. The contractor shall coordinate the work so as to allow minimum inconvenience to the government. Government work hours are from 7:00 AM – 4:00 PM, Monday through Friday. If deviation from official contract work hours is required; the contractor will submit a written request to deviate from official work hours three working days in advance of the requirement to the Contracting Officer and include:

1) State reason why deviation is necessary

a) Requested working hours

b) Dates required and/or duration

c) List of employees working the deviation

2) Work to be performed

3) Confirm if digging, utility cut-offs, or other work requiring Construction Contract

Inspector will be done

4) Indicate if work will or will not be at an additional cost to the government

Contractor will continue performing during official contract work hours until Contracting Officer’s approval is obtained to deviate.

1.2 GOVERNMENT OCCUPANCY

A. The Government will occupy the site adjacent to work location during the entire period of construction for the conduct of normal operations.

B. Cooperate with Government to minimize conflict, and to facilitate Government's operations.

C. Schedule the Work to accommodate Government occupancy.

1.3 PRODUCTS

Reinforced concrete pipe and concrete sealants shall meet the performance requirement as set forth in the Federal Specifications SS-S-210 and ASTM C-990-91

END OF SECTION 01010