FA4427-11-R-0103 Asbestos & Lead based Abatement
December 27, 2011 Page 1 of 1
FA4427-11-R-0103 QUESTIONS and ANSWERS #3 Asbestos/Lead Paint Abatement
Questions and answers received as of 27 December 2011
1. QUESTION: Please verify that you will only evaluate past performance of subcontractors we enter into an agreement with for this project or is this agreement just consent to disclose past performance information.
ANSWER: Follow instructions in section L proposal submission. Subcontractor agreement is not the same thing as subcontractor consent. Both agreement and consent are required to be submitted if subcontractor Past Performance Questionnaire is to be considered in the evaluation rating.