Past Performance Questionnaire

View the file

Other files for this federal contract opportunity

Other files attached to Joint Base McGuire-Dix-Lakehurst Electrical Service IDIQ MATOC, newest first.
File Type Posted
Main_Panel_B331-Another_View_Of_Main_Feeders_Into_Breaker.JPG JPG image
new_dig_permit_(7)-1.doc DOC document
Main_Panel_B331-Bottom_Of_Panel-Main_Feeders_On_Left_Side_Of_200_Amp_Breaker._Feeders_On_Panel_Buss_Feeding_Disconnect_For_New_Milling_Machine.JPG JPG image
FA4484-13-R-0005_Ammendment_1.pdf PDF
Main_Panel_B331-Main_Feeders_Bottom_Left_200_Amp_Breaker.JPG JPG image
Sign-in_Sheet.pdf PDF
new_dig_permit_page_2.docx DOCX document
Questions_and_Answers_Electrical_IDIQ.doc DOC document
Bid_schedule_Bldg__331_New_Electric_Feed_BS.ods ODS spreadsheet
Drawing_New_480V_Serv_to_Bld_331.pdf PDF
Wage_Determin_Ocean_County_Jun_2013.pdf PDF
Executive_Summary_Electrical_IDIQ_MATOC.doc DOC document
SOW__Bldg.__331-Upgrade_480_Volt_3_Phase_Electrical_Service.doc DOC document
FA4484-13-R-0005_Electrical_IDIQ___MATOC.pdf PDF
Past_Performance_Questionaire_Cover_Letter.doc DOC document
Security_Forces_Appendix.doc DOC document
Evironmental_Compliance_Statement_Ex.doc DOC document
SpecificationElec_ _IDIQ.pdf PDF
Wage_Determin_Burlington_County_Jun_2013.pdf PDF
Material_Submittal_Checklist_Upgrade_Electrical_Serv_to_Bldg__331.xlsx XLSX spreadsheet
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAST AND PRESENT PERFORMANCE QUESTIONNAIRE

A. GENERAL INFORMATION: Please correct any information below known to be inaccurate:

Contractor’s Name: ____________________ Telephone Number: ____________________

Address: __________________________ Fax Number: _________________________

__________________________ Point of Contact: ______________________

Project Title and Brief Description of Work: _____________________________________*

Contract Number Provided by Offeror: ___________________ Dollar Amount: ________*

Contract Period or Dates of Performance Provided by Offeror: ______________________* Contractor performed as the ( Prime Contractor ( Sub-Contractor ( Key Personnel.

* Note: If offeror holds or has held other contracts with your agency/organization in the last 3 years, please complete separate evaluation forms for those contracts as well.

B. RESPONDENT INFORMATION:

Name of Respondent:

_____________________ Title: ____________________________

Address: _____________________

Telephone Number: ___________________ _____________________________

Fax Number:

Email Address: _____________________

C. EMAIL/FAX COMPLETED SURVEY FORM TO:

FAX: (609) 754-4642 or e-mail to: lynn.mcmiller.1@us.af.mil Phone; (609)-754-2420 D. PERFORMANCE INFORMATION: Choose the appropriate letter on the scale (E, G, S, M, U, and N) that most accurately describes the contractor’s performance or situation. PLEASE PROVIDE A NARRATIVE EXPLANATION FOR ANY RATINGS OF M or U.

E
G
S
M
U
N
Exceptional
Good
Satisfactory
Marginal
Unsatisfactory
Neutral

Performance meets contractual requirements with many exceeded to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with no more than a few minor problems for which corrective actions taken by the contractor were highly effective.

Performance meets contractual requirements with some exceeded to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with no more than some minor problems for which corrective actions taken by the contractor were effective.

Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor were satisfactory.

Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

Performance was not observed or not applicable to the current effort being reported against.

CONTRACTOR’S NAME: _______________ CONTRACT NUMBER: _______________

Place an “X” in the appropriate column using the definitions matrix above.

The contractor:
E
G
S
M
U
N
1.
Provided experienced managers and supervisors with the technical and administrative abilities needed to meet contract requirements.
2.
Demonstrated ability to hire, maintain, and replace, if necessary, qualified personnel during the contract period.
3.
Delegated authority to project managers and supervisors commensurate with contract requirements.
4.
Home office participated in solving significant local problems.
5.
Followed approved quality control plan.
6.
Provided effective quality control and/or inspection procedures to meet contract requirements.
7.
Corrected deficiencies in timely manner and pursuant to their quality control procedures.
8.
Provided timely resolution of contract discrepancies.
9.
Identified problems as they occurred.
10.
Suggested alternative approaches to problems.
11.
Displayed initiative to solve problems.
12.
Developed realistic progress schedules.
13.
Met established project schedules.
14.
Provided timely resolution of warranty defects.
15.
Was responsive to contract changes.
16.
Provided adequate project supervision.
17.
Obtained consent of surety for increases in bonding as work-in-progress increased.
18.
Paid subcontractors/suppliers in a timely manner.
19.
Provided accurate and complete line item cost proposals including all aspects of work required for each task.
20.
Cooperated with Government personnel after award.
21.
How would you rate the contractor's overall performance?
22.
Was the contractor ever issued a cure or show cause notice under the referenced contract? If yes, explain outcome in “remarks.”
YES/NO
23.
Would you award another contract to this contractor? If not, explain in “remarks.”
YES/NO
24.
Is the contractor rated in CPARS?
YES/NO

CONTRACTOR’S NAME: ___________________ CONTRACT NUMBER __________

Remarks:________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ _________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________